2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
94520 Tri-Valley Triangle Study STREETS
DESCRIPTION - LOCATION
The purpose of the Tri-Valley Triangle Study is to develop a sequencing strategy for improvements identified in the
Alameda Countywide Transportation Plan for the. 1-580, 1-680, and Route 84 corridors. Since needed improvements
for these corridors are underfunded, consensus on critical projects is essential.
COMMENTS
In partnership with the Congestion Management Agency, Livermore, and Pleasanton, the City will contribute up to a
maximum of $58,500 to the Triangle Study's completion.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection 001 $ 58,500 $ 58,500
Other Contract Services $ 58,500
Land I Right of Way
Improvements
Machinery I Equipment
Miscellaneous
TOTAL $ 58,500 $ 58,500 $ 58,500
PROJECT I STAFF
MANAGEMENT (FTE) CONTRACT
-59-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96010 Dublin Boulevard Improvements - STREETS
SilverQate Drive to Hansen Drive
DESCRIPTION - LOCATION
e
COMMENTS
This project will widen Dublin Boulevard between
Silvergate Drive and Hansen Drive from two to four
lanes and realign the Dublin Boulevard/Silvergate
intersection into a standard ''I intersection. This
widening will take place on the south side of the street
where there is sufficient right-of-way to make these
improvements. In addition, the project will repair the
existing roadway section, which is creeping due to soil
instability. A traffic signal will be installed at the
intersection of Dublin Boulevard/Silvergate Drive.
The addition of new residential projects and expansion of the Valley Christian Church/School require the widening of
Dublin Boulevard from two to four lanes between Silvergate Drive and Hansen Drive. In 1992, an initial phase of the
work realigned the Dublin Boulevard/Silvergate Drive intersection through restriping and pavement modifications.
The developers of the Valley Christian Center, Hansen Hill, California Highland and Schaefer Ranch projects are
obligated to share the costs of this project, based on their proportionate generation of traffic. To date, developer fees
in the amount of approximately $720,000 have been expended to construct portions of the project, including the
installation of a traffic signal at the intersection of Dublin Boulevard and Hansen Drive, the widening of Dublin
Boulevard just west of Hansen Drive and the modification of a private driveway south of the intersection to align with
Hansen Drive due to the signalization of the intersection.
The final phase of the project will widen Dublin Boulevard to Silvergate Drive. For the purposes of this CIP, the
estimated cost of this phase is approximately $2,740,000; however, it is assumed that the Schaefer Ranch
development will perform the actual construction of the final phase of the project as a condition of the project's
Development Agreement. Under this scenario, any unspent development fees that have been collected by the City
will be contributed toward the project's construction. As of June 30, 2005, $43,289 remains in the fees collected to
fund the final phase of this project.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 543.432 300 $ 719.976 $ 2,741,259 $ 3.461,235
Other Contract Services 159,910
Land I Right of Way'
Improvements 2,742,860
Machinery I Equipment
Miscellaneous 15,033
TOTAL $ 3,461,235 $ 719,976 $ 2,741,259 $ 3,461,235
PROJECT 1 STAFF 0.44
MANAGEMENTIFTEj CONTRACT 0.35
-60-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96061 Street Light Pole Replacement STREETS
DESCRIPTION - LOCATION
This project provides a phased replacement program for older street light poles which have become corroded. The
project began in Fiscal Year 2002-2003, and was originally proposed to take five to six years to complete. The
project was accelerated in 2004-2005, and is now expected to be complete in four years. This will be the final year of
the replacement project, with 117 poles remaining to be replaced in 2005-2006.
COMMENTS
The City has experienced pole failures in areas of the City where street light poles are in excess of 40 years old.
This is proposed to be the final year of a four-year plan to replace approximately 363 poles. The cost of the program
was borne by the Citywide Street Light Assessment District and by the General Fund. The District could only pay for
future years if the City conducted a District-wide election to increase the street light assessment.
The original ungalvanized steel poles would be replaced with galvanized steel, which have a longer life span.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design ¡Inspection $ 6,194 001 $ 215,368 $ 129,370 $ 344,738
Other Contract Services 710 $ 109,982 75,000 184,982
Land ¡ Right of Way
Improvements 522,743
Machinery ¡ Equipment
Miscellaneous 783
TOTAL $ 529,720 $ 109,982 $ 215,368 $ 204,370 $ 529,720
PROJECT I STAFF
MANAGEMENT (FTE) CONTRACT
-61-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER
96082
PROJECT DESCRIPTION
Underground Utilities - Dublin Boulevardl
Dou he Road Intersection and Vicini
ACTIVITY
STREETS
DESCRIPTION - LOCATION
e
This project would underground existing overhead
utilities along Dougherty Road between Sierra Lane
and Dublin Boulevard as well as a portion of Dublin
Boulevard between Dublin Court and Dougherty
Road and Scarlett Court from Dublin Boulevard to
560 feet south of Dublin Boulevard.
-
1
,-
,-
~\'t__-
\ "" \. .,-...,..---
C \ "t .,._,.....
COMMENTS
The undergrounding of existing overhead utilities along portions of Dougherty Road, Dublin Boulevard and Scarlett
Court near the Dublin Boulevard and Dougherty Road intersection would be completed prior to the Dougherty Road
Improvements - Houston Place to 1-580 capital project. The majority of funds expended under this project will be
reimbursed with Public Utility Commission (PUC) Rule 20A funds collected by the City, except for costs associated
with Scarlett Court and traffic signal interconnect work. The Rule 20A PUC monies, reimbursements from other
utilities, and developer contributions would pay the City's project costs estimated at $633,857. It is anticipated that
up to $700,000 of Rule 20A funds will be available at the time of construction scheduled in Fiscal Year 2005-2006.
Staff costs associated with this project have been included in CIP #96852 - Dougherty Road - Houston Place to 1-
580.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 44,500 001 $ 44,557 $ 589,300 $ 633,857
Other Contract Services
Land I Right of Way
Improvements 588,000
Machinery I Equipment
Miscellaneous 1,357
TOTAL $ 633,857 $ 44,557 $ 589,300 $ 633,857
PROJECT I STAFF
MANAGEMENTIFTE) CONTRACT
-62-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96380 1-580 & San Ramon Road STREETS
Freeway Interchanae Improvements
DESCRIPTION - LOCATION
e
COMMENTS
This project included the planning, design and
improvements to the 1-580/San Ramon Road/Foothill
Road interchange. The improvements included
removal of the two offramp loops at this interchange
and the installation of direct exits to traffic signals onto
San Ramon Road and Foothill Road. In addition, the
project installed median landscaping and overlay on
San Ramon Road between Dublin Boulevard and 1-
580.
