RESOLUTION NO. 86-010
A RESOLUTION OF THE PLANNING COMMISSION
OF THE CITY OF DUBLIN
APPROVING IN PART THE APPEAL OF WILLIAM GLASS AND ASSOCIATES, ARCHITECTS, INC.
CONCERNING PA 85-096 GEMCO STORE REMODEL - SITE DEVELOPMENT REVIEW
AND AMENDING THE ZONING ADMINISTRATOR ACTION
OF JANUARY 27, 1986, CONDITIONALLY APPROVING THE REQUEST
TO MODIFY THE ARCHITECTURAL DETAIL OF THE STOREFRONT ELEVATION OF
THE EXISTING GEMCO STORE AND TO COVER AND ENCLOSE A PORTION
OF THE EXISTING OPEN-AIR NURSERY AREA, 7200 AMADOR PLAZA ROAD.
WHEREAS, William Glass and Associates, Architects, Inc., on behalf of
Lucky Stores, Inc./Gemco Division, filed a Site Development Review application
requesting approval to modify the storefront elevation of the existing Gemco
Store (tying the roof detail to the relocated store entry area), and to cover
and enclose 1,100± square feet of the existing open-air nursery area, at the
Dublin Gemco Store at 7200 Amador Plaza Road, more specifically described as
APN 941-305-29-02; and
WHEREAS, the application was reviewed in accordance with the
provisions of the California Environmental Quality Act and was determined to be
categorically exempt; and
WHEREAS, the Zoning Administrator found that the Site Development
Review request would not have a significant environmental impact; and
WHEREAS, the Zoning Administrator conditionally approved the request
on January 27, 1986, subject to an appeal period extending to February 6, 1986;
and
WHEREAS, the architectural firm for the project, William Glass and
Associates, Architects, Inc., filed a written appeal on behalf of the applicant
on February 4, 1986, indicating problems with Conditions 8, 9, 10, 12, 14, 15,
and 18 as well as those standard conditions which would apply to off-site or
common area improvements as difficulties were envisioned for the applicant in
securing the necessary approvals from numerous owners, tenants, and lenders who
have the right of refusal over any common area changes or improvements in the
subject shopping center; and
WHEREAS, the Planning Commission did hold a public hearing on said
appeal on March 3, 1986; and
WHEREAS, proper notice of said public hearing was given in all
respects as required by law; and
WHEREAS, the Planning Commission finds that the Site Development
Review will not have a significant environmental impact; and
WHEREAS, the Staff Report was submitted recommending the appeal be
denied and that the Zoning Administrator's decision of January 27, 1986,
conditionally approving the request be upheld; and
WHEREAS, the Planning commission did hear and consider all said
reports, recommendations and testimony herein above set forth; and
WHEREAS, an established City General Plan policy calls for the
provision of a vehicular interconnection between the subject shopping center
and the Dublin Library property (APN 941-305-12-2);
-1-
•
•
WHEREAS, the Planning Commission, in acknowledgement of the
constraints the applicant may face in securing the necessary approvals from
adjoining commercial tenants, landowners, lenders, etc., who have some level of
review authority over changes in the common areas of the subject shopping
center, adjusted the subject language in the draft Resolution for Conditions
#9, #10 and #18 to require the applicant to demonstrate that they have
diligently pursued the necessary approvals for easements to provide for the
physical improvements called for in the Conditions.
NOW, THEREFORE, BE IT RESOLVED THAT THE Planning Commission does
hereby find that:
1. The proposed remodel of the Gemco Store serves the public need by expanding
the retail service area available to the general public.
2. This project will be properly related to other land uses and transportation
and service facilities in the vicinity.
3. This project will not materially adversely affect the health or safety of
persons residing or working in the vicinity or be materially detrimental to
the public welfare or injurious to property or improvements in the
neighborhood, as all applicable regulations will be met.
4. This project will not be contrary to the specific intent clauses for
performance standards established for the District in which it is to be
located.
5. All provisions of Section 8-95.0 through 8-95.8 Site Development Review, of
the Zoning Ordinance are complied with.
6. Consistent with Section 8-95.0, this project, as conditioned by this
approval, will promote orderly, attractive, and harmonious development,
recognize environmental limitations on development, stabilize land values
and investments, and promote the general welfare by preventing
establishment of uses or erection of structures having qualities which
would not meet the specific intent clauses or performance standards set
forth in the Zoning Ordinance and which are not consistent with their
environmental setting.
7. The approval of the project as conditioned is in the best interest of the
public health, safety, and general welfare.
