HomeMy WebLinkAbout8.1 VHSCommunityGym DUSD .. . It - DUBLIN CITY COUNCIL DUBLIN UNIFIED SCHOOL DISTRICT BOARD OF TRUSTEES AGENDA STATEMENT JOINT MEETING DATE: July 25, 1995 SUBJECT: Proposed Valley High School Community G~ium . . Prepared by: Diane Lowart, Parks & Commumty ServIces DIrector Jeanne Howland, Assistant Superintendent - Business EXIllBITS ATTACHED: . Community Facilities Task Force Summary A model of the proposed gymnasium will be presented at the meeting . RECOMMENDATION: 1. 2. 3. 4. 5. Receive presentations from Staff and the Architect Receive public comment City Council/School Board deliberation Approve the conceptual terms for the joint development of the Valley High School Community Gymnasium Direct City and District Staff to prepare a draft agreement for consideration by each agency's legislative body FINANCIAL STATEMENT: Estimated Capital Cost: Estimated Annual Operating Cost: $ 2,080,000 $ 71,538 DESCRIPTION: The Liaison Committee of the Dublin City Council and the Dublin Unified School District Board of Trustees has developed a proposal for a community gymnasium at Valley High School for consideration by the entire City Council and Board of Trustees. Background At the November 14, 1994 and December 12, 1994 meetings of the Dublin City Council, Dublin resident Betsy Chapman addressed the Council on the need for additional gymnasiums in the City. Ms. Chapman indicated that the lack of gym space puts Dublin athletic teams at a disadvantage and stated that a petition was being circulated to generate community support for additional gymnasiums. In addition to addressing the City Council on this issue, Ms. Chapman also addressed the City's Parks and Community Services Commission on December 13, 1994 and the School District Board of Trustees on December 21, 1994. As a result of these requests, and given the need to make revisions to the Agreement Between the City and the District Regarding Use of Facilities, the City Council approved formation of the Community Facilities Task Force on February 13, 1995. The purpose of the Task Force was "to study, report and make recommendations on community facility needs in Dublin for both school and community use". The Community Facilities Task Force was made up of five at-large community members appointed by the Mayor, with the approval of the City Council, along with representatives from the following groups: Citv R~presentatives Parks & Community Services Commissioner (1) School Site Representatives Dublin High School (8) Murray School (1) Valley High School (1) Wells Middle School (2) Community Repr:esentatives Children's Theatre Workshop (1) Dublin Little league (1) Dublin United Soccer league (1) South Valley Youth Football (1) St. Raymond's CYO Basketball (1) Arroyo Vista (2) Additionally, Staff from both the City and School District participated in the meetings of the Task Force. --------------------------------------------------------------------------- ITEMNO.4L COPIES TO: Dublin Unified School District Parks & Community Services Commission Community Facilities Task Force CITY CLERK ,FILE ~ . . e e Following a series of meetings where the Task Force considered the major facility needs of the community and the schools, the following recommendations (shown in order of priority) were presented to the City Council/School Board Liaison Committee: 1. Pursue expansion of the Valley High School Gymnasium/Multi-purpose Room to accommodate community use. a) 10,000 s.f. gymnasium with wood floor b) bleacher seating for up to 400 c) restroom/changing facilities (no lockers or showers) 2. Pursue development of the Dublin Elementary School field area to accommodate community use (field layout would be geared to accommodate youth basebalVsoftball and youth football). a) 3 - 60' baseball fields (upgraded to game quality) b) 1 - full size soccer field c) Play Area with play equipment, benches, picnic tables .an.d[Qr asphalt area for roller hockey. d) Outdoor restroom/snackbar facility 3. Pursue renovation of Frederiksen Elementary School field area to accommodate community use for youth/adult soccer. 