The former westbound to northbound 1-580/San Ramon Road offramp in Dublin required motorists to merge three
lanes to the left to travel west on Dublin Boulevard within a very short segment of San Ramon Road. This project
signalized the offramp and eliminated the need to weave through northbound through-traffic coming from Pleasanton.
The project was funded with Tri-Valley Transportation Development Fee (20% portion) funds in the amount of
$2,353,163 and Pleasanton funds in the amount of $138,465, which were used toward completion of two reports
required by Caltrans. Construction was completed in November 2004.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design ¡Inspection $ 224,248 001 $ 138,465 $ 138,465
Other Contract Services 545,265 300 2,156,890 $ 196,273 2,353,163
Land ¡ Right of Way
Improvements 1,715,778
Machinery ¡ Equipment
Miscellaneous 6,337
TOTAL $ 2,491,628 $ 2,295,355 $ 196,273 $ 2,491,628
PROJECT I STAFF 0.10
MANAGEMENTIFTEj CONTRACT 0.09
-63-
PROJECT NUMBER
96400
PROJECT DESCRIPTION
Eastern Dublin
Arteri,al Street 1m rovements
ACTIVITY
STREETS
DESCRIPTION - LOCATION
e
-
1
.---¡
.,..",._-". .
."..-- I
.
I
I
.
I
i
L
This project establishes official Plan Lines for major
arterials in eastern Dublin, and constructs improvements
to those streets for the portion being funded by the
Eastern Dublin Traffic Impact Fee (TIF). This project
also includes engineering studies to update traffic impact
fees as development occurs, repayment of loans from
Pleasanton for the initial 2-lane construction of Dublin
Boulevard, and from Alameda County and BART for
roadway access to the eastern Dublin BART station.
Fees to be levied in eastern Dublin to complete required
improvements are currently estimated at approximately
$127 million. The amounts shown as "prior years"
reflect the work done by the City to date on engineering
and fee studies.
Projected expenditures for Fiscal Years 2004-2005 through 2008-2009 include improvements anticipated to be
constructed by developers in return for Eastern Dublin TIF credits during each of these years; however, since these
projects are not yet bonded, it is assumed for the purposes of the CIP that the City will pay for the work out of the
Eastern Dublin TIFs. The insufficient funds estimate of approximately $44.5 million reflects projects forecasted to be
constructed after the five-year time frame of the CIP. This project does not include Eastern Dublin TIF projects that
have become individual Capital Projects that are identified elsewhere in this document.
Projects completed or guaranteed during Fiscal Year 2004-2005 include partial payment to Pleasanton and BART for
the construction of two lanes of Dublin Boulevard, dedication of right-of-way and a small amount of improvements on
Tassajara Road just south of Fallon Road, and the dedication of right-of-way and construction of improvements,
including a bridge, at the north end of Fallon Road. Future projects include:
2005-2006: Minor median improvements to Dublin Boulevard just east of Scarlett Drive; extension of Dublin Boulevard
to Fallon Road; addition of one southbound lane on Hacienda Drive, between Gleason Drive and Central Parkway;
widening of Arnold Drive along Camp Parks; bridge on Tassajara Road, just north of the Dublin Ranch, Phase I,
development; Fallon Road widening between 1-580 and Dublin Boulevard; eastern Dublin BART parking structure; and
partial payments toward Pleasanton Roadway and BART loans.
2006-2007: Completion of bike/pedestrian trail along the Camp Parks frontage on Dublin Boulevard; westbound to
northbound'right-turn lane from Dublin Boulevard to Hacienda Drive; landscaping and final pavement lift on Central
Parkway and Gleason Drive through property owned by Dublin Land Company; extension of Central Parkway to Fallon
Road; improvements to Tassajara Road fronting the Wallis property; improvements to the east side of Tassajara Road
fronting the Dublin Ranch, Phase I, development; two additional lanes of traffic on Tassajara Road between Dublin
Boulevard and Gleason Drive; improvements to the east side of Tassajara Road between Dublin Boulevard and 1-580;
extension of the Tassajara Creek Trail through the Wallis property; and partial repayment of loans from BART and
Pleasanton.
2007-2008: Update of the Eastern Dublin TIF and partial payments on the loans from BART and Pleasanton.
2008-2009: Partial payments on the loans from BART and Pleasanton.
COMMENTS
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 177 .424 300 $ 1,384,653 $ 80,248 $ 22,383,176 $ 23,711,103 $ 1,354,003 $ 918,811 $ 49,831,994
Other Contract Services 680,774
Land I Right of Way
Improvements 84,010,793
Machinery I Equipment
Miscellaneous 9,442,582 Insufficient funding within CIP time frame 44,479.579
TOTAL $ 94,311,573 $ 1,384,653 $ 80,248 $ 22,383,176 $ 23,711 103 $ 1,354 003 $ 918,811 $ 94,311,573
PROJECT I STAFF 0.06 0.05
MANAGEMENTIFTE) CONTRACT 0.01
-64-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96405 Central Parkway & Persimmon Drive STREETS
Safety Improvements
DESCRIPTION - LOCATION
e
This project enhanced the sight distance associated
with the eastbound left-turn movement from Central
Parkway onto Persimmon Drive by relocating the left-
turn pocket to its ultimate location.
III'"
,
COMMENTS
The improvements also included extending the landscape median island 12 feet to the east to further enhance sight
distance and improve overall intersection geometries.
Category 1 Eastern Dublin Traffic Impact Fee (TIF) funds were used to cover the costs of this project. Project design
was completed in Fiscal Year 2003-2004 and the improvements were completed in Fiscal Year 2004-2005.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design /Inspection $ 17,926 300 $ 9,500 $ 103,666 $ 113,166
Other Contract Services 3,060
Land / Right of Way
Improvements 91,756
Machinery / Equipment
Miscellaneous 424
TOTAL $ 113,166 $ 9,500 $ 103,666 $ 113,166
PROJECT ¡STAFF 0.06
MANAGEMENT (FTE) CONTRACT
-65-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96420 1-580 & Tassajara Road STREETS
Freewav Interchange ImDrovements
DESCRIPTION - LOCATION
This project included the planning, design and
improvements to the 1-580/Tassajara Road/Santa Rita
Road freeway interchange to its ultimate configuration.
COMMENTS
e
....-.-,
.",...... I
.,.....".- .
............. I
I
I
I
I
I
.
I
.
I
New traffic from eastern Dublin development and from adjacent communities required a new Tassajara Road bridge over
Interstate 580 and other interchange ramp modifications to maintain the traffic level of service established by the City's
General Plan. Dublin developers deposited monies for the design and construction of the project as part of the Eastern
Dublin Traffic Impact Fee (TIF) Program, and received TIF credits in return.
