Loading...
HomeMy WebLinkAboutPC Reso 18-14 PLPA-2016-00064 Phase 4-5 Blvd Project VTMRESOLUTION NO. 18-14 A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF DUBLIN APPROVING VESTING TENTATIVE MAPS 8370, 8371, 8372, AND 8373 TO CREATE INDIVIDUAL NEIGHBORHOODS AND PARCELS ON APPROXIMATELY 42.16 ACRES IN PHASES 4 AND 5 OF THE BOULEVARD PROJECT (PORTION OF ASSESSOR PARCEL NUMBER 986-0001-001-15) PLPA-2016-00064 WHEREAS, the Applicant, Dublin Crossing LLC, is requesting approval of Vesting Tentative Maps 8370, 8371, 8372, and 8373 to create individual neighborhoods and parcels on 42.16 acres within Phases 4 and 5 of the Boulevard project area; and WHEREAS, the Applicant is also requesting approval to construct six new neighborhoods in the Boulevard (Dublin Crossing) project area ("Project Site"), which includes the construction of 510 townhomes, duets, and detached small -lot single family homes, landscape improvements, and street improvements for Phases 4 and 5 (the final phases of development); and WHEREAS, the project site is located within the Dublin Crossing Specific Plan and the Dublin Crossing Zoning District; and WHEREAS, Master Vesting Tentative 8150 was approved via Resolution 14-14 that divided the 189 -acre Boulevard project area into multiple master parcels to coincide with the five anticipated phases development; and WHEREAS, Vesting Tentative Maps 8370, 8371, 8372, and 8373 will further divide the large master parcels into smaller parcels for the purposes of development in compliance with the Dublin Crossing Specific Plan, which was approved by the City Council via Resolution 187-13; and WHEREAS, the Vesting Tentative Map application, Vesting Tentative Maps 8370, 8371, 8372, and 8373, included in the Project Plan Set that is attached as Exhibit A to the separate SDR Resolution (Resolution 18-12) defines this "Project" and is available and on file in the Community Development Department; and WHEREAS, Vesting Tentative Maps 8370, 8371, 8372, and 8373 illustrate the lotting pattern and plans, proposed roadway improvements (roadway widths, bike and pedestrian, and bus stops), utility plans (water, sewer, and wastewater), grading plans, and stormwater treatment plans throughout the Project Area; and WHEREAS, multiple future Final Maps map be filed in accordance with the detailed phasing of the subdivision construction; and WHEREAS, Vesting Tentative Maps 8370, 8371, 8372, and 8373 are in conformance with the Dublin Crossing Specific Plan and General Plan; and WHEREAS, in accordance with the California Environmental Quality Act certain projects are required to be reviewed for environmental impacts and when applicable, environmental 1 of 23 documents prepared; and WHEREAS, the project is located within the Dublin Crossing Specific Plan area (Specific Plan), which was the subject of an Environmental Impact Report (EIR) (SCH# 2012062009) prepared in accordance with the California Environmental Quality Act (CEQA) and certified by the City Council on November 5, 2013 (Resolution 186-13). Subdivision maps were included as part of the project entitlements listed in the EIR. The EIR provides the CEQA environmental review for those future entitlements to implement the Specific Plan, unless the standards for subsequent or supplemental environmental review under CEQA are met. Pursuant to CEQA, the Vesting Tentative Map approval for this project is within the scope of the project analyzed in the EIR and no further CEQA review or document is required; and WHEREAS, the Planning Commission did hold a noticed study session on April 10, 2018 and also did hold a public hearing on said application on May 8, 2018 for this project, at which time all interested parties had the opportunity to be heard; and WHEREAS, a Staff Report was submitted recommending that the Planning Commission approve Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373; and WHEREAS, the Planning Commission did hold a public hearing on said application on May 8, 2018, at which time all interested parties had the opportunity to be heard; and WHEREAS, proper notice of said public hearing was given in all respects as required by law; and WHEREAS, a Staff Report was submitted recommending that the Planning Commission approve Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373; and WHEREAS, the Planning Commission did hear and use independent judgment and considered all said reports, recommendations, and testimony hereinabove set forth. NOW, THEREFORE, BE IT RESOLVED that the Planning Commission of the City of Dublin does hereby make the following findings and determinations regarding Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 for the Boulevard (Dublin Crossing) Project in conformance with Chapter 9 (Subdivisions) of the Dublin Municipal Code: 1. Proposed Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373, together with the provisions for its design and improvement, are consistent with the Dublin General Plan and the Dublin Crossing Specific Plan, as amended, as they relate to the subject property in that they are subdivisions for implementation that are generally consistent with the design guidelines and development standards of the policy documents. 2. The subdivision site is physically suitable for the type and proposed density of development because the project design, architecture, and concept have been integrated with topography of the project site created by Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 to incorporate habitat preservation, install water quality measures, and minimize overgrading and extensive use of retaining walls. Therefore, the proposed subdivisions are physically suitable for the type and intensity of development proposed. 3. The tentative tract map is consistent with the intent of applicable subdivision design or improvements of the tentative tract map are consistent with the city's general plan and any applicable specific plan because the proposed Vesting Tentative Tract Maps 8370, 8371, 2 of 23 8372, and 8373 are consistent with the intent of the subdivision design of the Boulevard Project and improvements of the tentative tract map are consistent with the Dublin General Plan and the Dublin Crossing Specific Plan. 4. The design of Proposed Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 and proposed improvements will not cause substantial environmental damage or substantially and avoidably injure fish or wildlife or their habitat because all mitigations required by the Dublin Crossing Specific Plan related to biological resources have been complied with. 5. The design of the subdivision or type of improvements will not cause serious public health concerns because the design of the subdivision or type of improvements have been conditioned to comply with all building codes and ordinances in effect at the time of permit issuance and in addition the project was evaluated for its impacts to public health in the environmental impact report completed for the Dublin Crossing Specific Plan. 6. The design of proposed Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 and the type of improvements will not conflict with easements, acquired by the public at large, for access through or use of property within the proposed subdivision; or alternate easements are provided. The City Engineer has reviewed the maps and title reports and has not found any conflicting easements of this nature. 7. The design or improvements of proposed Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 are consistent with the Dublin General Plan and the Dublin Crossing Specific Plan because the project design, architecture, and concept have been integrated with topography of the project site created by Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 to incorporate habitat preservation, install water quality measures, and minimize overgrading and extensive use of retaining walls. Therefore, the proposed subdivisions are physically suitable for the type and intensity of development proposed. 8. Proposed Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 are designed to provide for future passive or natural heating or cooling opportunities in that, where feasible, building orientation and spacing has been taken into account when plotting the building locations on the development sites, and passive/natural heating and cooling opportunities have not been precluded; 9. Proposed Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373, including design and improvement, shall comply with all the applicable provisions and requirements of the zoning ordinance, the latest municipal stormwater permit issued to the city by the Regional Water Quality Control Board, this title, any other ordinance of the city, and the Subdivision Map Act as required by the Dublin Crossing EIR and project -specific conditions of approval noted herein. BE IT FURTHER RESOLVED that the Planning Commission of the City of Dublin does hereby make the following findings and determinations under CEQA regarding Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 for the Boulevard (Dublin Crossing) Project. These findings are based on information contained in the EIR, the Planning Commission Staff Report, and all other information contained in the entire record for the Project. These findings constitute a summary of the information contained in the entire record. Other facts and information in the record that constitute substantial evidence to support each finding that is not specifically included below are incorporated herein by reference: A. Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 are within the scope of the project analyzed in the EIR. The environmental impacts of Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 are analyzed in the EIR and no further environmental review 3 of 23 is required under CEQA for Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 under Public Resources Code section 21166 and CEQA Guidelines sections 15162 and 15163. B. Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 do not constitute a substantial change to the project analyzed in the EIR that will require major revisions to the EIR due to new significant environmental effects or a substantial increase in severity of previously identified significant effects. Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 are consistent with the Project analyzed in the EIR and do not propose any change to the Project. C. There are no substantial changes that have occurred with respect to the circumstances under which the Project will be undertaken that will require major revisions to the EIR due to the involvement of new significant environmental effects or a substantial increase in severity of significant effects identified in the EIR. The EIR was certified in 2013 and no substantial changes to circumstances affecting the Project have occurred within that period of time. D. There is no new information of substantial importance, which was not known or could not have been known with the exercise of reasonable diligence at the time the EIR was certified in 2013 that show any of the conditions in CEQA Guidelines section 15162(a)(3)(A) — (D). E. The mitigation measures in the Mitigation Monitoring and Reporting Program adopted by the City Council on November 5, 2013 apply to Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 as applicable. BE IT FURTHER RESOLVED that the Planning Commission of the City of Dublin hereby approves Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 for 510 residential units in six neighborhoods subject to the conditions included below. CONDITIONS OF APPROVAL — Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373: Unless stated otherwise, all Conditions of Approval shall be complied with prior to the issuance of building permits or establishment of use, and shall be subject to Planning Department review and approval. The following codes represent those departments/agencies responsible for monitoring compliance of the conditions of approval. [PL.1 Planning, [B] Building, [PO] Police, [PW] Public Works [P&CS] Parks & Community Services, [ADM] Administration/City Attorney, [FIN] Finance, [F] Alameda County Fire Department, [DSR] Dublin San Ramon Services District, [CO] Alameda County Department of Environmental Health, [Z7] Zone 7. COA # Condition Text Resp. Agency Required Prior to: PLANNING DIVISION 1. Approval. Vesting Tentative Tract Maps 8370, 8371, 8372, and 8373 PL Ongoing establish six residential neighborhoods for Phases 4 and 5 of the Boulevard Project. Unless modified by the Conditions of Approval contained herein, Development pursuant to these Vesting Tentative Tract Maps approval generally shall conform to the Vesting Tentative Tract Map sheets prepared by MacKay & Somps Civil Engineers dated received April 27, 2018 (attached to the SDR Resolution (Resolution 18- 4of23 COA # Condition Text Resp. Required Agency Prior to: 12) as Exhibit A), which is on file in the Community Development Department. 2. VTM 8150. All Conditions of Approval in PC Resolution 14-14 that are PL Ongoing not expressly modified by these Conditions of Approval remain in full force and effect. 3. Effective Date. This VTM approval becomes effective 10 days after PL Ongoing action by the Planning Commission unless otherwise appealed to the City Council. 4. Expiration. The Vesting Tentative Maps, of which the Landscape Master PL Ongoing Plan is a part, shall have that life determined by the Subdivision Map Act, including but not limited to Section 66452.6 5. Compliance. The Applicant/Property Owner shall operate this use in PL Ongoing compliance with the Conditions of Approval of this VTM approval, the approved plans and the regulations established in the Zoning Ordinance. Any violation of the terms or conditions specified may be subject to enforcement action. 6. Revocation of Permit. This VTM approval shall be revocable for cause PL Ongoing in accordance with Chapter 9 of the Dublin Municipal Code and the State Subdivision Map Act. Any violation of the terms or conditions of this permit shall be subject to citation. 7. Requirements and Standard Conditions. The Applicant/ Developer Various Building shall comply with applicable City of Dublin Fire Prevention Bureau, Dublin Permit Public Works Department, Dublin Building Department, Dublin Police Issuance Services, Alameda County Flood Control District Zone 7, Livermore Amador Valley Transit Authority, Alameda County Public and Environmental Health, Dublin San Ramon Services District and the California Department of Health Services requirements and standard conditions except where superseded by the Development Agreement. Prior to issuance of building permits or the installation of any improvements related to this project, the Developer shall supply written statements from each such agency or department to the Planning Department, indicating that all applicable conditions required have been or will be met. 8. Required Permits. Developer shall obtain all permits required by other PW Building agencies including, but not limited to Zone 7 Water Agency, California Permit Department of Fish and Wildlife, Army Corps of Engineers, Regional Issuance Water Quality Control Board, Caltrans and provide copies of the permits to the Public Works Department. 9. Fees. Applicant/Developer shall pay all applicable fees in effect at the Various Building time of building permit issuance, including, but not limited to, Planning Permit fees, Building fees, Traffic Impact Fees, TVTC fees, Dublin San Ramon Issuance Services District fees, Public Facilities fees, Dublin Unified School District School Impact fees, Fire Facilities Impact fees, Alameda County Flood and Water Conservation District (Zone 7) Drainage and Water Connection fees; or any other fee that may be adopted and applicable except where superseded by the Development Agreement. 10. Indemnification. The Developer shall defend, indemnify, and hold ADM Ongoing harmless the City of Dublin and its agents, officers, and employees from any claim, action, or proceeding against the City of Dublin or its agents, officers, or employees to attack, set aside, void, or annul an approval of the City of Dublin or its advisory agency, appeal board, Planning Commission, City Council, Community Development Director, Zoning Administrator, or any other department, committee, or agency of the City to the extent such actions are brought within the time period required by Government Code Section 66499.37 or other applicable law; provided, however, that the Developer's duty to so defend, indemnify, and hold 5 of 23 COA # Condition Text Resp. Required Agency Prior to: harmless shall be subject to the City's promptly notifying the Developer of any said claim, action, or proceeding and the City's full cooperation in the defense of such actions or proceedings. 11. Clarification of Conditions. In the event that there needs to be PL, PW Ongoing clarification to the Conditions of Approval, the Director of Community Development and the City Engineer have the authority to clarify the intent of these Conditions of Approval to the Developer without going to a public hearing. The Director of Community Development and the City Engineer also have the authority to make minor modifications to these conditions without going to a public hearing in order for the Developer to fulfill needed improvements or mitigations resulting from impacts to this project. 12. Archaeology. Should any prehistoric, cultural, or historic artifacts be PL During exposed during excavation and construction operations, the Community Construction Development Department shall be notified and work shall cease immediately until an archaeologist, who is certified by the Society of California Archaeology (SCA) or the Society of Professional Archaeology (SOPA), is consulted to evaluate the significance of the find and suggest appropriate mitigation measures, if deemed necessary, prior to resuming ground breaking construction activities. Standardized procedures for evaluating accidental finds and discovery of human remains shall be followed as prescribed in Sections 15064.5 and 15126.4 of the California Environmental Quality Act Guidelines. Compliance with this condition required throughout construction. 13. Mitigation Monitoring Program. The Applicant/Developer shall comply PL Ongoing with the Dublin Crossing Final Environmental Impact Report (EIR) certified by City Council Resolution 186-13, including all mitigation measures, action programs, and implementation measures contained therein. The EIR is on file with the Community Development Department. 14. Affordable Housing. For all units above 1,600, the project shall conform PL Building to the Inclusionary Zoning Regulations in Chapter 8.68. Permit Issuance for each unit over 1,600 DUBLIN SAN RAMON SERVICES DISTRICT (DSRSD) 15. All easement dedications for DSRSD facilities shall be by separate DSRSD Acceptance of instrument irrevocably offered to DSRSD or by offer of dedication on the Final Map Final Map. 16. Prior to approval by the City for recordation, the Final Map shall be DSRSD Acceptance of submitted to and approved by DSRSD for easement locations, widths, Final Map and restrictions. PUBLIC WORKS 17. Requirements and Standard Conditions. The Applicant/Developer PW On -Going shall comply with applicable City of Dublin Fire Prevention Bureau, Dublin Public Works Department, Dublin Building Department, Dublin Police Services, Alameda County Flood Control District Zone 7, Livermore Amador Valley Transit Authority, Alameda Health Services requirements and standard conditions. Prior to issuance of building permits or the installation of any improvements related to this project, the Developer shall supply written statements from each such agency or department to the Planning Department, indicating that all applicable conditions required have been or will be met. 18. Required Permits. Developer shall obtain all permits required by other PW Issuance of agencies including, but not limited to Zone 7 Water Agency, California Grading Department of Fish and Wildlife, US Fish and Wildlife Service, Army Permit & On - Corps of Engineers, Regional Water Quality Control Board, Caltrans and Going 6of23 COA # Condition Text Resp. Required Agency Prior to: provide copies of the permits to the Public Works Department. The project shall be modified as needed to respond to the conditions of the permits. 