8. General site considerations, including site layout, orientation, the
location of buildings, vehicular access, circulation and parking, setbacks,
height, public safety, and similar elements have been designed to provide a
desirable environment for the development.
9. General architectural considerations including the character, scale, and
quality of the design, the architectural relationship with the site and
other buildings, building materials and colors, screening of exterior
appurtenances, exterior lighting and signing and similar elements have been
incorporated into the project in order to insure compatibility of this
development with its design concept and the character of adjacent buildings
and uses.
10. General project landscaping and consideration including the locations,
type, size, color, texture and coverage of plant materials, provisions for
irrigation, maintenance and protection of landscaped areas and similar ele-
ments have been considered to insure visual relief to complement buildings
and structures and to provide an attractive environment to the public.
11. The project is consistent with the policies contained in the City's General
Plan.
BE IT FURTHER RESOLVED THAT THE Dublin Planning Commission does
hereby deny said appeal and reaffirms the Zoning Administrator action of
January 27, 1986, conditionally approving the request as indicated below:
Unless stated otherwise, all Conditions shall be complied with prior to
issuance of building or grading permits and shall be subject to Planning
Department review and approval.
-2-
r1 /1
GENERAL REQUIREMENTS:
1. Development shall generally conform with the revised plans prepared by
William Glass and Associates, Architects, Inc., consisting of four sheets
dated received by the City Planning Department December 23, 1985.
Collectively, these materials shall serve as Exhibit "B" for this project
and shall be maintained on file with the Planning Department. This
approval shall be valid until March 13, 1987. If construction has not
commenced by that time, this approval shall be null and void. This
approval may be extended one additional year by the Planning Director upon
his determination that the Conditions of Approval outlined in this document
continue to remain adequate to assure development consistent with the
aforestated Findings of Approval. Development shall be subject to the
conditions listed below.
2. Comply with the City of Dublin Site Development Review Standard Conditions
and the City of Dublin Police Services Standard Commercial Building
Security Recommendations (see Attachments A and B).
ARCHITECTURAL:
3. Elevations and examples of exterior colors and materials for buildings and
structures shall be subject to final review and approval by the Planning
Director. All ducts, meters, air conditioning equipment and other
mechanical equipment on the new structure shall be effectively screened
from view with materials architecturally compatible with the main
structure.
DRAINAGE:
4. The drainage system developed shall be subject to review and approval by
the City Engineer.
5. The area outside the building shall drain outward at a 2% minimum slope for
unpaved areas and a 1% minimum in paved areas (5% maximum).
6. Roof drains shall empty onto paved areas, concrete swales, or other
approval dissipating devices. Calculations (hydraulic) shall be prepared
by the developer for review by the City Engineer to determine the sizing of
new drainage lines.
DEBRIS/DUST/CONSTRUCTION ACTIVITY:
7. Measures shall be taken to contain all trash, construction debris, and
materials in the construction area until disposal off-site can be arranged.
The developer shall keep adjoining parking and driveway areas free and
clean of project dirt, mud, and materials during the construction period.
All construction areas shall be watered, or other dust-palliative measures
used, to prevent dust as conditions warrant.
EASEMENTS:
8. The developer shall acquire easements, and/or obtain rights-of-entry from
the adjacent property owners for any improvements, including grading,
required outside of the proposed development. Copies of the easements
and/or rights of entry shall be in written form and be furnished to the
City Engineer.
9. Prior to occupancy, the applicant shall provide a recorded cross easement
for vehicular ingress and egress from the southeast portion of the
contiguous library parking lot through the subject property to Amador
Valley Boulevard (see Staff Study dated January, 1986) or show to the
satisfaction of the Planning Director that diligence has been pursued to
accomplish the Condition. If upon the request for occupancy it is the
desire of the applicant to request additional time to satisfy this
Condition, the request shall be taken to the Planning Commission as another
public hearing item for consideration by the Commission. The alignment of
the cross vehicular connection and the necessary adjustments to parking and
landscapes shall be subject to review and approval by the Planning
Director. The easement document shall be subject to review and approval by
the City Attorney prior to recordation (see sample agreement marked
Attachment C). Development of the vehicular connection between the two
-3-
i'1 /1
properties shall not be the responsibility of this applicant. The
developer shall supply the necessary right-of-entry agreements to the
Library's agent who is subsequently chosen to make the modifications to the
respective parking lots to allow said vehicular access connection.
