HomeMy WebLinkAboutItem 5.3 Forest Park Project CIP No. PK0322 Contract Change Order and Project Acceptance Authorization Agenda Item 5.3
STAFF REPORT
CITY COUNCIL
Page 1 of 3
DATE: April 21, 2026
TO: Honorable Mayor and City Councilmembers
FROM: Colleen Tribby, City Manager
SUBJECT:
Forest Park Project, CIP No. PK0322, Contract Change Order and Project
Acceptance Authorization
Prepared by: Rosemary Alex, Parks Planner
EXECUTIVE SUMMARY:
The City Council will consider a resolution approving an increase to the contract change order
authority of the City Manager by $20,000 to compensate the contractor, Suarez & Munoz
Construction, Inc., for needed irrigation system revisions for Forest Park Project, CIP No.
PK0322. The resolution also authorizes the City Manager to accept the Project upon
completion.
STAFF RECOMMENDATION:
Adopt the Resolution Approving a Contract Change Order with Suarez & Munoz Construction,
Inc. and Authorizing the City Manager to Accept the Forest Park Project, CIP No. PK0322,
Upon Completion.
FINANCIAL IMPACT:
Sufficient budget is available within the Forest Park Project to absorb the increased cost
associated with the recommended action, as shown below:
Project Funding Source
Public Facility Fees $2,898,947
General Fund
Measure BB Bike and Ped Fund (Alameda CTC)
Measure BB Local Streets Fund (Alameda CTC)
$350,000
$250,000
$40,000
Total Funding $3,538,947
77
Page 2 of 3
Expenditures
Construction Contract with Change Orders
Additional Change Order Contingency
$2,416,700
$20,000
Contract Services, Design, Salary, and Testing $1,098,276
Total Expenditures $3,534,976
Estimated Remaining Project Balance $3,971
DESCRIPTION:
On July 16, 2024 the City Council adopted Resolution No. 82-24 awarding a construction
contract of $2,197,000 to Suarez & Munoz Construction, Inc. for Forest Park Project, CIP No.
PK0322, and authorizing the City Manager to approve change orders up to a contingency
amount of $219,700 for a total potential construction contract of $2,416,700. The Project
improvements include the following elements:
A multi-use court that allows for basketball and futsal
Picnic tables and shade elements
Reservable picnic area with shade elements and BBQ
Fitness stations
Playgrounds for ages 2 to 5 years and 5 to 12 years
A grass area for free play
Interior pathways for circulation and exercise
Modifications to ADA ramps along Central Parkway, Twain Hart, and Pino Grande
Roads
Realignment of crosswalk intersection at Central Parkway and T wain Hart Road
In November 2025 during the Project’s maintenance period, Dublin San Ramon Services
District notified the City that the temporary potable water meter could be converted to a
permanent meter for recycled water service. In December 2025 the meter was changed and in
January 2026 an irrigation audit revealed lower water pressure than the initial system design.
To prevent burning of the grass during the summer and improve spray coverage, the irrigation
needs modifications. Since previously approved change orders utilized the full amount of the
Project’s contingency, Staff is seeking approval to increase the City Manager’s change order
authority by $20,000 for a total potential construction contract amount of $2,436,700.
Staff has determined that the Project will be complete and ready for acceptance upon
implementation of the irrigation modifications. Staff is seeking City Council approval to provide
the City Manager the authority to accept the Project upon completion.
78
Page 3 of 3
STRATEGIC PLAN INITIATIVE:
None.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
The City Council Agenda was posted. A copy of this report was sent to Suarez & Munoz
Construction, Inc.
ATTACHMENTS:
1) Resolution Approving a Contract Change Order with Suarez & Munoz Construction, Inc.
and Authorizing the City Manager to Accept the Forest Park Project, CIP No. PK0322,
Upon Completion
2) Resolution No. 82-24 Approving the Plans and Specifications and Awarding a Contract to
Suarez & Munoz Construction, Inc. for the Forest Park Project, CIP No. P K0322
3) CIP No. PK0322
79
Attachment 1
Reso. No. XX-26, Item X.X, Adopted XX/XX/2026 Page 1 of 2
RESOLUTION NO. XX – 26
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING A CONTRACT CHANGE ORDER WITH SUAREZ & MUNOZ CONSTRUCTION, INC.
AND AUTHORIZING THE CITY MANAGER TO ACCEPT THE FOREST PARK PROJECT, CIP NO.
