HomeMy WebLinkAbout4.12 Park Furn Replacement CITY CLERK File # D~[Q][Q]-~l5J AGENDA STATEMENT CITY COUNCIL MEETING DATE: July 15, 2008 SUBJECT: ATTACHMENTS: RECOMMENDATION: ~. FINANCIAL STATEMENT: Park Furniture Replacement - Contract No. 08-04, Change Order #1 Report Prepared by Rosemary Alex, Parks and Facilities Development Coordinator 1) Proposed Change Order # 1 2) Budget Change Form 1) Approve Change Order # 1 2) Approve Budget Change Original Contract Amount Proposed Change Order # 1 Total 10% Contingency for Construction Total Budget for Construction $61,575.75 $81,490.00 $143,065.75 $14,306.57 $157,373.00 Project Budget (FY 07/08) Project Budget (FY 08/09) Total Project Budget Amount Required to Approve Change Order # 1 $67,734.00 $77,000.00 $144,734.00 $12,639.00 DESCRIPTION: The Park Furniture Replacement Project was approved as part of the 2008-2013 Capital Improvement Program. The intent of the project is to replace existing picnic tables, benches and trash receptacles with new furniture consisting of recycled plastic and metal components. The project extends over four fiscal years at the following locations: 1) 2) 3) 4) 5) Dolan Park Alamo Creek Park Stagecoach Park Shannon Park Kolb Park Completed FY 2005-2006 Completed FY 2006-2007 Completed FY 2006-2007 FY 2007-2008 FY 2008-2009 COPY TO: MAK. Associates, Incorporated ------------------------------------------------------------------------------------------------------------- Page 1 of2 ITEM NO. 5./2.. G:\COUNCILlAgenda Statements\2008\7-15 Park Furniture CO Report.doc On March 18, 2008 the City Council authorized Staff to solicit bids for furniture replacement at Shannon Park and subsequently awarded the contract to M.A.K. Associates, Incorporated on May 6, 2008. In an effort to garner improved pricing by increasing the furniture purchase, Kolb Park was included as an additive bid item. At its meeting of June 26, 2008 the Dublin City Council adopted the Fiscal Year 2008-2009 Budget, which included the replacement of furniture at Kolb Park. In order to proceed with the purchase, a Change Order to the original contract in the amount of $81 ,490 is needed. Approval of the Change Order will allow the contractor to immediately order the equipment with delivery and installation in Fiscal Year 2008-2009. In addition, a budget change is required to cover the difference between the Fiscal Year 2008- 2009 Budget of $77,000 and change order amount of $81 ,490 ($4,490) as well as for the 10% contingency ($8,149). The budget change also includes the carryover amount of $48,093 unspent from Fiscal Year 2007-2008. RECOMMENDATION: Staff recommends that the City Council take the following action: 1. Approve Change Order #1 with M.A.K. Associates Inc. in the amount of$81,490. 2. Approve Budget Change c? ~( ol {Of.. ~ CITY OF DUBLIN CONTRACT CHANGE ORDER NO.1 PROJECT: Park Furniture Replacement Contract No. 08-04 PAGE 1 OF 1 TO: M.A.K. Associates Incorporated AGREEMENT DATED May 6, 2008 between M.A.K. Associates Incorporated and the City of Dublin You are hereby directed to make the herein described changes from the scope of services or do the following described work not included in the scope of services on this contract NOTE: This change order is not effective until allProved bv the City Manager Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price, agreed price and force account Un less otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be madc for idle time. Change requested by: City of Dublin Include Additivc Bid Item #] picnic tables, benches and trash receptacles for Kolb Park (attached hereto). Additional Time: 45 calendar days COST INCREASE: $81,490 SUBMITTED BY: '"d'/'\ ""j _,-: C";<j'--_. )--'i~' "7 I 'I)' <4/ /' Al/t //} / />:/./' ///1:( ,<f ,,' /l~/// A" MeliSEia Morton Dater Pubiic Works Director >' <,;'-,,7 1- _/~ "OV AL RECOjM;NDED BY tJU~t.J4L 7~7/~ Richard C. Ambrose Date City Manager APPROVED BY Janet Lockhart Date Mayor We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, to all terms of this change order, and to provide all equipment and furnish all materials except as may otherwise be noted above, and to perform all services necessary for the work above specified, and to accept as full payment the prices and time extensions shown above for any and all cost and time impacts resulting from this change order. Accepted, Date Contractor: M.A.K. Associates, Incorporated By Title J t~:tf 4' I ;) 7/ r{"! 1Y{ !