19. Community Facilities District No. 2015-1 (Dublin Crossing) ("CFD PW First Final 2015-1"). The Owner shall submit a Request and Unanimous Approval Map for any of for Annexation and Landowner -Voter Ballot Form ("Form") requesting the the property be annexed into CFD No. 2015-1. The Form shall be neighborhood accompanied by an Annexation Map for CFD 2015-1. The Form and s Annexation Map shall be subject to City Engineer review and approval. 20. Community Facilities District No. 2017-1 (Dublin Crossing — Public PW First Final Services) ("CFD 2017-1"). The Owner shall submit a Request and Map for any of Unanimous Approval for Annexation and Landowner -Voter Ballot Form the ("Form") requesting the property be annexed into CFD No. 2017-1. The neighborhood Form shall be accompanied by an Annexation Map for CFD 2017-1. The s Form and Annexation Map shall be subject to City Engineer review and approval. 21. Ownership and Maintenance of Improvements. Ownership and PW On -Going maintenance of street right-of-ways, common area parcels and open space areas and improvements shall be by the City of Dublin, the Boulevard Master Homeowner's Association or Zone 7 as shown on the Boulevard Phases 4 and 5 Site Development Review Maintenance Responsibility Plans, except as modified by these Conditions of Approval. 22. Landscape Features within Public Right of way. The Developer shall PW Final Map enter into an "Agreement for Long Term Encroachments" with the City to allow the Boulevard Master Homeowner's Association or individual neighborhood Homeowner's Associations to maintain the landscape and decorative features within public Right of Way including frontage landscaping, decorative pavements and special features (i.e., walls, portals, benches, etc.) as generally shown in the Site Development Review exhibits. The Agreement shall identify the ownership of the special features and maintenance responsibilities. The Homeowner's Association will be responsible for maintaining the surface of all decorative pavements including restoration required as the result of utility repairs. 23. Covenants, Conditions and Restrictions (CC&Rs). A Homeowners PW Final Map Association(s) shall be formed by recordation of a declaration of Covenants, Conditions, and Restrictions to govern use and maintenance of the signage, landscape, decorative pavement and other features and structures within the public right of way contained in the Agreement for Long Term Encroachments; box culvert maintenance, wing wall, headwall, and debris clearing, all open space and common area landscaping; and all stormwater treatment and hydromodification measures including those on private parcels. Said declaration shall set forth the Association name, bylaws, rules and regulations. The CC&Rs shall also contain a provision that prohibits the amendment of those provisions of the CC&Rs without the City's approval. The CC&Rs shall ensure that there is adequate provision for the maintenance, in good repair and on a regular basis, the landscaping & irrigation, decorative pavements, median islands, fences, walls, drainage, lighting, signs and other related improvements. The Developer shall submit a copy of the CC&R document to the City for review and approval 24. Covenants, Conditions and Restrictions (CC&Rs). At a minimum the PW Final Map following statements or similar shall be included in the CC&Rs: • Stormwater Management Maintenance Agreement. The Development is subject to the Stormwater Management Maintenance Agreement dated and 7 of 23 COA # Condition Text Resp. Agency Required Prior to: recorded on as Document No. in the records of Alameda County, CA. It is intended that Stormwater Management Maintenance Agreements will be entered into by and between Declarant and the City for each Map which is recorded and such agreements shall collectively be Stormwater Management Maintenance Agreements as defined in this Section. • Under the Stormwater Management Maintenance Agreement, this Development is responsible for ensuring that the installed stormwater management measures remain in effective operating condition in perpetuity. Commencing on the date the Homeowners Association begins operation, the Association assumes the rights and duties of the Property Owner as defined in the Stormwater Management Maintenance Agreement. The Board shall have full right, power and authority to act on behalf of the Association, its Members and the homeowners under the Stormwater Management Maintenance Agreement. • On -lot bioretention areas: The Homeowner's Association shall be responsible for the maintenance of all stormwater management measures, including the bioretention areas on private lots. The private, on -lot bioretention areas shall be maintained in accordance with the Stormwater Management Maintenance Agreement and shall not be modified without written approval from the City of Dublin. • Stormwater Management Measure Maintenance: The stormwater management measures shall be inspected and maintained as detailed in the Stormwater Management Maintenance Agreement. The Association shall maintain an inspection and maintenance record on file made available to the City upon request. In addition, all on -site storm drains shall be cleaned at least annually before commencement of the rainy season (by October 1) of each year. • Storm Drainage Restrictions: As part of the original construction of the Development, stormwater management measures were installed within the Development in connection with the Development's drainage system. Neither the Association nor any Owner shall do any work, construct any improvement, place any landscaping or otherwise perform any action whatsoever which alters or interferes with the drainage pattern for any Lot or any portion of the Common Areas, except to the extent such alteration in drainage pattern is approved in writing by the City of Dublin. • Stormwater Management Maintenance Measures: No objects may be placed in or around any stormwater management measure which may impact functionality of the stormwater management measure. • Good Housekeeping: The Homeowner's Association shall be responsible for litter control and sweeping of all paved surfaces within the development. All private storm drain systems are to be cleaned immediately before the commencement of the rainy season (October 15). • Landscape Maintenance: Landscaping shall be designed with an efficient irrigation system to reduce runoff and promote surface infiltration. Landscaping shall also be designed and maintained to minimize the use of fertilizers, herbicides and pesticides. Each Owner, and the Association, is encouraged to use integrated pest management practices (less toxic pest management) as a first step in maintaining landscaping. Chemical pesticides and fertilizers should be employed as a last step in managing weeds and other pests, and shall not be applied prior to forecast rain. 8 of 23 COA # Condition Text Resp. Required Agency Prior to: 25. Transportation Fees. The Developer shall be responsible for payment PW Issuance of of Transportation Fees as outlined in Section 10 of the Dublin Crossings Building Development Agreement and Amendments. Fees will be payable at Permits & On - issuance of building permits. Going 26. Phased Improvements. Right-of-way dedication and installation of tract PW On -Going improvements may be done in phases as indicated on the Tentative Map subject to the review and approval of the City Engineer. With each phased Final Map, the City Engineer shall identify all improvements necessary to serve and access the phased lots created. All rights -of -way and improvements identified by the City Engineer for construction within the boundaries of each phase of the development shall be required with the Final Map for that phase. In addition, the City Engineer may require the Developer to perform off -site grading in order to conform site grading to the adjacent grade outside of the phase proposed for development. 27. Pedestrian Access and Sidewalk Easements. Five foot by five foot PW Approval of (5'x5') "turnaround" areas shall be provided at intervals of no less than Improvement two hundred feet (200') along sidewalks with a width of less than five feet Plans to meet current accessibility requirements. Pedestrian Access and Sidewalk Easements shall be dedicated over those areas of sidewalk located outside of the common area lots needed to provide the required "turnaround" areas. 28. Pedestrian Ramps. All pedestrian ramps shall be designed and PW Approval of constructed to provide direct access to marked or unmarked crosswalks. Improvement Each pedestrian ramp shall be oriented such that it is aligned and parallel Plans to the marked or unmarked crosswalk it is intended to serve. Pedestrian ramps serving more than one marked or unmarked crosswalk shall not be provided, unless specifically approved by the City Engineer. All pedestrian curb ramps serving Class I bikeway open to both bicycle and pedestrians shall be ADA compliant directional ramps and designed to provide a wider ramp width of at least 7 feet, unless otherwise approved by the City Engineer. 29. Bike Lanes. Bike Lanes on project frontage streets and other Backbone PW Approval of Streets shall be designed and constructed to provide a continuous bike Improvement lane facility. Dropping of bike lanes at or near the intersections or along Plans street segments shall not be allowed unless specifically approved by the City Engineer. Note — Backbone streets per Tract 8150 VTM are not covered by Ph. 4/5 SDR/VTM. 30. Sight Distance. All landscaping and any architectural features or PW Approval of monuments shall be limited to 30 inch height inside the sight triangles Improvement shown on the Sight Distance Exhibits of the Vesting Tentative Maps. Any Plans deviations from this rule shall be approved by the Traffic Engineer. 31. Rolled Curb. Prior to the approval of any Improvement Plans which PW Approval of include the use of the proposed 3 -inch Rolled Curb, the Developer shall Improvement submit gutter capacity calculations, signed and stamped by the Engineer Plans of Record, demonstrating that accumulated stormwater runoff will not overtop the 3 -inch curb under the design storm. 