4. Pursue renovation of Nielsen Elementary School field area to accommodate community use as a practice site for youth baseball/softball and youth soccer. Expansion of the Valley High School Gymnasium/Multi-purpose Room was the number one priority of the Community Facilities Task Force. Given that the District is currently masterplanning the Valley High SchoollW ells Middle School site, the timing for implementation of this recommendation is crucial. The development of the Dublin Elementary School field area was also viewed as a high priority by the Task Force but they agreed that implementation of this recommendation could not move forward until a decision is made regarding the possible re-opening of Dublin Elementary. Attached is a detailed summary of the actions of the Community Facilities Task Force. Proposed Community Gymnasium As stated previously, the top priority of the Community Facilities Task Force was construction of a community gymnasium to meet the growing needs of organized sports leagues sponsored by the City as well as local community groups. Although there are currently two gymnasiums in the City of Dublin (Dublin High School and Wells Middle School), City and community groups are competing for gymnasium space with school sponsored programs. This competition for limited gym space has created conflict between school athletic teams, between individual schools, and between school programs and City/community programs. The Community Facilities Task Force considered possible locations for an additional gymnasium and determined that the proposed multi-purpose room identified in the preliminary masterplan for Valley High School could be enlarged to meet the needs of the community. Since Valley High School seldom needs to utilize the gymnasium afterschool, at night or on weekends, the gymnasium could be available for community use during the peak use periods. At present, the Valley High School site consists of three buildings; two which are used by the High School and one which is leased to a Montessori School. As proposed in the preliminary master plan for Valley High School, two of the buildings would be renovated and one of the buildings would be completely rebuilt. The new building would include offices and workrooms for school personnel, a kitchen, a community room and a multi-purpose room/gymnasium. To meet the needs of the community, the size of the proposed multi-purpose room/gymnasium would be increased from 6,000 s.f. to approximately 10,000 s.f. The gymnasium would be able to accommodate one a full size basketball court (84' x 50'), two half-court basketball courts (74' x 42), one full size volleyball court (60'x30') and two half-court volleyball courts. In addition, the gym would include bleacher seating for up to 400 and storage areas for both school and City use. Also, it is proposed that the kitchen would be modified in order to accommodate a concession area and that the restrooms would be enlarged to provide a changing area. I .T. . . e e The estimated capital cost for construction of the proposed gymnasium and related facilities is $2,080,000. The estimated annual cost for maintenance, utilities and supervision of the gymnasium and related facilities is $71,538. A breakdown of the costs are shown below. (S1.!.J2QJx and Utility Costs are based upon actual annual costs at Wells and Dublin High pro-rated on a combined square foot basis for both sites) Salary: $13.11/hr. Retirement: .55/hr. (PERS - 4.17%) FICA: .81/hr. (6.2%) Medicare: .19/hr. (1.45%) SUI: .04/hr. (.32%) Worker' Comp: .14/hr. (1.0324%) Fringe: 2.63/hr. Total: $17.47/hr. x 1,149 hrs./yr. (Mon.-Fri., 4 hrs.lday; Sat./Sun., 2 hrs.lday; 11 mos./year) $ 15,087 expensel230,698 sq. ft. = $0.065/sq. ft. X 11,105 sq. ft. $355,418 expense/230,698 sq. ft. = $1.54 /sq. ft. X 11,105 sq. ft. Maintenance: Annual Repair and Replacement Set Aside Subtotal: Indirect Cost Rate: DUSO's State Approved 1993/94 Actual Indirect Cost Rate (7.52%) Total Annual Operational Costs: Facility Usage Calculation: Facility available 13 hours [9:00 a.m. to 10:00 p.m.] per dayl7 days per week = 91 hrs./wk School Use: 6 hours per day [9:00 a.m. to 3:00 p.m.] x 5 days per week = 30 hrs./wk City Use: 7 hours per day [3:00 p.m. to 10:00 p.m.] x 5 days per week 13 hours per day [9:00 a.m. to 10:00 p.m.] x 2 days per week = 61 hrs.lwk Operational Cost Proration: School Use: 30 hrs./wk. = 33% x $46,123 = $15,221 Projected Annual Expense City Use: 61 hrs.lwk. = 67% x $46,123 = $30,902 Projected Annual Expense Preliminary Supervision Costs Gym Attendant: Salary: $7.50/hr. FICA: $ .47/hr. (.0620) Medicare: $ .11/hr. (.0145) Workers' Comp: $ .60/hr. (.0789) Total: $8.68/hr. x 2,928 hrs./yr. (based on total available hours for City/community use) Summary of Operational and Supervision Costs Operational: Custodian Supplies Utilities Maintenance Indirect Costs Subtotal Operational: Supervision: Gym Attendant Subtotal Supervision: Preliminary Conceptual Bud.get. Capital Construction Costs Total Project City Portion of Project* District Portion of Project 16,000 s.f. x $130/s.f. = $2,080,000 5,500 s.f. x $130/s.f. = $ 715,000 10,500 s.f. x $130/s.f. = $1,365,000 * Increase size of gym floor; provide storage for City functions; increase size of lobby; increase size of restroom, janitorial and mechanical.lelectrical spaces. Preliminary Operational Costs Square Footage of Proposed Facility: Gym: Office/Storage: Bathrooms: Kitchen: Total: 10,000 sq. ft. 550 sq. ft. 380 sq. ft. 175 sq. ft. 11,105 sq. ft. Custodian: Supplies: Utilities: TOTAL: $20,073 722 17,102 5,000 3.226 $46, 123 $25.415 $25.415 $71,538 = $ 20,073 = $ 722 = $17,102 = $ 5.000 $ 42,897 = $ 3.226 $ 46,123 = $ 25,415 . . e e Proposed Agreement The City Council/School Board Liaison Committee has given conceptual approval for the proposed community gymnasium at Valley High School and has discussed potential terms for an agreement between the City and the District as follows. District Re$ponsibilities 1. District would fund 100% of capital construction cost (including design, inspection, permits, etc.). 2. District would maintain building including interior and exterior surfaces, electrical and mechanical systems, roof, plumbing, etc. at no cost to City. 3. District would guarantee City/community use as follows: Monday-Friday from 3:00 p.m. to 10:00 p.m. and Saturday/Sunday from 9:00 a.m. to 10:00 p.m. (District could reserve facility for District related functions six times per year to be scheduled at the beginning of each school year.) Citv Responsibilities 1. City would reimburse District for 100% of the annual operating cost (including custodian, supplies, utilities and annual repair and replacement set aside). 2. City would reimburse District for expenses related to the repair and maintenance of gym furnishings (Le. bleachers, backboards, scoreboards, floor surfaces, etc.) and would reimburse District for any damages to the interior of the facility incurred during the times of City/community use. 3. City would schedule City/community use and provide qualified supervision during times of City/community use at no cost to District. 4. City would make facility available for District related functions six times per year to be scheduled at the beginning of each school year. 5. City would levy, collect and retain all facility use fees for City/community use of the proposed community gymnasium (all fee schedules would be approved by District). As discussed by the Liaison Committee, the terms of the proposed agreement would be for a period of ten years with an option to renew the agreement for additional five year increments. For the first three years of the agreement, an annual review would be undertaken; after three years, a biennial review would be undertaken for the remainder of the agreement. In addition to the aforementioned terms regarding the construction and operation of the proposed community gymnasium, the Liaison Committee discussed and recommended that the City make the Dublin Swim Center available to the District from February through May of each year for the purpose of conducting swim team programs, swimming instruction and other appropriate aquatic programs at no cost to the District. As proposed, this would b~ effective at the time that construction of the gymnasium is complete and is available for use by the community. The current Agreement Between the City and the District Regarding Use of Facilities provides that the District will reimburse the City for one-third of the actual operating cost of the Swim Center and 100% of the cost of supervision. Over the past five years, this has amounted to approximately $6,250 per year. It should be noted that if Dublin High School was not utilizing the Dublin Swim Center during the spring months, the City would not need to open the facility until Memorial Day weekend. Consequently, the actual cost to the City to open the Dublin Swim Center for use by Dublin High School during the months of February through May is approximately $20,000. Conclusion The proposed community gymnasium at Valley High School has received the support of the Community Facilities Task Force, the City's Parks and Community Services Commission and the City/District Liaison Committee. In the case of the City's Parks and Community Services Commission, the Commission conducted a special meeting to review the proposed design for the gymnasium and provided Staff and the Architect with recommendations that will be incorporated to the final design of the facility. Like the Community Facilities Task Force, the Parks and Community Services Commission also views the Valley High School Community Gymnasium as it's top priority. . . . . e e The Valley High School Community Gymnasium will not only serve the needs of the Valley High students, but will also meet the growing needs of organized sports leagues sponsored by the City and the community, as well as alleviate the overcrowding of the District's other gymnasiums. The proposed project and resulting agreement represent another example of the cooperation between the City and the School District which, ultimately, benefits the residents of Dublin. Therefore, it is recommended that the City Council of the City of Dublin and the Board of Trustees of the Dublin Unified School District take the following action: 1. 