HomeMy WebLinkAboutReso 121-13 Storm Drain Improvements RESOLUTION NO. 121 - 13
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
AWARDING CONTRACT NO. 13-08,
2013 STORM DRAIN SYSTEM IMPROVEMENTS CONTRACT TO SANACT INC. DBA ROTO-
ROOTER
WHEREAS, the City of Dublin did, on July 2, 2013, publicly open, examine, and declare
all sealed bids for doing the work described in the approved Plans, Specifications, and
Modifications for Contract No. 13-08, 2013 Storm Drain System Improvements Contract, which
Plans, Specifications, and Modifications are hereby expressly referred to as a description of
said work and for all particulars relative to the proceedings under the request for bids; and
WHEREAS, said bids were submitted to the Public Works Director, who has reviewed
the bids to determine the lowest bid which was responsive to the requirements of the bid
documents.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby award Contract No. 13-08, 2013 Storm Drain System Improvements, to the lowest
responsible bidder therefore, to wit, Sanact Inc. dba Roto-Rooter, at a bid of Ninety Seven
Thousand, Six Hundred Ten Dollars and No Cents ($97,610.00), the particulars of which bid are
on file in the office of the Public Works Director.
BE IT FURTHER RESOLVED that the City Manager is authorized to execute the
Agreement.
PASSED, APPROVED AND ADOPTED this 16th day of July, 2013, by the following vote:
AYES: Councilmembers Biddle, Gupta, Hart, Haubert, and Mayor Sbranti
NOES: None
ABSENT: None
ABSTAIN: None N
Mayor
ATTE
P Oct
City Clerk
Reso No. 121-13, Adopted 7-16-13, Item 4.8 Page 1 of 1