32. Stormwater Management. The provided Stormwater Treatment Plans PW Approval of are approved in concept only. The final Stormwater Management Plan Improvement for each neighborhood is subject to City Engineer approval prior to Plans & On - approval of the Improvement Plans for said neighborhood. Approval is Going subject to the developer providing the necessary plans, details, and calculations that demonstrate the plan complies with the standards established by the San Francisco Bay Regional Water Quality Control Board (RWQCB) National Pollutant Discharge Elimination System (NPDES) Municipal Regional Permit (MRP 2.0). 9of23 COA # Condition Text Resp. Required Agency Prior to: 33. Stormwater Management. If the neighborhood tracts are developed in PW On -Going phases, suitable stormwater treatment and hydromodification measures shall be installed with each phase such that the stormwater runoff from the impervious areas created or replaced within the boundaries of each phase shall be property treated and metered with stormwater treatment and hydromodification measures constructed with that phase or in previous phases. 34. Stormwater Management. The curb openings for bio-retention areas PW Approval of shall not be less than 18" wide unless otherwise demonstrated by sizing Improvement calculations that a 12" wide curb opening will be adequate to convey the Plans required treatment volume. 35. Stormwater Management. Planting used within the bio-retention areas PW Approval of shall be consistent with the approved list found in the Clean Water Improvement Program Technical Guidance and a 3" layer of pea gravel or an approved Plans non -floating mulch shall be applied within the bio-retention areas. 36. Hydromodification Measures. Hydromodification measures shall be PW Approval of completed and operational prior to the creation or replacement of Improvement impervious improvements on the subject parcel. Plans 37. Hydromodification Vaults. The hydromodification vaults to be located PW Prior to in the future Community Park shall be designed and constructed Approval of concurrent with the neighborhoods that it will serve. The Developer shall Improvement coordinate design of these vaults with the approved Park Master Plan to Plans of the ensure that there will be no conflict with any proposed future structures. first neighborhood that will be served 38. Stormwater Management Measures, on -lot bioretention areas. All PW Approval of on -lot stormwater management measures must be bounded by a design Improvement element approved by the City Engineer to delineate the stormwater Plans management measures from the rest of the landscaping in order to provide visual delineation for maintenance purposes. 39. Trash Capture. The project Stormwater Management Plan for each PW Approval of neighborhood shall incorporate trash capture measures such as screens, Improvement filters or CDS/Vortex units to address the requirements of Provision C.10 Plans of the Regional Water Quality Control Board (RWQCB) Municipal Regional Permit (MRP). Storm drain inlet trash capture devices shall meet both the full trash capture requirements of the Regional Water Control Board and allow for maintenance access as required by the Mosquito Abatement District. To the extent possible, trash capture devices shall be located such that long-term maintenance will be the responsibility of the Developer/Property Owner. 40. Stormwater Management Measures and Trash Capture Devices PW Approval of Geospatial Information. Prior to project acceptance, the developer Improvement must provide the City with a geospatial layer compatible with the City's Plans GIS system locating each stormwater management measure and trash capture device. 41. Storm Water Treatment Measures Maintenance PW Final Map Agreement. Developer shall enter into an Agreement with the City of Dublin that guarantees the property owner's perpetual maintenance obligation for all stormwater treatment measures and trash capture devices installed as part of the project. Said Agreement is required pursuant to the Municipal Regional Stormwater NPDES Permit, Order No. R2-20015-0049. Said permit requires the City to provide verification and assurance that all treatment devices will be properly operated and maintained. The Agreement shall be recorded against the property and shall run with the land. Said agreement shall include an additional exhibit 10 of 23 COA # Condition Text Resp. Required Agency Prior to: detailing that certain private lots include stormwater treatment measures and purchasers of those lots or purchasers of condominium units on those lots must sign the acknowledgement during escrow. 42. Stormwater Source Control. All stormwater source controls PW Acceptance of required under MRP 2.0, including but not limited to the following storm drain must be implemented: improvements 1. "No Dumping Drains to Bay" storm drain medallions per City Standard Detail CD -704 shall be placed on all public and private storm drain inlets. 2. Air Conditioning Condensate: Condensate from air conditioning units shall be directed to appropriately -sized landscaped areas or the ground. Rooftop Equipment (examples include but are not limited to exhaust hoods, motors, and pumps): Roof top equipment, other than that producing air conditioning condensate, must drain to the sanitary sewer, or be covered and have no discharge to the storm drain system. The applicant must contact Dublin San Ramon Services District for specific connection and discharge requirements. 43. Geotechnical Investigation. The Developer shall submit a design level PW Issuance of geotechnical investigation report for each phase defining and delineating Grading any seismic hazard. The report shall be prepared in accordance with Permits guidelines published by the State of California. The report is subject to review and approval by a City selected peer review consultant prior to the acceptance of the first Final map for each phase. The applicant shall pay all costs related to the required peer review. The recommendations of those geotechnical reports shall be incorporated into the project phases subject to the approval of the City Engineer. 44. Soils Report. The Developer shall submit a detailed soils report PW Prior to prepared by a qualified engineer, registered with the State of California. Approval of The required report shall include recommendations regarding pavement Improvement sections for all project streets including all internal streets. Grading Plans operations shall be in accordance with recommendations contained in the required soils report and grading shall be supervised by an engineer registered in the State of California to do such work. 45. Geotechnical Engineer Review and Approval. The Project PW Approval of Geotechnical Engineer shall be retained to review all final grading plans Grading and specifications. The Project Geotechnical Engineer shall approve all Permits grading plans prior to City approval and issuance of grading permits. 46. Building Setback to Top of Bank. The Developer shall provide PW Issuance of documentation confirming the review and approval of the designed Building building setbacks with existing creeks from Zone 7, the Geotechnical Permits Engineer of Record, and other approving agencies. 47. Demolition and Removal of Existing Underground Utilities. A PW Issuance of building demolition permit from the Building Department will be required Grading for the demolition and/or removal of underground utilities within 2' from Permits the building footprint. For the demolition or removal of underground utilities beyond 2' of the building, the Developer shall obtain a letter from the responsible Utility agency with original signature on company letterhead signifying that the underground facilities can be or have been removed. 48. Groundwater Wells. Any groundwater wells found on the project site PW Issuance of that are not needed for the project or groundwater basin management Grading shall be properly sealed and/or destroyed under a Zone 7 permit. The Permits Developer shall provide the City with a copy of this permit prior to grading permit issuance or approval of the first small lot final map, whichever comes first. 49. Grading. The disposal site and haul truck route for any off -haul dirt PW Approval of materials shall be subject to the review and approval by the City Engineer Grading Plans 11 of 23 COA # Condition Text Resp. Required Agency Prior to: prior to the approval the improvement plans or issuance of a Grading Permit. If the Developer does not own the parcel on which the proposed disposal site is located, the Developer shall provide the City with a Letter of Consent, signed by the current owner, approving the placement of off - haul material on their parcel. A grading plan may be required for the placement of the off -haul material. 50. Overland Release. The Developer shall design for an overland release PW Approval of that will not create standing water greater than 6" or to an elevation Grading Plans greater than the protective slope elevation around the building foundation, within the public or private road, court, driveway, parking, trails, pathways, landscape, and common areas. Overland release shall not drain into creeks unless otherwise approved by Zone 7 Water Agency. 51. Dust Control/Street Sweeping. The Developer shall provide adequate PW Construction; dust control measures at all times during the grading and hauling Ongoing operations. All trucks hauling export and import materials shall be provided with tarp cover at all times. Spillage of haul materials and mud - tracking on the haul routes shall be prevented at all times. Developer shall be responsible for sweeping of streets within, surrounding and adjacent to the project if it is determined that the tracking or accumulation of material on the streets is due to its construction activities. 