To help reduce the overall cost of the project, the City had agreed with the Alameda County Congestion Management
Agency to exchange $4.7 million in State Transportation Improvement Program funds with $4.23 million in TIF funds, for a
net savings of $470,000. Furthermore, the City and the Alameda County Surplus Property Authority had also agreed to
exchange up to $3.0 million in TEA-21 funds with up to $2.7 million in TIF funds, for a net savings to the City of up to
$300,000. These monies have been deducted from the total project cost to reduce developers' contributions. A total of
$12,935,691 was received from the developers for the project. The project has now been completed and the unused
developer deposits were returned to the developers.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design ¡Inspection I
Contract Services $ 3,321,548 001 $ 4,938 $ 4,938
Land I Right of Way 219 7.438,168 7,438,168
Improvements 8,136,938 300 4,015,003 $ 18,228 4,033,231
Machinery I Equipment
Miscellaneous 17,851
TOTAL $ 11,476,337 $ 11,458,109 $ 18,228 $ 11,476,337
PROJECT I STAFF 0.09
MANAGEMENT IFTEj CONTRACT
-66-
"......._._"""""'_..._.....___..____.__ __..-....... _,_,.",-"M.",.,'.A
2004.2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96430 1-580 & Fallon Road Freeway Interchange STREETS
ImDrovements . Phase I
~ \"'{ ---.",:
~ \. \ ~ ...-- .
Phase I of this project would improve the 1-580/Falion Road - c \ :_~.--...----- .i
, .-
freeway interchange to accommodate future traffic in the next M--...· !
10 to 15 years, including traffic generated by several recently _....-...------ ¡
approved developments in eastern Dublin. Phase I consists of --_.....- L.____.
the following: ~;
i
.
!.
DESCRIPTION - LOCATION
1) Widen existing Fallon Road overcrossing to provide
two lanes in each direction.
2) Widen eastbound 1-580 offramp to provide a second
left-turn lane at the ramp end at the EI Charro Road
intersection and install a traffic signal at EI Charro Road.
3) Construct a southbound to eastbound 1-580 two-lane
loop onramp (one mixed-flow lane with an HOV bypass).
4) Widen northbound Fallon Road north of the 1-580 over-
crossing for additional capacity at ramp intersection.
5) Widen westbound 1-580 offramp to four lanes (two left-
and two right-turn lanes) at the Fallon Road intersection.
6) Widen Fallon Road southbound and north of 1-580
approaching the intersection with the westbound ramps.
7) Widen westbound 1-580 onramp and install Fallon Road
traffic signal.
8) Adding one westbound 1-580 auxiliary lane 1,300' in
advance of the interchange.
COMMENTS
New traffic from eastern Dublin development and from adjacent communities will require a new bridge and ramp
modifications at Fallon Road over 1-580 to maintain the level of service within the range established by the City's General
Plan. The Eastem Dublin Traffic Impact Fee (TIF) is expected to fund Dublin's portion of this project. The developer of
Dublin Ranch has deposited monies for preparation of the State-required Project Study Report, Project Report and Project
Design, and has agreed to fund the Phase I construction.
Pleasanton requested that Dublin amend the Project Report to include additional improvements associated with proposed
developments in Pleasanton. This work includes a northbound Fallon Road to westbound 1-580 loop to accommodate
traffic from the proposed Staples Ranch development in Pleasanton. A funding agreement between the two cities has
been approved for the design and construction of the northbound to westbound loop and the cost of this improvement is
being reimbursed by Pleasanton. DSRSD has also requested the installation of a 20" potable waterline within the Caltrans
right-of-way as part of the project, and has agreed to pay for its design and ultimately its construction. The ultimate phase
will be required once the area becomes fully developed. It is anticipated that Pleasanton and Livermore will contribute their
fair share of the cost of this ultimate project.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008·2009 Totals
Design ¡Inspection $ 275,420 001 $ 282,753 $ 49,396 $ 375,836 $ 579,293 $ 1,287,278
Other Contract Services 4,314,640 300 1,759,778 642,220 3.966,946 6,783,063 13,152,007
Land ¡ Right of Way
Improvements 9,830,000
Machinery ¡ Equipment
Miscellaneous 19,225
TOTAL $ 14,439.285 $ 2,042.531 $ 691,616 $ 4,342,782 $ 7 362,356 $ 14439,285
PROJECT I STAFF 0.31 0.54 0.35
MANAGEMENT (FTE) CONTRACT 0.25 3.32 4.88
-67-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96452 Downtown Traffic Signal STREETS
EauiDment ReDia cement
DESCRIPTION - LOCATION
e
This project will acquire Type 2070 controllers, Traffic
Operations Center (TOC) modems, controller modems,
and other related equipment over a five-year period
ending June 30, 2007, to complete the interconnection
of traffic signals within Downtown Dublin and integrate
these signals into the City's TOC communication
network.
COMMENTS
This project is needed to establish central communications with traffic signals in Downtown Dublin and facilitate signal
coordination to improve traffic flow. Some of the City's existing signal controllers are 10 to 15 years old and are
technically outdated. The installation of state-of-the-art traffic signal controllers and communications equipment will
help expand the central traffic management system for the 1-580 Smart Corridor Project by allowing the downtown
traffic signals and future traffic monitoring cameras to be added to the system. The 1-580 Smart Corridor system is
designed to allow the City to monitor traffic flows on major streets from a central location, detect traffic incidents, and
manage the timings of the traffic signals based on an automated time-of-day schedule. The system also serves as
an important tool to diagnose reported problems at signalized intersections from the Civic Center and possibly identify
the nature of the problem before directing signal maintenance staff to travel to the site. This CIP project has enabled
the City to accomplish the following tasks:
Fiscal Year 2003-2004: Upgraded traffic signal controllers at six intersections on Dublin Boulevard and coordinated
the signals between Hacienda Drive and Scarlett Drive during weekdays.
Fiscal Year 2004-2005: Coordinated the signals on Dublin Boulevard between Village Parkway and Regional Street
for the morning commute period.