2. 3. 4. Receive presentation from Staff and the District Architect Receive Public Comment Approve the conceptual terms for the joint development of the Valley High School Community Gymnasium Direct City and District Staff to prepare a draft agreement for consideration by each agency~s legislative body. . . e e COMMUNITY FACILITIES TASK FORCE SUMMARY BACKGROUND Formation of the Community Facilities Task Force was approved in February of 1995. The purpose of the Task Force was "to study, report and make recommendations on community facility needs in Dublin for both school and community use". The Task Force was comprised of representatives from the following groups: 1. City Representatives a) Parks & Community Services Commissioner 2. School Site Re.,presentatives a) Dublin High School - 8 b) Frederiksen School - 0 c) Murray School - 1 d) Nielsen School - 0 e) Valley High School - 1 f) Wells Middle School - 2 3. Community Groups/Organizations a) Children's Theatre Workshop - 1 b) Dublin Little League - 1 c) Dublin United Soccer League - 1 d) South Valley Youth Football- 1 e) St. Raymond's CYO Basketball- 1 f) Arroyo Vista - 2 4. Community At Larlle - 5 TASK FORCE MEETINGS The Community Facilities Task Force met on three separate occasions: March 28, April 13 and May 11, 1995. The meetings were open to the public and there were several members of the public in attendance at each meeting. The results of each meeting are summarized below: March 28~ 1995 The Task Force was presented with background information regarding the history of the Agreement Between the City and the School District Regarding Use of Facilities. In addition, previously identified joint City/District improvement projects were reviewed including completed projects (DHS Football Stadium, Frederiksen Kindergarten Tot Lot, Murray 90' Baseball Field, and Nielsen and Cronin Play Areas), projects undertaken by the School District (DHS Athletic Field Renovation, Phases 1 and 2, and DHS Tennis Court Renovation) and projects which have not yet been undertaken (Athletic Field Renovations at Frederiksen, Murray, Nielsen and Wells Schools as well as the Athletic Field and Play Area Renovation for Dublin Elementary School). e e Task Force Members were then divided into small groups to brainstorm on what the current facility needs are in reference to school and community groups. The needs were ranked in order of importance and each group identified five top facility needs. The entire group then reviewed the individual group lists and rated each facility need. The result was a list of five top facility needs as shown below. Overall Ranking of Top Five Gym(s) & Staff Gyms - Expand or Build Multi-Purpose Gymnasium Double Gym Elementary School Fields - SB, BB, Soccer, Basket, Tennis Additional Sports Fields School Sports Field Renovation Youth Center CTW at Wells' Performing Arts/Auditorium Auditorium Dublin Little Theatre/New Auditorium Teen Center Teen Center/Community Recreation Center All Weather Track All Weather Track (DHS) Lighted Fields (Existing & New) Dublin Sports Grounds - Drainage, Leveling Increase Accessibility of Existing Facilities Meeting Space For Community Groups Top Five - By Facility 'lype Gymnasium Sports Fields Theatre/Auditorium Teen/Y outh Center All Weather Track April 13. 1995 Rating 20 18 18 17 17 16 14 13 13 12 11 11 11 09 09 08 07 06 05 05 Rating 73 60 47 33 13 At this meeting the Task Force Members once again confirmed the top five facility needs and agreed to defer consideration of the Theatre/Auditorium to the Wells Middle Master Plan Study Committee, the Teen/Youth Center to the Teen Task Force and the All Weather Track to the Dublin High School Master Plan Study Committee. Task Force members were then divided into two groups to meet with the District's Architect to discuss gymnasium needs and the District's Landscape Architect to discuss sports fields needs. 