52. Underground Obstructions. Prior to demolition, excavation and grading PW Grading on any portion of the project site, all underground obstructions (i.e., Operations debris, septic tanks, fuel tanks, barrels, chemical waste) shall be identified and removed pursuant to Federal, State and local regulations and subject to the review and approval by the City. Excavations shall be properly backfilled using structural fill, subject to the review and approval of the City Engineer. 53. Utilities. All new utility service connections, including electrical and PW Approval of communications, shall be installed underground. Electrical transformers Improvement shall be installed in underground vaults within an appropriate utility Plans easement or public service easement. 54. Backbone Street Light Spares. The Developer shall provide spare PW Issuance of quantities of street lights along the backbone streets of each phase, Building calculated at approximately ten percent of the total street lights subject to Permits the review and approval of the City Engineer. 55. Public Service Easements. Six foot (6') minimum Public Service PW Approval of Easement (PSE) shall be dedicated along all existing and proposed Improvement public streets and only public utility facilities/ infrastructures can be Plans located within this easement unless otherwise approved by the City Engineer. 56. Intersections: The design of the intersections shall be generally as PW Approval of shown on the Tentative Map and the Site Development Review. Improvement Improvement Plans shall include intersection layout details showing the Plans design for the ramps, sidewalks, entry walls, stop signs, landscape planters, street trees, crosswalk locations and decorative pavement to be approved by the City Engineer. Decorative pavement shall not be installed over traffic signal loops or pavement striping and markings. Stamped Asphalt Concrete Pavement will be allowed within crosswalks. Final design details shall be subject to review and approval by the City Engineer. Any decorative pavers/paving installed within City right-of-way shall be done to the satisfaction of the City Engineer. Maintenance costs of the decorative paving shall be the responsibility of the Homeowners Association (HOA). 12 of 23 COA # Condition Text Resp. Required Agency Prior to: 57. Fire Hydrants No Parking Zone. All fire hydrants shall have a no PW Approval of parking zone extending 15 feet on each side of the hydrant. Improvement Plans 58. Cross walks No Parking Zones. All crosswalks shall have a minimum PW Approval of 20 feet no parking zone at each traffic approach. Improvement Plans 59. Bicycle Parking. All bicycle parking (short and long term) locations shall PW Approval of be included in the Civil Design Plans and as well as on Landscape plans. Improvement Plans 60. Resource Agency Permits. Prior to the start of any grading of the site, PW Prior to all required permits shall be obtained from the US Army Corps of Issuance of Engineers, the San Francisco Bay Regional Water Quality Control Board, Grading the State of California Department of Fish and Game, and the US Fish Permit and Wildlife Service for the grading or alteration of wetland areas within the site. The project shall be modified as needed to respond to the conditions of the permits. 61. Private street and common area subdivision improvements. PW Final Map Common area improvements, private streets, private alleys and all other subdivision improvements owned or maintained by the homeowners' owners association are subject to review and approval by the City Engineer prior to Final Map approval and shall be included in the Tract Improvement Agreement for each respective tract. Such improvements include, but are not limited to: curb & gutter, pavement areas, sidewalks, access ramps & driveways; enhanced street paving; parking spaces; street lights (wired underground) and appurtenances; drainage facilities; utilities; landscape and irrigation facilities; open space landscaping; stormwater treatment facilities; striping and signage; and fire hydrants. 62. Private Street Easements. Public Utility Easements (PUE), Sanitary PW Final Map Sewer Easements (SSE) and Water Line Easements (WLE) shall be established over the entire private street right-of-ways within all subdivisions. The PUE, SSE and WLE dedication statements on each Final Map are to recite that the easements are available for, but not limited to, the installation, access and maintenance of sanitary and storm sewers, water, electrical and communication facilities. Project entry monument signs and walls shall not be located within these easements. 63. Private Street Easements. The Developer shall dedicate Emergency PW Final Map Vehicle Access Easements (EVAE) over the clear pavement width of all private streets and alleys. Easement geometry shall be subject to the approval of the City Engineer and Fire Marshall. 64. Monuments. Final Maps shall include private street monuments to be PW Monuments to set in all private streets. Private street monuments shall be set at all be shown on intersections and as determined by the City Engineer. Final Map and installed prior to acceptance of improvements 65. Landscape Plans. Developer shall submit design development PW Approval of Landscape Plans with the first plan check for the street improvement Improvement plans and final map for each respective tract. The Landscape Plans shall Plans show details, sections and supplemental information as necessary for design coordination of the various civil design features and elements including utility location to the satisfaction of the City Engineer. Complete Landscape Plans shall be concurrently approved with the Tract Improvement Agreement and Final Map. 13 of 23 COA # Condition Text Resp. Required Agency Prior to: 66. Street Light and Joint Trench Plans. Streetlight Plans and Joint Trench PW Approval of Plans shall be submitted with the first or second plan check for the street Improvement improvement plans and final map for each respective tract. Joint Plans trenches for public facilities shall be separated from private joint trenches, and to the extent possible, street lights shall not be placed inside bio- retention areas. The final streetlight plan and joint trench plan shall be completed prior to Final Map approval for each respective subdivision. 67. Parallel Parking Adjacent to Bio-retention areas. Parallel parking PW Approval of adjacent to Bio-retention areas will not be permitted on public streets. Improvement Plans 68. Regulatory Traffic Control and Accessibility Signs. In -tract PW Approval of Regulatory Traffic Control and Accessibility Signs shall conform to the Improvement CA Manual on Uniform Traffic Control Devices (MUTCD) Manual with no Plans exceptions. 69. Public Street Name Signs. All street name signs shall be compliant with PW Approval of the City and CA MUTCD Standard signs on all public street intersections Improvement and on all private street that are intersecting with public streets. Plans 70. Mailboxes. Any gang mailboxes located on public streets or at an PW Approval of intersection of a public street and private street, shall have two Improvement designated short term parking spaces for mail pick up. These spaces Plans shall not be counted towards the guest parking count. 71. Underground Bioretention. The required number of trees within an PW Approval of Underground Bioretention System shall be designed such that the type Improvement of tree will have a canopy and root limits that will cover the entire system Plans at maturity. TRACT 8370 (Neighborhood 19) 72. Horizon Parkway. Developer shall install improvements along the PW Prior to project's frontage as shown on the Tentative Map. Required frontage Approval of improvements shall include, but are not limited to the installation of 5' Improvement landscape strip inclusive of curb width, 8' and 10' sidewalk, 10' Class I Plans Trail, 8' parking, 12' dual turn lane, 6' high good neighbor fence, curb, gutter, drainage structures, stormwater treatment and hydromodification measures, street trees, landscaping, irrigation, utilities, street lights, signage, striping and fire hydrants. Note — Horizon Pkwy is not covered by the Ph 4/5 SDR/VTM. This is a Backbone roadway per the Tract 8150 Master VTM. 73. Private Streets (Parcels A -O). The Developer shall establish private PW Prior to street right-of-way and install complete street improvements, including Approval of landscaping, for the proposed private streets, Streets A thru D and Courts Improvement A thru Court O, within the development as shown on the Tentative Map Plans Tract 8370 and the Site Development Review package. 74. Traffic Index. Roadway pavement section for Horizon Parkway shall be PW Prior to designed using a Traffic Index of 9. Note — Horizon Pkwy is not covered Approval of by the Ph 4/5 SDR/VTM. This is a Backbone roadway per the Tract 8150 Improvement Master VTM. Plans Parcels P thru U, X, and Y. Parcels P thru U, X, and Y shall be private PW Final Map common area parcels to be owned and maintained by the Homeowner's Association. 75. Parcel V. Parcel V (HOA parcel) shall be a HOA parcel with Zone 7 PW Final Map Easement for Zone 7 Maintenance Area. 76. Parcel W. Parcel W (Drainage parcel) to be conveyed to Alameda PW Final Map County Zone 7 Flood Control District. 77. Lots I thru 91. Lots 1 thru 91 shall be for single family residential lots. PW Final Map 78. Special Flood Hazard Area. Portion of Neighborhood 19 is within the PW Prior to Special Flood Hazard Area designated as AE. The Developer shall Approval of submit flood studies and reports to determine the Base Flood Elevation(s) 14 of 23 COA # Condition Text Resp. Required Agency Prior to: (BFEs) for Neighborhoods 19. The lots that are within the Special Flood Improvement Hazard Area shall be labeled on the Vesting Tentative Map. A Conditional Plans Letter of Map Revision (CLOMR-F) was submitted to the City and FEMA for review in November 2017. A Letter of Map Revision (LOMR-F) shall be submitted to FEMA and receive approval prior to the issuance of the Certificate of Occupancy for each building within the flood zone. TRACT 8371 (Neighborhood 20) Horizon Parkway. Developer shall install improvements along the PW Prior to project's frontage as shown on the Tentative Map. Required frontage Approval of improvements shall include, but are not limited to the installation of 5' Improvement landscape strip inclusive of curb width, 8' sidewalk, 10' Class I Trail, 8' Plans parking, 12' dual turn lane, 6' high theme wall, curb, gutter, drainage structures, stormwater treatment and hydromodification measures, street trees, landscaping, irrigation, utilities, street lights, signage, striping and fire hydrants. Note — Horizon Pkwy is not covered by the Ph 4/5 SDR/VTM. This is a Backbone roadway per the Tract 8150 Master VTM. 79. Private Streets (Parcels A -J). The Developer shall establish private PW Prior to street right-of-way and install complete street improvements, including Approval of landscaping, for the proposed private streets, Streets E and F and Courts Improvement P thru Court W, within the development as shown on the Tentative Map Plans Tract 8371 and the Site Development Review package. 