10. Prior to occupancy, the applicant shall provide a recorded cross easement
for vehicular ingress and egress through the parking area adjoining the
northwest corner of the Gemco building to APN 941-305-14-2 (see Staff Study
dated January, 1986) or show to the satisfaction of the Planning Director
that diligence has been pursued to accomplish the Condition. If upon the
request for occupancy it is the desire of the applicant to request
additional time to satisfy this Condition, the request shall be taken to
the Planning Commission as another public hearing item for consideration by
the Commission. The alignment of the cross vehicular connection and the
necessary adjustments to parking and landscape areas in vicinity of the
connection shall be subject to review and approval by the City Engineer and
the Planning Director. The easement document shall be subject to review
and approval by the City Attorney prior to recordation. Development of the
vehicular connection between the two properties shall be jointly the
responsibility of the owners of the Gemco property and APN 941-305-14-2.
Installation of the connection shall be accomplished within 120 days of the
City's notification to both owners for work to commence. The developer
shall supply the necessary right-of-entry agreements to the agent for APN
941-305-14-2, who is chosen to make their share of the modifications to the
existing parking/ landscape areas to accommodate the referenced driveway
connection.
FIRE:
11. Prior to the issuance of building permits, the developer shall supply
written confirmation that the requirements of the Dublin San Ramon Services
District Fire Department have been, or will be, met.
LANDSCAPING AND IRRIGATION PLANS:
12. A detailed Landscape and Irrigation Plan, along with a cost estimate of the
work and materials proposed, shall be submitted for review and approval by
the Planning Director. Said Plan shall detail all proposed modifications
to existing landscape areas modified as a result of the work detailed
within this permit (including changes prompted by Conditions #9, #10 and
#18).
LIGHTING:
13. Exterior lighting shall be of a design and placement so as not to cause
glare onto adjoining properties. Wall lighting along the north side of the
new structure shall be supplied to provide "wash" security lighting along
that area of the structure-. Release from the discharge of this condition
may be granted by the City Engineer and the City Police Department upon
their determination that the lighting is not necessary.
PARKING AND DRIVEWAYS:
14. The developer shall be responsible for the correction of the minor
deficiencies in the existing frontage improvements as determined necessary
by the City Engineer.
15. The landscape-walkway-drive aisle area adjoining the northeast corner of
the Gemco building shall be modified to promote better delineation between
pedestrian walkway and vehicular travel areas. This shall be accomplished
by continuing the raised concrete walkway around the corner of the building
which may transition back to the existing grade alignments approximately 50
feet west of the intersection of the two drive aisles (see Staff Study
dated January, 1986).
SIGNAGE:
16. Any new signs proposed in conjunction with the building addition/
modification shall be subject to review and approval by the Planning
Director.
-4-
STORAGE AND EXTERIOR ACTIVITIES:
17. Unenclosed outside storage of merchandise display is expressly prohibited
(unless authorized by subsequent CUP or ACUP approvals for special
promotional events). The construction-related exterior storage adjoining
the rear (west) side of the Gemco building shall be cleared prior to the
issuance of a building permit for the proposed building modifications. All
demonstrations, displays, services, and other activities shall be conducted
entirely within the structures on the site. No loudspeakers or amplified
music shall be permitted outside the enclosed structure.
MISCELLANEOUS:
18. Prior to occupancy, the applicant shall establish a four-foot (minimum
clear width) pedestrian walkway extending from the northeast corner of the
Gemco Store along the westerly edge of the access road and extending to the
southwest corner of the intersection of the shopping center entry and
Amador Valley Boulevard or show to the satisfaction of the Planning
Director that diligence has been pursued to accomplish the Condition. If
upon the request for occupancy it is the desire of the applicant to request
additional time to satisfy this Condition, the request shall be taken to
the Planning Commission as another public hearing item for consideration by
the Commission. The materials used for new pedestrian walkways shall be of
a uniform design and shall be subject to review and approval of the
Planning Director. Those portions of walkways adjoining parking areas
shall be raised six inches (minimum) above the parking/drive aisle surface
and shall provide for a minimum 2-foot vehicle overhang.
19. The Planning Director shall have the discretion to make minor adjustments
to these Conditions as determined necessary to reflect the outcome of the
requirements called for in Conditions #9, #10 and #18, listed above.
20. Except as specifically altered by these conditions of approval, development
shall comply with the conditions established for S-646.
PASSED, APPROVED AND ADOPTED this 3rd day of March, 1986.
AYES: Commissioners Barnes, Burnham, Mack, Petty and Raley
NOES: None
ABSENT: None
%ngsion Chairperson
ATTEST:
Planning Director