2 , . e e The gymnasium group reviewed the proposed masterplan for the Wells Middle SchoollV alley High School site which identifies an additional multi-purpose room/cafeteria at Wells Middle School and a gymnasium/multi-purpose room at Valley High School. Additionally, the Task Force discussed the potential for an additional gymnasium at Dublin High School. It was the consensus of the Task Force that the multi-purpose/gymnasium facility identified for construction at Valley High School should be expanded to meet the gymnasium needs of the community. The basis for this recommendation stemmed from the fact that the programs at Valley High School are typically limited to school hours and that they would have little use for the gym in the evenings and on weekends. The potential new gymnasium at Dublin High School was also considered but it was determined that the needs of the High School sports programs would preclude use by the community. The sports fields group reviewed the athletic field potential at Dublin Elementary, Frederiksen, Murray, Nielsen and Wells Schools. They learned that the Murray fields would be renovated during the upcoming summer and reviewed the proposed field layout as identified in the W ellsN alley masterplan. It was agreed that the Dublin Elementary site has the greatest amount of available land and asked the Landscape Architect to develop field alternatives. May 11~ 1995 The Task Force received presentations from both the District's Architect and Landscape Architect regarding conceptual plans for a community gymnasium at Valley High School and a ball field layout plan for Dublin Elementary School. The proposed community gymnasium at Valley High School would be approximately 10,000 square feet with bleacher seating for up to 400. The gymnasium would have a wood floor and be sized to include a full-size basketball court as well as two half-size courts. Restrooms, storage, a community meeting room and a cafeteria/snack bar would be made available for community use in the proposed plan. The Task Force was generally in agreement with the plan but stressed the need for adequate space in the restrooms for a changing area. Three alternate plans for field placement at Dublin Elementary were reviewed. The recommended plan included three 60' baseball diamonds, a full size soccer field and a play area. Additionally the Task Force stressed the need for outdoor restroom facilities, a snackbar and possibly lighting. However, the Landscape Architect discouraged lighting of the fields due to the proximity of the fields to the adjacent residences. RECOMMENDATIONS (Shown in priority order) 1. Pursue expansion of the Valley High School Gymnasium/Multi-purpose Room to accommodate community use. a) 10,000 s.f. gymnasium with wood floor b) bleacher seating for up to 400 c) restroom/changing facilities (no lockers or showers) 3 ."' . e e Given the fact that Valley High School would seldom need the gymnasium/multi-purpose room on evenings and weekends, it was determined that this site would best serve the needs of community sports groups. However, the Task Force felt strongly that scheduling of the facility needed to coordinated in such a way that community use was given priority for evening and weekend hours. 2. Pursue development of the Dublin Elementary School field area to accommodate community use (field layout would be geared to accommodate youth baseball/softball and youth football). a) 3 - 60' baseball fields (upgraded to game quality) b) 1 - full size soccer field c) Play Area with play equipment, benches, picnic tables and/or asphalt area for roller hockey. d) Outdoor restroom/snackbar facility The Task Force understands that this plan could not move forward until a decision is made regarding the possible re-opening of Dublin Elementary as this could affect the ultimate use and layout of the field areas. 3. Pursue renovation of Frederiksen Elementary School field area to accommodate community use for youth/adult soccer. The Task Force felt that this site could be best utilized as a back-up facility for youth/adult soccer games and tournaments as well as a practice site for youth/adult soccer and youth baseball/softball. 4. Pursue renovation of Nielsen Elementary School field area to accommodate community use as a practice site for youth baseball/softball and youth soccer. Given the limited potential of this site due to the size of the field area, the Task Force felt that this site could only accommodate team practices. Additionally, the Community Facilities Task Force urged the City to pursue needed renovations to the Dublin Sports Grounds and asked that additional ball field lighting be considered. It was also recommended that the Dublin Sports Grounds renovation be phased around the Dublin High School athletic field renovations so as not to have all of the fields closed to the community at the same time. 4