80. Traffic Index. Roadway pavement section for Horizon Parkway shall be PW Prior to designed using a Traffic Index of 9. Note — Horizon Pkwy is not covered Approval of by the Ph 4/5 SDR/VTM. This is a Backbone roadway per the Tract 8150 Improvement Master VTM. Plans 81. Parcel K. Parcel K shall be a private common area parcel to be owned PW Final Map and maintained by the Homeowner's Association. 82. Lots 1 thru 75. Lots 1 thru 75 shall be for single family residential lots. PW Final Map TRACT 8372 (Neighborhood 21, 22, and 23) 83. Horizon Parkway. Developer shall install improvements along the PW Prior to project's frontage as shown on the Tentative Map. Required frontage Approval of improvements shall include, but are not limited to the installation of 5' Improvement landscape strip inclusive of curb width, 11' Iron Horse Trail, 8' parking, Plans 12' dual turn lane, 6' high theme wall , curb, gutter, drainage structures, stormwater treatment and hydromodification measures, street trees, landscaping, irrigation, utilities, street lights, signage, striping, and fire hydrants. 84. Scarlett Drive. Developer shall install improvements along the project's PW Prior to frontage as shown on the Tentative Map. Required frontage Approval of improvements shall include, but are not limited to the installation of 5' Improvement landscape strip, 12' Iron Horse Trail, bike lane, curb, gutter, median, Plans wetland ditch, drainage structures, stormwater treatment and hydromodification measures, street trees, landscaping, irrigation, utilities, street lights, signage, striping and fire hydrants. 85. Dougherty Road. Developer shall install improvements along the PW Prior to project's frontage as shown on the Tentative Map. Required frontage Approval of improvements shall include, but are not limited to the installation of 5' Improvement landscape strip, 12' Iron Horse Trail, bike lane, curb, gutter, drainage Plans structures, stormwater treatment and hydromodification measures, street trees, landscaping, irrigation, utilities, street lights, signage, striping and fire hydrants. 86. Private Streets (Parcels A -S, X, Z, AA-AH thru J). The Developer shall PW Prior to establish private street right-of-way and install complete street Approval of improvements, including landscaping, for the proposed private streets, Improvement Streets G, H, I, J, K and M and Courts Y, Z, A2 -Z2, and A3 -F3, within the Plans 15 of 23 COA # Condition Text Resp. Required Agency Prior to: development as shown on the Tentative Map Tract 8372 and the Site Development Review package. 87. Traffic Index. Roadway pavement section for Horizon Parkway, Scarlett PW Prior to Dive, and Dougherty Road shall be designed using a Traffic Index of 9, Approval of 11 and 13, respectively. Improvement Plans 88. Parcels T -W, Y, Al. Parcels T -W, Y, and Al shall be a private common PW Final Map area parcel to be owned and maintained by the Homeowner's Association. Parcel AJ. The Developer shall dedicate public right-of-way for Scarlett PW Final Map Drive and Dougherty and install improvements along the project's frontage as shown on the Tentative Map. Required frontage improvements shall include, but are not limited to the installation of landscape strip inclusive of curb width, sidewalk, 12' Iron Horse Trail, curb, gutter, drainage structures, stormwater treatment and hydromodification measures, street trees, landscaping, irrigation, utilities, streetlights, signage, striping and fire hydrants. 89. Future HOA Parcel at corner of Horizon Parkway and Scarlett Drive. PW Final Map Excess right-of-way at Scarlett Drive by Horizon Parkway shall be Future HOA Parcel. 90. Lots 1 thru 62. Lots 1 thru 62 shall be for single family residential lots. PW Final Map 91. Lots 63 thru 97. Lots 63 thru 97 shall be for condominium residential PW Final Map units. 92. Ownership and Maintenance for 60" Army Storm Drain. Applicant PW Final Map shall work with the US Army Corp of Engineers and the City to execute the appropriate agreement and instruments and documents, including, but not limited to legal descriptions, plat maps, grant deeds, grants of easement, assigning maintenance responsibilities for the 60" storm drain over the applicable storm drainage facilities and appurtenances. TRACT 8373 (Neighborhood 24) 93. Horizon Parkway. Developer shall install improvements along the PW Prior to project's frontage as shown on the Tentative Map. Required frontage Approval of improvements shall include, but are not limited to the installation of 5' Improvement landscape strip inclusive of curb width, 8' sidewalk, 10' Class I Trail, 8' Plans parking, 12' dual turn lane, 6' high good neighbor fence, curb, gutter, drainage structures, stormwater treatment and hydromodification measures, street trees, landscaping, irrigation, utilities, street lights, signage, striping and fire hydrants. Note — Horizon Pkwy is not covered by the Ph 4/5 SDR/VTM. This is a Backbone roadway per the Tract 8150 Master VTM. 94. Private Streets (Parcels A -Y). The Developer shall establish private PW Prior to street right-of-way and install complete street improvements, including Approval of landscaping, for the proposed private streets, Streets N, O, and P and Improvement Courts G3 -Z3 and A4 -D4, within the development as shown on the Plans Tentative Map Tract 8373 and the Site Development Review package. 95. Traffic Index. Roadway pavement section for Horizon Parkway shall be PW Prior to designed using a Traffic Index of 9. Note — Horizon Pkwy is not covered Approval of by the Ph 4/5 SDR/VTM. This is a Backbone roadway per the Tract 8150 Improvement Master VTM. Plans 96. Parcels Z, AB thru AF. Parcels Z, AB thru AF shall be a private common PW Final Map area parcels to be owned and maintained by the Homeowner's Association. 97. Parcel AG. Parcel AG (HOA parcel) shall be a HOA parcel with Zone 7 PW Final Map Access Easement. 98. Parcel W. Parcel W (Drainage parcel) to be conveyed to Alameda PW Final Map County Zone 7 Flood Control District. 16 of 23 COA # Condition Text Resp. Required Agency Prior to: 99. Lots 1 thru 100. Lots 1 thru 100 shall be for single family residential lots. PW Final Map 100. Special Flood Hazard Area. Portion of Neighborhood 24 is within the PW Prior to Special Flood Hazard Area designated as AE. The Developer shall Approval of submit flood studies and reports to determine the Base Flood Elevation(s) Improvement (BFEs) for Neighborhoods 24. The lots that are within the Special Flood Plans Hazard Area shall be labeled on the Vesting Tentative Map. A Conditional Letter of Map Revision (CLOMR-F) was submitted to the City and FEMA for review in November 2017. A Letter of Map Revision (LOMR-F) shall be submitted to FEMA and receive approval prior to the issuance of the Certificate of Occupancy for each building within the flood zone. 101. Chabot Creek. The final civil design and landscape design of Chabot PW Prior to Creek improvements: paved access trail, riparian landscape within Zone Approval of 7's ownership parcel for Chabot Creek and within the access easement Improvement shall be subject to review and approval by Zone 7 or other public agency Plans responsible for the creek. 102. Maintenance of Chabot Creek. If the Developer is unsuccessful in PW Approval of reaching an agreement with Zone 7 or other public agency to maintain Second the realigned Chabot Creek (both above- and under -ground sections), Phase of Park the Developer shall enter into a "Maintenance Agreement" with the City Improvements to allow the Boulevard Master Homeowner's Association to maintain the open channel and/or box culvert sections of the alignment, maintenance responsibilities and minimum maintenance requirements to ensure that the facilities are maintained properly and will be operated in a manner that does not impede the use of the Community Park. The Agreement shall be subject to approval of the City Engineer, Maintenance responsibilities of the Homeowner's Association shall include, but shall not be limited to hydraulic performance of open channel and/or box culvert sections of the creek alignment; box culvert structure; dredging of channel; landscaping; slope stability; and removal of debris. 103. HOA Maintenance Agreements & Zone 7 Agreement. Applicant shall PW Prior to work with the City and Zone 7 to execute the appropriate agreements and Approval of instruments and documents, including, but not limited to legal Improvement descriptions, plat maps, grant deeds, grants of easement, assigning Plans maintenance responsibilities to the Boulevard Master HOA over the applicable storm drainage facilities and appurtenances. 104. Recreational Use License Agreement Amendment by Zone 7. PW Prior to Applicant shall work with the City and Zone 7 to execute an Amendment Approval of to the Recreational Use License Agreement and associated instruments Improvement and documents, including, but not limited to legal descriptions, plat maps, Plans grant deeds, grants of easement, quitclaims, to add the applicable storm drainage facilities and appurtenances to the existing agreement between the City and Zone 7. 105. Storm Drainage Facilities and Culvert Maintenance Agreement PW Prior to (HOA/City). Applicant shall work with the City to execute the appropriate Approval of agreement and instruments and documents, including, but not limited to Improvement legal descriptions, plat maps, grant deeds, grants of easement, assigning Plans maintenance responsibilities to the Boulevard Master HOA over the applicable storm drainage facilities and appurtenances. 