\~~t(~.q.'i " ATTACHMENT #1 ' DATE: PROJECT NAME: CIP#: CONTRACT NO. CHANGE ORDER NO. PERCENT COMPLETE: CONTRACTOR: CONTRACT AMOUNT: 10% CONTINGENCY AMOUNT FY 2008/2009 BUDGET: CONSTRUCTION BUDGET CHANGE ORDERS AS % OF CONTRACT: CITY OF DUBLIN EXHIBIT "A" CHANGE ORDER FORM 7/15/2008 Park Furniture Replacement 95631 08-04 1 0% M.AK. Associates Incorporated $61,576 $6,157 $77 ,000 $144,733 132% CONTRACT CHANGE ORDERS: CHANGE ORDER #01 Additive Bid Item #1 Kolb Park Furniture CHANGE ORDER #02 CHANGE ORDER #03 CHANGE ORDER #4 CHANGE ORDER #5 CHANGE ORDER #6 CHANGE ORDER #7 CHANGE ORDER #8 CHANGE ORDER #9 CHANGE ORDER #10 CHANGE ORDER #11 CHANGE ORDER #12 CHANGE ORDER #13 TOTAL OF ALL CURRENT AND PRIOR CHANGE ORDERS: ADJUSTED CONTRACT AMOUNT: REMAINING CONTINGENCY PROGRESS PAYMENTS MADE: PAYMENT #01 PAYMENT #02 PAYMENT #03 PAYMENT #04 PAYMENT #05 PAYMENT #06 PAYMENT #07 PAYMENT #08 PAYMENT #09 TOTAL ACTUAL PAYMENTS: ADJUSTED TOTAL CONTRACT: REMAINING BALANCE ON CONTRACT: RECOMMENDA TION: SIGNATURE: APPROVED DENIED , .I j/iC;i%,P ;;/ SuperVising Dept. Head.. ,J','::" ")";'."- L I 1'-- ,'i.',:/ .F AMOUNT 81,490.00 81,490.00 APPROVED DENIED v ~ J'l~\~~(li City Manager $81,490.00 $143,065.75 $ $143,065.75 $143,065.75 APPROVED DENIED c? Gj.,lf Mayor 30jA PROPOSAL TO THE CITY OF DUBLIN FOR THE CONSTRUCTION PROJECT ENTITLED PARK FURNITURE REPLACEMENT CONTRACT NO. 08-04 NAME OF BIDDER: h', ". BUSINESS ADDRESS: y' ,/j"\c J"AJ' / // Cd.":.~; ;1- frfC./";t ' ~::::~~',~,.. t j' { r\ '-; t~/:"~>-" k:.. e,l~ .~. "-, i'.' t_'1'~_'/-- l.I-.i ? ;' -r-;..:"r~ TELEPHONE NO. 1~;;r /J; :.../ ,-,' 7_,:~!,rLfr ""- (.,1 :t..~ '-/ i~~.," : '.,_ t" ___ _ .._. The work for which this proposal is submitted is for construction in accordance with the special provisions (including the payment of not less than the minimum wage rates) and the contract annexed hereto, the project specifications described below, and also in accordance with the Department of Industrial Relations - General Prevailing Wage Rates in effect on the date the work is accomplished. Price shall be a lump sum for the project as identified in the specification, appendix, and plan sheets. The price bid shall include all material and labor needed to provide a complete and functional installation as provided in the Specification. The undersigned, as Bidder, declares that the only persons or parties interested in this proposal as principals are those named herein; that this proposal is made without collusion with any other person, firm, or corporation; that he has carefully examined the location of the proposed work, the annexed proposed form of contract, and the plans therein referred to; and he proposes and agrees if this proposal is accepted that he will contract with the City of Dublin in the form of the scope of the contract annexed hereto, to provide all necessary machinery, tools, apparatus, and other means of construction, and to do all the work and furnish all the materials specified in the contract, in the manner and time therein prescribed, and according to the requirements of the Engineer as therein set forth, and that he will take in full payment therefor the following lump sum price, to wit: Total Base Bid:. ($ , , r-.~ ,-f~, /'''1 . I': ..-. ""0'" .. ........... -~ ".... ~ ;._- ~,'-- ~ c,",\!- ""'"'~t-i.--'t .~ "'_"l-.-~ -."" ..... ) '>.",' i! ;.;( ,.-4.,-~"",,,z:,!t,..,~'t~~ c""__~'\,f("'{ -"~ ,,/~ -Y' ".J'S"l t \';' 'L (i'- ,... ( .,.:."",,-~~~.. dollars Additive Bid Items Additive Bid Item #1: Add Park Furniture for Kolb Park ",; Ie. i",'l-' 1 '..J, .e A':t;, i.., .. Total Additive Bid Item #1: ~'~'~'\iL,..,i n'~l"'-r-'_,,~-----"< i dollars ($ ~-:11 t:..-{Cj('i.'..... ,,",.. ill,_' l_ I Total Base Bid and Additive Bid Item #1 :; l;,;:.4,"-~ ^~.,;#< -1- 'l';I"." dollars '" "'; t-:_.~ ".~: .~ ($ i ._, J ClCj-'1~ ) f Page P-1 BUDGET CHANGE FORM CHANGE FORM # Lf:iLf New Appropriations (City Council Approval Required): Budget Transfers: xxx From Un-appropriated Reserves From Budgeted Contingent Reserve (1080-799.000) Within Same Department Activity Between Departments (City Council Approval Required) Other From New Revenues DECREASE BUDGET ACCOUNT AMOUNT INCREASE BUDGET ACCOUNT AMOUNT Name: Name: MEASURE D FUNDI $ 60,732 PARK FURNlTURE REPLACEMENT CIPI CAPITAL IMPROVEMENTS Account #: Account #: 224.9563] .750.050 Name: Name: Account #: Account #: Name: Name: Account #: Account #: Name: Name: Account #: Account #: REASON FOR BUDGET CHANGE ENTRY: On March 18, 2008 the City awarded the contract to M.A.K & Associates for the Park Furniture replacement project. The proposed contract to include Ko1b Park as an additive bid item is $143,066 plus 10% contingency is $157,373. This budget adjustment provides an additional funding of $12,639 to include Kolb Park and a carryover of the fiscal year 2007-2008 budget balance of $48,093 unspent at June 30, 2008. There is $77,000 provided in the fiscal year 2008-2009 adopted CIP project. Funding is available in the Measure D Recycling fund. Fin Mgr/ASD: f~~-."i' .__ /,.,( --"{:7j~:~\,) , k~, _ It.... _' Y~_______, .://-/ / ) Date: .~ \. . -Signature r I.. "- Ii.... "".. ..... f't'.. Signature City Manager: r"~". .,r J.. .;:t:.,t..",,1'" -;..1 -"I !~. D Date: !i.. " L'", As Approved at the City Council Meeting on 07/15/2008 Mayor: Date: Signature Posted By: Date: Signature A~rnY11- ~