In Fiscal Year 2005-2006, the City will upgrade six traffic signal controllers on San Ramon Road and Amador Valley
Boulevard, and integrate these intersections into the 1-580 Smart Corridor system. In Fiscal Year 2006-2007, five
signal controllers on Village Parkway will be upgraded and integrated into the system. The need for signal
coordination on San Ramon Road, Amador Valley Boulevard, and Village Parkway will also be assessed and possibly
implemented in conjunction with the signal controller upgrades.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 15,818 001 $ 48,169 $ 27,819 $ 30,200 $ 24,929 $ 131,117
Other Contract Services
Land I Right of Way
Improvements 115,299
Machinery I Equipment
Miscellaneous
TOTAL $ 131,117 $ 48,169 $ 27,819 $ 30,200 $ 24,929 $ 131,117
PROJECT I STAFF 0.01 0.02 0.02
MANAGEMENT (FTE) CONTRACT
-68-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96480 Downtown Dublin Roadway Improvements STREETS
DESCRIPTION - LOCATION
On October 19, 2004, the City Council adopted Resolution
No. 210-04 establishing a Traffic Impact Fee (TIF) for future
developments within the downtown area of Dublin. The
Downtown TIF program identifies six roadway improvement
projects as listed below. These improvements will be
required to mitigate future traffic impacts generated by new
development in Downtown Dublin.
e
1) St. Patrick Way Extension *
2) Golden Gate Drive Widening
3) Dublin Boulevard/Golden Gate Drive Intersection
Improvements
4) Dublin Boulevard/Amador Plaza Road Intersection
improvements
5) Dublin Boulevard/Dougherty Road Intersection
Improvements * (includes widening of Dublin Boulevard
between Dougherty Road & Sierra Court)
6) San Ramon Road/Dublin Boulevard Intersection
Improvements
M'"
1
The total cost for these improvements is estimated at
$8,711,298, including the cost of developing and updating
the TIF program.
* Specific CIP projects have been set up for these improvements. As such, expenditures using funds collected from the
Downtown TIF or other sources associated with these improvements are not reflected in the schedule below to avoid double-
counting of expenditures. The estimated cost for the remaining four improvements is $5,529,492, including the cost of
developing and updating the TIF program.
COMMENTS
The City has accumulated fees and traffic mitigation contributions from a number of development projects, which will be
utilized to construct certain portions of the above improvements. Through the end of Fiscal Year 2004-2005, fees collected
specifically for the projects associated with this CIP are estimated at $1,415,483, leaving $4,077,196 in unfunded
improvements, excluding the two separate CIP projects (#1 and #5) listed above.
The TIF Fee is calculated to generate the unfunded portion of improvement costs and includes a provision for construction
escalation over time. The City anticipates constructing these improvements as development occurs in the Downtown area
according to land use projections described in the Downtown TIF program.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 25,100 300 $ 34,917 $ 1,920 $ 36,837
Other Contract Services 9,173
Land I Right of Way
Improvements 5,492,679
Machinery I Equipment
Miscellaneous 2,564 Insufficient Funding within CIP Time Frame 5,492,679
TOTAL $ 5,529,516 $ 34,917 $ 1,920 $ 5,529,516
PROJECT ¡STAFF 0.22 0.02
MANAGEMENT (FTE) CONTRACT
-69-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96566 Traffic Signal at Dublin Boulevard STREETS
and Inspiration Drive
DESCRIPTION - LOCATION
e
This project provides for the installation of a traffic signal
at the intersection of Dublin Boulevard and Inspiration
Drive.
-:u",j
.....
1
COMMENTS
This project installed a traffic signal system at the intersection of Dublin Boulevard and Inspiration Drive. The project
was còmpleted in February 2005.
This project is funded through General Fund (Fund 001) and Traffic Impact Fee contributions (Fund 300) from Valley
Christian Center's (VCC). VCC is anticipated to contribute approximately 14% of the traffic signal cost at full build-out
of their proposed improvements.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 27,822 001 $ 19,258 $ 160,783 $ 180,041
Other Contract Services 300 32,950 32,950
Land I Right of Way
Improvements 183,956
Machinery I Equipment
Miscellaneous 1,213
TOTAL $ 212,991 $ 19,258 $ 193,733 $ 212,991
PROJECT I STAFF 0.08
MANAGEMENT (FTE) CONTRACT
-70-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96567 Traffic Signal at Amador Valley STREETS
Boulevard and Starward Drive
DESCRIPTION - LOCATION
e
This project installed a traffic signal at the intersection
of Amador Valley Boulevard/Starward Drive and
upgraded the existing traffic signal at Amador Valley
Boulevard/Donohue Drive. The two traffic signals are
designed to operate as a single traffic signal for both
Starward Drive and Donohue Drive.
-
1
, "t ."...",.-
\. \ '" ,----
"" ....--
C \ '1 _---~
COMMENTS
The traffic signal at Amador Valley Boulevard/Starward Drive enhances the safety of turning movements to and from
Starward Drive due to the heavy traffic volumes of approximately 18,000 vehicles per day on Amador Valley
Boulevard in the vicinity of Starward Drive. The new signal also improves access to the new Senior Center and
Senior housing development. The construction of this traffic signal project was completed in spring, 2005.
This project was funded through General Fund monies (Fund 001 ).
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005·2006 2006·2007 2007-2008 2008-2009 Totals
Design ¡Inspection $ 56,347 001 $ 44,462 $ 517,265 $ 561,727
Other Contract Services 3,000
Land ¡ Right of Way
Improvements 502,123
Machinery I Equipment
Miscellaneous 257
TOTAL $ 561,727 $ 44,462 $ 517,265 $ 561,727
PROJECT I STAFF 0.11
MANAGEMENT (FTE) CONTRACT
-71-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96568 Traffic Signal Upgrade - STREETS
Dublin Boulevard and Scarlett Drive
DESCRIPTION - LOCATION
e
This project upgraded the existing traffic signal
system on Dublin Boulevard at Scarlett Drive. This
upgrade allowed for the opening of two northbound
lanes of Scarlett Drive on the east side of the Chabot
Channel and widened Scarlett Drive to four lanes.
-
1
\A ' .,. ..,.......,.
\.. \ ............
C\\'(-~_....·
....
COMMENTS
The traffic signal at the intersection of Dublin Boulevard and Scarlett Drive was originally constructed in 2001 as part
of the Dublin Boulevard Widening from Dougherty Road to Scarlett Drive. With the completion of private
development on the east side of Scarlett Drive, it was necessary to open the two northbound lanes constructed along
the east side of the Chabot Channel. This project completed the improvements to the traffic signal system in order to
open these northbound lanes of Scarlett Drive to traffic. Improvements were completed in fall, 2004.
This project is funded through Category 2 Eastern Dublin Traffic Impact Fees.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006·2007 2007-2008 2008-2009 Totals
Design I Inspection $ 6,434 300 $ 3,540 $ 42,893 $ 46,433
Other Contract Services
Land I Right of Way
Improvements 39,536
Machinery I Equipment
Miscellaneous 463
TOTAL $ 46,433 $ 3,540 $ 42,893 $ 46,433
PROJECT I STAFF 0.03
MANAGEMENT (FTE) CONTRACT
-72-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96580 Annual Street Overlay Program STREETS
DESCRIPTION - LOCATION
This project provides for the placement of a 1-1/2 inch asphalt overlay on streets that are presently in a
deteriorated condition at various locations.