106. Assignment Agreement (City to HOA). Applicant shall work with the PW Prior to City to execute an assignment agreement, and associated instruments Approval of and documents, including, but not limited to legal descriptions, plat maps, Improvement grant deeds, grants of easement, assigning maintenance responsibilities Plans and rights to enter to the Boulevard Master HOA over storm drainage facilities and appurtenances covered under the Amendment to the Recreational Use License Agreement between the City and Zone 7. 17 of 23 COA # Condition Text Resp. Required Agency Prior to: 107. Master Stormwater Management Maintenance (O&M) Agreement. PW Prior to Applicant shall work with the City to execute a master storm water Approval of operations and maintenance agreement (O&M Agreement) outlining the Improvement responsibilities of the Boulevard Master HOA over the clean water (i.e. Plans C.3 and C.10) facilities and appurtenances throughout the entire Boulevard development. PUBLIC WORKS STANDARD CONDITIONS: 108. Developer shall comply with the City of Dublin Public Works Standard PW On -going Conditions of Approval contained below ("Standard Condition") unless specifically modified by Project Specific Conditions of Approval above. 109. The Developer shall comply with the Subdivision Map Act, the City of PW On -going Dublin Subdivision, and Grading Ordinances, the City of Dublin Public Works Standards and Policies, the most current requirements of the State Code Title 24 and the Americans with Disabilities Act with regard to accessibility, and all building and fire codes and ordinances in effect at the time of building permit. All public improvements constructed by Developer and to be dedicated to the City are hereby identified as "public works" under Labor Code section 1771. Accordingly, Developer, in constructing such improvements, shall comply with the Prevailing Wage Law (Labor Code. Sects. 1720 and following). 110. The Developer shall defend, indemnify, and hold harmless the City of PW On -going Dublin and its agents, officers, and employees from any claim, action, or proceeding against the City of Dublin or its agents, officers, or employees to attack, set aside, void, or annul an approval of the City of Dublin or its advisory agency, appeal board, Planning Commission, City Council, Community Development Director, Zoning Administrator, or any other department, committee, or agency of the City to the extent such actions are brought within the time period required by Government Code Section 66499.37 or other applicable law; provided, however, that The Developer's duty to so defend, indemnify, and hold harmless shall be subject to the City's promptly notifying The Developer of any said claim, action, or proceeding and the City's full cooperation in the defense of such actions or proceedings. 111. In the event that there needs to be clarification to these Conditions of PW On -going Approval, the Director of Community Development and the City Engineer have the authority to clarify the intent of these Conditions of Approval to the Developer without going to a public hearing. The Director of Community Development and the City Engineer also have the authority to make minor modifications to these conditions without going to a public hearing in order for the Developer to fulfill needed improvements or mitigations resulting from impacts of this project. 112. If there are conflicts between the Vesting Tentative Map approval and the PW On -going SDR approval pertaining to mapping or public improvements the Tentative Map shall take precedent. AGREEMENTS AND BONDS 113. The Developer shall enter into a Tract Improvement Agreement with the PW First Final City for all public improvements including any required offsite storm Map and drainage or roadway improvements that are needed to serve the Tract Successive that have not been bonded with another Tract Improvement Agreement. Maps 114. The Developer shall provide performance (100%), and labor & material PW First Final (100%) securities to guarantee the tract improvements, approved by the Map and City Engineer, prior to execution of the Tract Improvement Agreement Successive and approval of the Final Map. (Note: Upon acceptance of the Maps improvements, the performance security may be replaced with a maintenance bond that is 25% of the value of the performance security.) FEES 18 of 23 COA # Condition Text Resp. Required Agency Prior to: 115. The Developer shall pay all applicable fees in effect at the time of building PW Zone 7 and permit issuance including, but not limited to, Planning fees, Building fees, Parkland In Dublin San Ramon Services District fees, Public Facilities fees, Dublin Lieu Fees due Unified School District School Impact fees, Public Works Traffic Impact prior to filling fees, Alameda County Fire Services fees, Noise Mitigation fees, each Final Inclusionary Housing In -Lieu fees, Alameda County Flood and Water Map, other Conservation District (Zone 7) Drainage and Water Connection fees and fees required any other fees as noted in the Development Agreement. with issuance of building permits PERMITS 116. Developer shall obtain an Encroachment Permit from the Public Works PW Prior to Start Department for all construction activity within the public right-of-way of of Work any street where the City has accepted the improvements. The encroachment permit may require surety for slurry seal and restriping. At the discretion of the City Engineer an encroachment for work specifically included in an Improvement Agreement may not be required. 117. Developer shall obtain a Grading / Sitework Permit from the Public Works PW Prior to Start Department for all grading and private site improvements that serves of Work more than one lot or residential condominium unit. 118. Developer shall obtain all permits required by other agencies including, PW Prior to Start but not limited to Alameda County Flood Control and Water Conservation of Work District Zone 7, California Department of Fish and Game, Army Corps of Engineers, Regional Water Quality Control Board, Caltrans and provide copies of the permits to the Public Works Department. SUBMITTALS 119. All submittals of plans and Final Maps shall comply with the requirements PW Prior to of the "City of Dublin Public Works Department Improvement Plan Approval of Submittal Requirements", and the "City of Dublin Improvement Plan Improvement Review Check List". Plans or Final Map 120. The Developer will be responsible for submittals and reviews to obtain PW Prior to the approvals of all participating non -City agencies. The Alameda County Approval of Fire Department and the Dublin San Ramon Services District shall Improvement approve and sign the Improvement Plans. Plans or Final Map 121. Developer shall submit a Geotechnical Report, which includes street PW Prior to pavement sections and grading recommendations. Approval of Improvement Plans or Final Map 122. Developer shall provide the Public Works Department a digital vectorized PW Acceptance of file of the "master" CAD files for the project when the Final Map has been Improvements approved. Digital raster copies are not acceptable. The digital vectorized and Release files shall be in AutoCAD 14 or higher drawing format. Drawing units shall of Bonds be decimal with the precision of the Final Map. All objects and entities in layers shall be colored by layer and named in English. All submitted drawings shall use the Global Coordinate System of USA, California, NAD 83 California State Plane, Zone III, and U.S. foot. FINAL MAP 123. All Final Maps shall be substantially in accordance with the Tentative PW Approval of Maps approved with this application, unless otherwise modified by these Final Map conditions. Multiple final maps may be filed in phases, provided that each phase is consistent with the tentative map, that phasing progresses in an orderly and logical manner and adequate infrastructure is installed with 19 of 23 COA # Condition Text Resp. Required Agency Prior to: each phase to serve that phase as a stand-alone project that is not dependent upon future phasing for infrastructure. 124. All rights -of -way and easement dedications required by the Tentative PW Approval of Map shall be shown on the Final Map. Final Map 125. Any phasing of the final mapping or improvements of a Tentative Map is PW Approval of subject to the approval and conditions of the City Engineer. Final Map 126. Street names shall be assigned to each public/private street pursuant to PW Approval of Municipal Code Chapter 7.08. The approved street names shall be Final Map indicated on the Final Map. 127. All Final Maps shall include street monuments to be set in all public PW Monuments to streets. be shown on final map and installed prior to acceptance of improvements EASEMENTS 128. The Developer shall obtain abandonment from all applicable public PW Approval of agencies of existing easements and right of ways that will no longer be Improvement used. Plans 129. The Developer shall acquire easements, and/or obtain rights -of -entry PW Approval of from the adjacent property owners for any improvements on their Improvement property. The easements and/or rights -of -entry shall be in writing and Plans copies furnished to the City Engineer. GRADING 130. The Grading Plan shall be in conformance with the recommendations of PW Approval of the Geotechnical Report, the approved Tentative Map and/or Site grading plans Development Review, and the City design standards & ordinances. In or issuance of case of conflict between the soil engineer's recommendations and City grading ordinances, the City Engineer shall determine which shall apply. permits; going 131. A detailed Erosion Control Plan shall be included with the Grading Plan PW Approval of approval. The plan shall include detailed design, location, and grading plans maintenance criteria of all erosion and sedimentation control measures. or issuance of grading permits; going 132. Tiebacks or structural fabric for retaining walls shall not cross property PW Approval of lines, or shall be located a minimum of 2' below the finished grade of the grading plans upper lot, or issuance of grading permits; going IMPROVEMENTS 133. Applicant shall meet with the trash collection agency during plan check PW Approval of review for the distance, maneuvering and pick-up requirements for trash Improvement collection. Documentation of results, recommendations, requirements, Plans and approval generated from this meeting shall be provided to the City. 134. Hydrology and Hydraulic calculations using shall be submitted for PW Approval of approval by the City Engineer. Alameda County published an updated Improvement version of the Alameda County Hydrology & Hydraulics Manual. The Plans H&H Manual includes updates to calculating runoff and should be used as the basis for your hydrology and hydraulics design of flood control facilities in Alameda County. The manual is available for download at acfloodcontrol.org/hh-manual. 