Loading...
HomeMy WebLinkAbout4.08 Advertise For Bids91-8 CITY OF DUBLIN AGENDA STATEMENT CITY COUNCIL MEETING DATE: October 28, 1991 SUBJECT: Authorization to Solicit Bids - Contract 91-08 Senior Center Vinyl Floor Replacement Report by Public Works Director Lee Thompson EXHIBITS ATTACHED: A copy of the project specifications will be available at the City Council meeting. RECOMMENDATION: Authorize Staff to solicit bids. Authorize an additional appropriation in the amount of $2,203.00 to this project from additional 1991-92 CDBG revenues. FINANCIAL STATEMENT: This project is funded entirely by Community Development Block Grant (CDBG) monies. The total budget and expenditures to date for this project are as follows: Fiscal Year 1990-91 Fiscal Year 1991-92 Budget: $ 9,400.00 $ 19,725.00 E__g_penditures to Date: Water Heaters: 5,136.00 New Range: 2,061.38 Painting: 1,945.00 $ 7,197.38 $ 1,945.00 Estimated Costs: Contract 91-08 Floor Replacement HVAC repairs: 15,000.00 3,100.00 $ 20,045.00 Total estimated expenditures for both years: $ 27,242.~8 Total CDBG grant monies available: $29,125.00 This leaves an estimated remaining balance of $1,882.62 which may be used for needed roof gutter and overhang repairs. Preliminary estimates on this work indicate that the cost for both would be approximately $2,800 to $3,000. Only $7,197.38 of the budgeted $9,400 was used in FY 1990-91, leaving an unused balance of $2,202.62. In order to take advantage of the entire grant, an additional appropriation in that amount is necessary for Fiscal Year 1991-92. The CDBG grant will reimburse the City up to $29,125.00 as the monies are expended. Staff recommends that an additional appropriation up to the grant amount be approved at this time but that a decision on any additional expenditures be delayed until the firm costs of the floor and HVAC work are known. DESCRIPTION: This contract provides for replacement of the vinyl floors in the social hall and kitchen at the Dublin Senior Center as part of the Senior Center Kitchen Upgrade Capital Improvement Project. I CITY CLERK ITEM NO. COPIES TO: I I;Iolo It is proposed to replace the existing social hall flooring with new vinyl tile and to replace the kitchen floor with coved sheet vinyl as required by the Alameda County Health Department. The project includes removal of the existing floor coverings, and surface preparation and crack patching of the existing concrete floors as necessary prior to installation of the new flooring. The total Capital Improvement Project includes replacement of the kitchen range and water heaters and some painting, which has already been accomplished, and some minor repairs to the roof gutters and repair of the deteriorated overhang near the entrance to the building. Additionally, problems with the building's heating and air conditioning systems have surfaced and must be corrected. Since different phases of the project involve entirely separate trades, Staff felt that each phase should be a separate contract or purchase order. The CDBG grant will cover any of this work up to the allotted amount. If the HVAC, roof gutter, and overhang repairs cannot all be accomplished within the remaining grant funds, Staff will return to the City Council for a decision regarding an additional budget transfer. The HVAC repair is the most important, followed by the overhang and then the roof gutters. It is recommended that the City Council authorize Staff to solicit bids for Contract 91-08 Senior Center Vinyl Floor Replacement and authorize a budget transfer in the amount of $2,203 to this project from unallocated reserves. ~ a:(bldspecs)~senior~agstbid - 2 -