COMMENTS
As streets begin showing structural failures, it is important to reinforce these streets with pavement repairs and
overlay to reduce the need for more costly pavement reconstruction in the future. The City's Pavement
Management Program has provided the City with funding guidelines and priorities for maintaining the City streets.
The scope of work in this annual program includes removing and replacing failed pavement, placing 1-1/2 inches
of asphalt concrete overlay, and restriping the street.
This program will protect the substantial investment the City has in its street system.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 204,792 206 Annual $ 60,444 $ 154,398 $ 140,000 $ 173,000 $ 320,000 $ 847,842
Other Contract Services 42,550 217 Annual 90,512 631,048 410,000 295,000 305,000 1,731,560
Land f Right of Way 228 Annual 132,000 132,000
Improvements 2,460,860
Machinery I Equipment
Miscellaneous 3,200
TOTAL $ 2,711,402 $ 150,956 $ 785,446 $ 550,000 $ 600,000 $ 625,000 $ 2,711,402
PROJECT I STAFF 0.16 0.39 0.33 0.33 0.33
MANAGEMENT (FTE) CONTRACT
-73-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96585 Annual Slurry Seal Program STREETS
DESCRIPTION - LOCATION
This program would slurry seal existing street surfaces as a preventive maintenance technique used to prolong the life
of asphalt concrete pavement.
COMMENTS
As streets begin showing some wear and stress cracking, it is important to seal the cracks to keep water from getting
into the roadway subgrade, and to prolong the life of the asphalt concrete pavement. Slurry seal consists of a
sand/oil mixture which seals cracks and provides a new uniform wearing surface.
The City's Pavement Management Program provides the funding guidelines and the priorities for properly maintaining
the City streets.
This program will protect the substantial investment the City has in its street system.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 186,699 206 Annual $ 9,419 $ 756,180 $ 550,000 $ 600,000 $ 625,000 $ 2,540,599
Other Contract Services
Land I Right of Way
Improvements 2,352,000
Machinery I Equipment
Miscellaneous 1,900
TOTAL $ 2,540,599 $ 9,419 $ 756,180 $ 550,000 $ 600,000 $ 625,000 $ 2,540.599
PROJECT I STAFF 0.06 0.38 0.32 0.32 0.32
MANAGEMENT (FTE) CONTRACT
-74-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96840 Scarlett Drive STREETS
Iron Horse Trail Extension
DESCRIPTION - LOCATION
e
This project would provide an extension of Scarlett Drive
and relocate and enhance a portion of the Iron Horse
Trail. The roadway element is a connection between
Dougherty Road and Dublin Boulevard (within the
Southern Pacific Railroad Right-of-Way).
....
1
"^ \ .,. ....",......-
\. \ ..--
"'(" ........
C \ .....'-
COMMENTS
The extension of Scarlett Drive, which is included in the
Dublin General Plan, will relieve traffic congestion at the
Dougherty Road/Dublin Boulevard intersection, especially
for BART Station-bound traffic. Traffic mitigation fees
which have been collected specifically for this project are
estimated at $306,258 through the end of Fiscal Year
2004-2005. The balance of project costs will need to be
funded by additional developer dedications/contributions,
County-Wide half-cent transportation sales tax, Eastern
Dublin Traffic Impact Fees (Category 2), Contra Costa
County contributions and/or outside grants.
This project is included in the voter-approved Alameda County Transportation Expenditure Plan funded by the half-cent
sales tax. The sales tax funding programmed for this project is presently $5.55 million, and is subject to approval by the
Alameda County Transportation Improvement Authority (ACTIA). The ACTIA monies have not been included in the
project at this time, as ACTIA has not approved the present scope of the project.
Castle Construction has constructed a portion of Scarlett Drive from Dougherty Road to Houston Place as part of the
Scarlett Place housing development, located next to Scarlett Drive. The value of the dedicated street right-of-way and
street improvements is estimated at $2,386,360. The total cost of the project has been reduced by this amount to reflect
this latest improvement. A future development that could impact this project is the City General Plan Amendment being
proposed by Parks Reserve Forces Training Area (PRFTA). This development would be located on the southern part of
the PRFTA property bounded by Dublin Boulevard, Dougherty Road, Amold Road, and 5th Street. Any proposed streets
within this area could impact the extension of Scarlett Drive.
In Fiscal Year 2003-2004, the scope of this project was changed from a 2-lane to a 4-lane facility, based on a traffic study
for the newly-approved Transit Center Development.
Project development, including preliminary engineering and environmental work, will be performed in Fiscal Year 2005-
2006, using traffic mitigation fees specifically collected for this project.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007 -2008 2008-2009 Totals
Design I Inspection $ 874,884 217 $ 1,728,935 $ 3,817,222 $ 5,546,157
Other Contract Services 641,341 300 $ 979 $ 1,657 $ 236,240 $ 69,000 4,001,984 683,882 4,993,742
Land I Right of Way 5,170,000
Improvements 3,817,222
Machinery I Equipment
Miscellaneous 36,452
TOTAL $ 10,539,899 $ 979 $ 1,657 $ 236,240 $ 69,000 $ 5,730,919 $ 4,501,104 $10,539,899
PROJECT I STAFF 0.01 0.14 0.07 0.14 0.13
MANAGEMENT (FTE} CONTRACT 1.91
-75-
,. _."^.~~..._~-~~_.,.._~-~--~~-~.._. ._.,_.,.~---^,,---~.._~-,,"
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96850 Dougherty Road Improvements - STREETS
North of Amador Valley Boulevard
to North of Houston Place
DESCRIPTION - LOCATION
e
.....
1
"'i --
\ '" \ ........-
\.. ,.--
\' '(' ........-
C \ _..-~""
This project consists of two phases. The first
phase widened the travel lanes by removing
existing dirt medians on Dougherty Road and
replacing them with new pavement. This
completed the ultimate pavement improvements
for southbound traffic for this segment of
Dougherty Road. A second phase of this project
will widen Dougherty Road from four to six lanes
and will include landscaped medians from Amador
Valley Boulevard to north of Houston Place.