20 of 23 COA # Condition Text Resp. Required Agency Prior to: 135. The public improvements shall be constructed generally as shown on the PW Approval of Tentative Map and/or Site Development Review. However, the approval grading plans of the Tentative Map and/or Site Development Review is not an approval or issuance of of the specific design of the drainage, sanitary sewer, water, and street grading improvements. permits; On- going 136. All public improvements shall conform to the City of Dublin Standard PW Approval of Plans and design requirements and as approved by the City Engineer. Improvement Plans or start of construction; On -going 137. The asphalt concrete (AC) section of the roadway for public streets shall PW Approval of be a minimum of 4" thick. Improvement Plans 138. The height of walls, gates, signs, monuments, pilasters, and any other PW Approval of architectural and landscaping features shall be kept below 30 inches Improvement inside the intersection visibility zone. The intersection visibility zones shall Plans or start be determined by the City Traffic Engineer, of construction; On -going 139. Public streets shall be at a minimum 1% slope with minimum gutter flow PW Approval of of 0.7% around bumpouts. Private streets and alleys shall be at minimum Improvement 0.5% slope. Intersections shall have a maximum 6% slope through Plans or start intersections and 2% maximum cross slope, of construction; On -going 140. Curb Returns on arterial and collector streets shall be 40 -foot radius, all PW Approval of internal public streets curb returns shall be minimum 30 -foot radius (36- Improvement foot with bump outs) and private streets/alleys shall be a minimum 20- Plans or start foot radius, or as shown on this Tentative Map, and as approved by the of Fire Dept. and as approved by the City Engineer. Curb ramp locations construction; and design shall conform to the most current Title 24 and Americans with On -going Disabilities Act requirements and as approved by the City Traffic Engineer. 141. The Developer shall install all traffic signs and pavement marking as PW Occupancy of required by the City Engineer. Units or Acceptance of Improvements 142. Street light standards and luminaries shall be designed and installed per PW Occupancy of approval of the City Engineer. To the extent possible, street lights shall Units or not be located within bio-retention areas The maximum voltage drop for Acceptance of streetlights is 5%. Improvements 143. The Developer shall construct bus stops and shelters at the locations PW Occupancy of designated and approved by the LAVTA and the City Engineer. The Units or Developer shall pay the cost of procuring and installing these Acceptance of improvements. Improvements 144. Developer shall construct all potable and recycled water and sanitary PW Occupancy of sewer facilities required to serve the project in accordance with DSRSD Units or master plans, standards, specifications and requirements. Acceptance of Improvements 145. Fire hydrant locations shall be approved by the Alameda County Fire PW Occupancy of Department. A raised reflector blue traffic marker shall be installed in the Units or street opposite each hydrant. Acceptance of Improvements 21 of 23 COA # Condition Text Resp. Required Agency Prior to: 146. The Developer shall furnish and install street name signs for the project PW Occupancy of to the satisfaction of the City Engineer. Units or Acceptance of Improvements 147. Developer shall construct gas, electric, cable TV and communication PW Occupancy of improvements within the fronting streets and as necessary to serve the Units or project and the future adjacent parcels as approved by the City Engineer Acceptance of and the various Public Utility agencies. Improvements 148. All electrical, gas, telephone, and Cable TV utilities, shall be underground PW Occupancy of in accordance with the City policies and ordinances. All utilities shall be Units or located and provided within public utility easements and sized to meet Acceptance of utility company standards. Improvements 149. All utility vaults, boxes and structures, unless specifically approved PW Occupancy of otherwise by the City Engineer, shall be underground and placed in Units or landscape areas and screened from public view. Prior to Joint Trench Acceptance of Plan approval, landscape drawings shall be submitted to the City showing Improvements the location of all utility vaults, boxes and structures and adjacent or Approval of landscape features and plantings. The Joint Trench Plans shall be signed Improvement by the City Engineer prior to construction of the joint trench Plans improvements. 150. Vertical and horizontal curves and sight distances shall be designed per PW Approval of Caltrans Highway Design Manual (HDM) for all public streets. A vertical Improvement curve shall be required in public streets for grades that have an algebraic Plans difference of 1% and vertical curves shall be a minimum 50 feet in length. Private streets shall be designed with these same criteria wherever practical, as determined between the City Engineer and Design Engineer of Record. CONSTRUCTION 151. The Erosion Control Plan shall be implemented between October 1st and PW On -Going as April 30th unless otherwise allowed in writing by the City Engineer. The needed Developer will be responsible for maintaining erosion and sediment control measures for one year following the City's acceptance of the subdivision improvements. 152. If archaeological materials are encountered during construction, PW On -Going as construction within 100 feet of these materials shall be halted until a needed professional Archaeologist who is certified by the Society of California Archaeology (SCA) or the Society of Professional Archaeology (SOPA) has had an opportunity to evaluate the significance of the find and suggest appropriate mitigation measures. 153. Construction activities, including the maintenance and warming of PW On -Going as equipment, shall be limited to Monday through Friday, and non -City needed holidays, between the hours of 7:30 a.m. and 5:30 p.m. except as otherwise approved by the City Engineer. Extended hours or Saturday work will be considered by the City Engineer on a case -by -case basis. 154. Developer shall prepare a construction noise management plan that PW Start of identifies measures to be taken to minimize construction noise on construction surrounding developed properties. The plan shall include hours of implementatio construction operation, use of mufflers on construction equipment, speed n and on - limit for construction traffic, haul routes and identify a noise monitor. going as Specific noise management measures shall be provided prior to project needed construction. 155. Developer shall prepare a plan for construction traffic interface with public PW Start of traffic on any existing public street. Construction traffic and parking may construction be subject to specific requirements by the City Engineer. implementatio n and on - 22 of 23 COA # Condition Text Resp. Required Agency Prior to: going as needed 156. The Developer shall be responsible for controlling any rodent, mosquito, PW On -Going or other pest problem due to construction activities. 157. The Developer shall be responsible for watering or other dust -palliative PW On -Going measures to control dust as conditions warrant or as directed by the City Engineer. 158. The Developer shall provide the Public Works Department with a letter PW Issuance of from a registered civil engineer or surveyor stating that the building pads Building have been graded to within 0.1 feet of the grades shown on the approved Permits or Grading Plans, and that the top & toe of banks and retaining walls are at Acceptance of the locations shown on the approved Grading Plans. Improvements STORM WATER QUALITY (NPDES) _ 159. Prior to any clearing or grading, the Developer shall provide the City PW Start of any evidence that a Notice of Intent (NOI) has been sent to the California construction State Water Resources Control Board per the requirements of the NPDES. A copy of the Storm Water Pollution Prevention Plan (SWPPP) shall be provided to the Public Works Department and be kept at the construction site. 160. The Storm Water Pollution Prevention Plan (SWPPP) shall identify the PW SWPPP to be Best Management Practices (BMPs) appropriate to the project prepared prior construction activities. The SWPPP shall include the erosion control to approval of measures in accordance with the regulations outlined in the most current improvement version of the ABAG Erosion and Sediment Control Handbook or State plans, Construction Best Management Practices Handbook. The Developer is implementatio responsible for ensuring that all contractors implement all storm water n prior to start pollution prevention measures in the SWPPP. of construction and on -going as needed PASSED, APPROVED AND ADOPTED this 8th day of May 2018 by the following vote: AYES: Bhuthimethee, Kothari, Mittan, Qureshi, Wright NOES: ABSENT: ABSTAIN: 7 7JT - Planning Commission Chair ATTEST: Assistant Community Development Director 23 of 23