PK0322, UPON COMPLETION
WHEREAS, on July 16, 2024, the City Council adopted Resolution No. 82-24 awarding a
construction contract of $2,197,000 to Suarez & Munoz Construction, Inc. for the Forest Park Project,
CIP No. PK0322 (Project), and authorizing the City Manager to approve change orders up to a
contingency amount of $219,700 for a total potential construction contract amount of $2,416,700; and
WHEREAS, in November 2025 during the Project’s maintenance period, Dublin San Ramon
Services District notified the City that the temporary potable water meter could be converted to a
permanent meter for recycled water service; and
WHEREAS, in December 2025 the meter was changed and in January 2026 an irrigation audit
revealed lower water pressure than the initial system design ; and
WHEREAS, to prevent burning of the grass during the summer and improve spray coverage,
the irrigation system needs modifications; and
WHEREAS, compensating the contractor for the additional cost of the modifications requires an
increase of $20,000 to the City Manager’s change order authority, for a total change order authority of
$239,700 and a total potential construction cost to $2,436,700.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby
authorize the City Manager, or designee, to approve up to $239,700 in Contract Change Orders with
Suarez & Munoz Construction, Inc.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize
the City Manager, or designee, to accept the Forest Park Project, CIP No. PK0322, upon completion
of Project in accordance with plans and specifications, and any approved modifications thereof, to the
satisfaction of the City Engineer of the City of Dublin.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize
the City Manager or designee to release the retention, if after 35 days of filing the Notice of Completion
there are no subcontractor claims.
{Signatures on the Following Page}
80
Reso. No. XX-26, Item X.X, Adopted XX/XX/2026 Page 2 of 2
PASSED, APPROVED AND ADOPTED BY the City Council of the City of Dublin, on this 21st
day of April, 2026 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
______________________________
Mayor
ATTEST:
_________________________________
City Clerk
81
Reso. No. 82-24, Item 5.9, Adopted 07/16/2024 Page 1 of 2
RESOLUTION NO. 82 – 24
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING THE PLANS AND SPECIFICATIONS AND AWARDING A CONTRACT TO
SUAREZ AND MUNOZ CONSTRUCTION, INC. FOR THE FOREST PARK PROJECT, CIP
NO. PK0322
WHEREAS, on December 6, 2022 the City Council approved the schematic design for the
Forest Park Project (Project), formally known as Jordan Ranch Neighborhood Square, located
along Central Parkway, Pino Grande Road, Twain Harte Road, and Pandora Way; and
WHEREAS, the design team has completed the plans and specifications for the Project;
and
WHEREAS, the City of Dublin did, on May 23, 2024, publicly open, examine, and declare
all sealed bids for doing the work described in the approved plans and specifications for the
Project, which plans and specifications are hereby expressly referred to for a description of said
work and for all particulars relative to the proceedings under the request for bids; and
WHEREAS, said bids were submitted to Staff and Suarez and Munoz Construction, Inc.
was determined to be the lowest responsive and responsible bidder for doing said work.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin hereby
approves the Plans and Specifications for the Project.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby award
the Contract for the Project to the lowest responsive and responsible bidder, Suarez and Munoz
Construction, Inc., at a bid of two million one-hundred and ninety- seven thousand dollars and zero
cents ($2,197,000.00), the particulars of which bids are on file in the Office of the Public Works
Director.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
authorize the City Manager or designee to approve the Project contract change orders based on
the appropriated funds designated for the Project up to the contingency amount of two-hundred
nineteen thousand seven-hundred dollars and zero cents ($219,700.00).
BE IT FURTHER RESOLVED that the City Manager or designee is authorized to execute
the Construction Agreement for the Project with Suarez and Munoz Construction, Inc. and make
any necessary, non-substantive changes to carry out the intent of this Resolution.
Signatures on the Following Page}
Docusign Envelope ID: B587DB3E-92DB-4BC8-84C5-641C427B432C
Attachment 2
82
Reso. No. 82-24, Item 5.9, Adopted 07/16/2024 Page 2 of 2
PASSED, APPROVED AND ADOPTED this 16th day of July 2024, by the following vote:
AYES: Councilmembers Hu, Josey, Qaadri, Thalblum and Mayor McCorriston
NOES:
ABSENT:
ABSTAIN:
Mayor
ATTEST:
City Clerk