COMMENTS
The first phase of this project allowed the two southbound lanes to move away from the westerly curb, thus improving
intersection sight distance and providing an area along the curb for bus stops, emergency parking and on-street
. bicyclists. The City received an Intermodal Surface Transportation Efficiency Act (ISTEA) Grant to fund the bulk of this
project. The City also overlaid this segment of Dougherty Road, including a portion of Dougherty Road north of
Amador Valley Boulevard. The second phase of this project is anticipated to be funded by Traffic Impact Fees,
including contributions from the Dougherty Valley (Contra Costa County) projects and eastem Dublin. To date,
approximately $163,648 of Developer Impact Fees have been collected and are available for this project.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 435,295 206 $ 139.186 $ 139,186
Other Contract Services 146,104 210 285,044 285,044
Land I Right of Way 217 62,269 62,269
Improvements 3,326,668 220 69,340 69,340
Machinery I Equipment 300 14,430 $ 380,850 $ 3,106,975 3,502,255
Miscellaneous 150,027
TOTAL $ 4,058,094 $ 570,269 $ 380,850 $ 3,106,975 $ 4,058,094
PROJECT I STAFF 0.33 0.47
MANAGEMENT (FTEj CONTRACT 0.26
-76-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96852 Dougherty Road Improvements - STREETS
Houston Place to 1-580
DESCRIPTION - LOCATION
e
1) Widen northbound Dougherty Road between 1-
580 and Dublin Boulevard.
2) Widen southbound Dougherty Road between the
1-580 westbound onramp and Dublin Boulevard.
3) Widen southbound Dougherty Road between
Dublin Boulevard and Sierra Lane,
4) Widen westbound Dublin Boulevard between
Dougherty Road and approximately 500 feet east
of Dougherty Road.
5) Widen westbound Dublin Boulevard between
Dublin Court and Dougherty Road.
6) Widen eastbound Dublin Boulevard between
Dublin Court and Dougherty Road.
This project provides for acquisition of right-of-way and
widening of Dougherty Road between 1-580 and
Houston Place, and required improvements at the
intersection of Dublin Boulevard and Dougherty Road.
To accommodate the necessary left-tum, right-turn and
through lanes, the following improvements are
proposed:
COMMENTS
Recent traffic studies have indicated the need to widen Dougherty Road and Dublin Boulevard to improve the level of
service at the intersection of the two roadways, which is necessary to accommodate planned growth in the Dublin
General Plan and the proposed Transit Village at the eastern Dublin BART Station. The project cost is proposed to be
funded by developer dedications/contributions, Traffic Impact Fees (TIF), and/or outside grants. In Fiscal Year 2005-
2006, the City will have approximately $433,229 in voluntary traffic mitigation contributions, which are restricted for use
on this project. The City will have approximately $4,913,000 in Dougherty Valley TIF in Fiscal Year 2005-2006 which
can be used for this project. The Downtown TIF program is intended to cover 16% of the total project cost when
sufficient funds are collected from this program. The project is also proposed to be funded by Eastern Dublin Traffic
Impact Fees (Category 2).
Preliminary engineering and environmental work for this capital project were completed in Fiscal Year 2003-2004.
Design and right-of-way acquisition started in Fiscal Year 2004-2005, with completion in Fiscal Year 2005-2006.
Construction is scheduled to start in Fiscal Year 2005-2006, and be completed in Fiscal Year 2006-2007.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design !Inspection $ 857,543 300 $ 201,004 $ 1,307,062 $ 8,867,552 $ 4,093,740 $ 14,469,358
Other Contract Services 486,108
Land I Right of Way 8,151,589
Improvements 4,945,000
Machinery I Equipment
Miscellaneous 29,118
TOTAL $ 14,469,358 $ 201,004 $ 1,307,062 $ 8,867,552 $ 4,093,740 $ 14,469,358
PROJECT I STAFF 0.82 1.06 0.93
MANAGEMENT IFTE) CONTRACT
-77-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96870 Saint Patrick Way - STREETS
Regional Street to Golden Gate Drive
DESCRIPTION - LOCATION
e
This project will construct a 2-lane roadway
between Golden Gate Drive and Regional Street,
south of and parallel to Dublin Boulevard.
.....
,
tA \ '1 ....,...""..
"i \.. \ ..-,...-
C \ 1: .__~_....
COMMENTS
The need for a connector road for three long commercial cul-de-sacs was first identified in the City's original
Downtown Study. This need is becoming more apparent as this portion of the Central Business District develops
further and the proposed BART parking lot is constructed along Golden Gate Drive. The section of Saint Patrick Way
between Amador Plaza Road and Golden Gate Drive was constructed by the Alameda County Transportation
Authority (ACTA) as part of the 1-580/1-680 Interchange Improvements. It is anticipated that the City's project,
between Golden Gate Drive and Regional Street, will be funded through private contributions in the form of a
downtown traffic development impact fee. BART mitigation funds, and developer-built mitigation improvements.
For the purpose of this Capital Project, only the portion of Saint Patrick Way that is anticipated to be built by the City is
included in the cost estimate.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 171,776 300 $ 6,786 $ 572,412 $ 1,054,400 $ 1,633,598
Other Contract Services 92,275
Land I Right of Way 522,130
Improvements 847,350
Machinery I Equipment
Miscellaneous 67
TOTAL $ 1,633,598 $ 6,786 $ 572,412 $ 1,054,400 $ 1,633,598
PROJECT I STAFF 0.10 0.26
MANAGEMENT (FTE) CONTRACT 0.17
-78-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
96930 Dublin Boulevard Improvements - STREETS
Sierra Court to Dublin Court
DESCRIPTION - LOCATION
e
This project will widen Dublin Boulevard from
Sierra Court to Dublin Court and underground
existing overhead utilities. This project will
increase the roadway capacity from four to six
lanes.
.....
1
'" \ .,. ............
\.. \ ...-,-
1" "< ........
'-~-
COMMENTS
This is the third phase of the Dublin Boulevard widening. The widening of this segment of Dublin Boulevard will
complete the improvements on Dublin Boulevard from San Ramon Road to Dougherty Road. Recent traffic studies
have shown that six lanes of traffic will be needed as Dublin continues to expand to the east.
It is anticipated that this project will be funded through Traffic Impact Fees (TIF) and outside grants. Through the end
of Fiscal Year 2004-2005, TIF fees collected specifically for this project are estimated at $584,501. In addition, the
project may be funded from Category 2 Eastern Dublin TIF fees. The budget proposes to proceed with preliminary
engineering and environmental work in Fiscal Year 2007-2008, design and land acquisition during Fiscal Year 2008-
2009, with construction starting in Fiscal Year 2009-2010.
Existing overhead utilities will also be relocated along Dublin Boulevard prior to the road improvements. It is anticipated
that sufficient Public Utility Commission Rule 20A funds will be available in Fiscal Year 2009-2010 to reimburse the City
for these improvements.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 242,590
Other Contract Services 117,875 300 $ 109,715 $ 754,875 $ 864,590
Land I Right of Way 521.325
Improvements 1,673,385
Machinery I Equipment
Miscellaneous 56,375 Insufficient Funding within CIP Time Frame 1,746,960
TOTAL $ 2,611,550 $ 109,715 $ 754,875 $ 2,611,550
PROJECT I STAFF 0.17 0.33
MANAGEMENT (FTE) CONTRACT
-79-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
Not Yet Assigned Bike Lane - Amador Valley Boulevard STREETS
Stagecoach Road to Douahertv Road
DESCRIPTION - LOCATION
Q
This project would construct a Class 2 bicycle
lane along the north side of Amador Valley
Boulevard between Stagecoach Road and
Dougherty Road to allow for the exclusive use of
bicycles and pedestrians.
--
1
"^ \ l' _""._~-'-
'l \. ...:..............
c \ "'t .......-..
COMMENTS
This Bike Lane Project on Amador Valley Boulevard will connect the Iron Horse Trail, the Alamo Creek Bike Path,
and the Dougherty Road Bike Path.
As of the end of Fiscal Year 2004-2005, developer fees in the amount of approximately $61,085 have been collected
for this project. The balance of the project is proposed for funding from future Measure B Bike/Pedestrian Funds.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 75,763 227 $ 211,629 $ 211,629
Other Contract Services 7,820 300 61,085 61,085
Land I Right of Way
Improvements 187,630
Machinery I Equipment
Miscellaneous 1,501
TOTAL $ 272,714 $ 272,714 $ 272,714
PROJECT I STAFF 0.16
MANAGEMENT (FTE) CONTRACT
-80-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
Not Yet Assigned Countdown Pedestrian Signals STREETS
DESCRIPTION - LOCATION
This project would install "countdown" type pedestrian traffic signals at major intersections throughout the City.
Countdown pedestrian signals provide a readout which advises the pedestrian how much time is available to cross
the street safely.
COMMENTS
Countdown pedestrian signals were installed at the Dublin BoulevardNillage Parkway intersection during Fiscal Year
2002-2003 on.a trial basis. This installation has worked very well, giving the pedestrians an actual time, in seconds,
to complete street crossings. Additional countdown pedestrian signals will be provided at the Amador Valley &
Donohue and Amador Valley & Starward intersections as part of the Fiscal Year 2004-2005 signal construction
project.
This project proposes to install countdown pedestrian signals at 23 major intersections, based on pedestrian volume
for school, transit, retail, and recreational facilities.
The California Energy Commission recently adopted regulations which require the use of LED (light emitting diode)
modules for all traffic signal indications, and it is therefore recommended that this project be completed within one
fiscal year.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007 -2008 2008-2009 Totals
Design I Inspection 001 $ 43,200 $ 43,200
Other Contract Services
Land I Right of Way
Improvements $ 43,200
Machinery I Equipment
Miscellaneous
TOTAL $ 43,200 $ 43,200 $ 43,200
PROJECT I STAFF
MANAGEMENT (FTEj CONTRACT
-81-
,.~-_.~..._--.__._- -.-.......-.-........
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
Not Yet Assigned Dublin Boulevard - STREETS
Right Turn at Village Parkway
DESCRIPTION - LOCATION
e
This project will construct an eastbound right-turn
lane on Dublin Boulevard at Village Parkway.
-
1
tit \ "t' .......-..,.
"'( \. ~...-....."""
C. \ \' ø-"!.·....
.-
COMMENTS
The 1-580/1-680 Direct Connector Project identified the need to construct an eastbound right-turn lane on Dublin
Boulevard at Village Parkway. This project will accommodate additional traffic from downtown Dublin attracted to the
new 1-680 northbound on-ramp at Village Parkway and will improve the level of service at the intersection of Dublin
Boulevard and Village Parkway. This project will be funded from available Traffic Impact Fees (Eastern Dublin TIF
Category 3).
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 67,Q42 300 $ 46,537 $ 593,665 $ 640,202
Other Contract Services 11,809
Land I Right of Way 137,726
Improvements 421,936
Machinery I Equipment
Miscellaneous 1,689
TOTAL $ 640,202 $ 46,537 $ 593,665 $ 640,202
PROJECT I STAFF 0.10 0.09
MANAGEMENT (FTE) CONTRACT
-82-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
Not Yet Assigned Dougherty Road, Improvements - STREETS
Amador Vallev Boulevard North to City Limits
DESCRIPTION - LOCATION
e
This project consists of constructing the ultimate
northbound lanes from Amador Valley Boulevard
north to the Dublin City Limits. This would make
Dougherty Road a six-lane facility.
-
1
\ .,. ...-,-
\. \ ~ ,......-
"'(' 'l .."....-
C \ .,._-"!.
COMMENTS
The present configuration of the road is now four lanes; however, the easterly lane is in the future median. This project
will widen Dougherty Road to a six-lane divided roadway with landscaped medians within the limits of the project. The
need for this project is being driven by development in the Dougherty Valley. It is anticipated that developers' Traffic
Impact Fees, including Contra Costa County's Dougherty Valley fees, will fund the project. In Fiscal Year 2002-2003,
Dougherty Valley impact fees funded the traffic signal at the intersection of Dougherty Road and Willow Creek Drive.
Through the end of Fiscal Year 2004-2005, the remaining Traffic Impact Fees collected specifically for this project are
estimated to total $366,290.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 413,100
Other Contract Services 158,875
Land I Right of Way
Improvements 3,199,350
Machinery I Equipment
Miscellaneous 115,825 Insufficient funding within CIP time frame $ 3,887,150
TOTAL $ 3,887,150 $ 3,887,150
PROJECT I STAFF
MANAGEMENT (FTE) CONTRACT
-83-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
Not Yet Assigned Tri-Valley Transportation Development Fee STREETS
Reaional TransDortation Projects
DESCRIPTION - LOCATION
This project would contribute to the construction of the following Regional Transportation projects:
1) 1-580/1-680 Interchange Improvements (Complete)
2) Improvements - SR 84 between 1-580 and 1-680
3) 1-680 Auxiliary Lanes from Bollinger Canyon Road to Diablo Road
4) West Dublin/Pleasanton BART Station ($4 million TVTDF obligation fulfilled)
5) 1-580 HOV Lanes between Santa Rita Road and Greenville Road
6) 1-680 HOV Lanes between SR84 and Sunol Grade
7) Improvements to the 1-580/San Ramon Road Interchange (Dublin portion of project complete)
8) 1-680/Alcosta Blvd Interchange Improvements (Under Construction as a City of San Ramon CIP Project)
9) Crow Canyon Road Safety Improvements west of Bollinger Canyon Road
10) Vasco Road Safety Improvement North of 1-580
11) Express Bus Service in the Tri-Valley Area
COMMENTS
The seven Tri-Valley jurisdictions (Dublin, Pleasanton, Livermore, Alameda County, San Ramon, Danville and
Contra Costa County) are collecting Tri-Valley Transportation Development Fees (TVTDF) from developers as a
mitigation for new developments in the Tri-Valley area. These fees are to be collected and used to construct projects
on the above project list. The local match for the 1-580/1-680 Flyover Project, which was completed in June 2002,
was funded first, and the remaining projects were prioritized based on the recently adopted Strategic Expenditure
Plan 2004 Update through the development of a funding priority list. The TVTDF is projected to generate $93.9
million over the lifetime of the program, of which approximately $21.597 million is expected to be collected in Dublin.
Each jurisdiction submits 80% of the fees collected to the Tri-Valley Transportation Council (TVTC) and retains 20%
of the fees collected to fund top priority projects. Dublin designated the 1-580/San Ramon Road Interchange and the
West Dublin BART Station as its two top priority projects for the 20% set-aside monies. The 1-580/San Ramon Road
Interchange project on the Dublin side of 1-580 was completed in 2004, and the West Dublin BART Station is in the
planning stages.
In 2003, the TVTC appropriated $800,000 in 80% TVTDF funds for the 1-580/San Ramon Road Interchange project,
which was expended in conjunction with Dublin's 20% set-aside funds for construction of this project in 2004.
Additionally, the City received $4,000,000 in Fiscal Year 2003-2004 from the TVTC for the West Dublin BART
Station project, and passed these funds through to BART for use on this project.
The amount shown in the schedule below reflects the TVTDF revenue expected to be collected in Dublin
($21,597,000) through Fiscal Year 2012-2013.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection
Other Contract Services
Land I Right of Way
Improvements $ 21,597,000
Machinery I Equipment
Miscellaneous Insufficient funding within CIP time frame $ 21,597,000
TOTAL $ 21,597,000 $ 21,597,000
PROJECT I STAFF
MANAGEMENT (FTEI CONTRACT
-84-
"._-",,--,"...-""-~' -..,-,,-""_.__.,_.~ ,.'"
2004-2009 CAP IT AL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
New Alamo Canal Trail Under 1-580 STREETS
DESCRIPTION - LOCATION
e
The City of Dublin is working jointly with the East Bay
Regional Park District, the City of Pleasanton, Caltrans
and Zone 7 in preparing an engineering study to
determine the feasibility of constructing a trail
underneath 1-580. This section of the trail will connect
the segment of the Alamo Canal Trail north of the
freeway (adjacent to the City Library) with the
Pleasanton trail south of the freeway to transform it to a
regional trail.
M'"
1
COMMENTS
The Alameda County Transportation Improvement Authority has approved Measure B funds in the amount of
$50,000 for the study, requiring a local match of $25,000 each from Pleasanton and Dublin.
2005-2006 GOAL
1. Work with EBRPD and the City of Pleasanton to conduct a preliminary engineering study and
identify funding sources to facilitate the connection of Alamo Creek Trail under 1-580 to
Pleasanton trails (High Priority Goal)
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 6.400
Other Contract Services 25,000 227 $ 31,400 $ 31,400
Land I Right of Way
Improvements
Machinery I Equipment
Miscellaneous
TOTAL $ 31,400 $ 31,400 $ 31,400
PROJECT I STAFF 0.06
MANAGEMENT (FTE) CONTRACT
-85-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
New Citywide Bicycle I Pedestrian Plan STREETS
DESCRIPTION - LOCATION
This project provides for the development of a City-wide Bicycle Master Plan that would evaluate existing bicycle
conditions and incorporate an integrated plan including access to parks and open space areas.
COMMENTS
The City applied for Transportation Development Act Article 3 funding in the amount of $45,144 that would partially
fund the development of the Plan. Supplementary funds from the Measure B Bicycle Program would be used to fully
fund the project.
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008·2009 Totals
Design I Inspection $ 20,800 211 $ 45,144 $ 45,144
Other Contract Services 60,144 227 36,000 36,000
Land I Right of Way
Improvements
Machinery I Equipment
Miscellaneous 200
TOTAL $ 81,144 $ 81,144 $ 81,144
PROJECT I STAFF 0.18
MANAGEMENT IFTE) CONTRACT
-86-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
New Dublin Boulevard - Raise Catch Basin Grates STREETS
DESCRIPTION - LOCATION
e
This project would raise the grade of the catch basin
grates along both the north and south curb lines on
Dublin Boulevard to match the existing gutter
elevations. Project limits would extend from Donlon
Way to just east of Village Parkway.
M'"
1
COMMENTS
The early phase of the improvements to Dublin Boulevard restriped the existing 4 lanes to 6 lanes without moving the
existing curbs. The City's standard curb inlet drops approximately 1 1/2 inches through the gutter line to allow for a 6-
inch opening in the face of the curb. On a normal street with a shoulder, this design is acceptable; however, when
the outside lane is moved up to the curb, motorists' vehicles experience a dip on the right side when passing over the
catch basins. In addition, with a wide shoulder, bicyclists can steer around the catch basin grates. This project would
make it safer for bicyclists and more comfortable for motorists passing over the curb inlets.
FINANCINGIYEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008·2009 Totals
Design I Inspection $ 7,030 001 $ 32,530 $ 32,530
Other Contract Services
Land I Right of Way
Improvements 25,000
Machinery I Equipment
Miscellaneous 500
TOTAL $ 32,530 $ 32,530 $ 32,530
PROJECT I STAFF 0.06
MANAGEMENT IFTE) CONTRACT
-87-
2004-2009 CAPITAL IMPROVEMENT PROGRAM
PROJECT NUMBER PROJECT DESCRIPTION ACTIVITY
New Summer Concert Series Banners STREETS
DESCRIPTION - LOCATION
This project provides for the replacement of the current Summer Concert Series banners. The project would also
expand the number of banners from 20 to 55, so that the banners could be hung along the entire length of Dublin
Boulevard (from Donlon Way to Keegan Way) and provide better exposure for the concert series.
COMMENTS
When the concert banners were first purchased, the City did not have hardware on light poles in the eastern part of
Dublin; therefore, more replacement banners are needed to provide coverage throughout the City. This project
would also provide enough banners for future expansion to cover the entire length of Dublin from Donlon Way fo
Fallon Road.
These banners would be hung starting in June 2006.
2005-2006 GOAL
1. Purchase additional banners to advertise summer concert series throughout the city (High Priority Goal)
FINANCINGNEARS SCHEDULE
ESTIMATED COSTS Fund Prior Years 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 Totals
Design I Inspection $ 415 001 $ 17,335 $ 17,335
Other Contract Services
Land I Right of Way
Improvements
Machinery I Equipment 16,920
Miscellaneous
TOTAL $ 17,335 $ 17 ,335 $ 17,335
PROJECT I STAFF
MANAGEMENTCFTEj CONTRACT