DATE: March 3, 2026
TO: Honorable Mayor and City Councilmembers
FROM: Colleen Tribby, City Manager
SUBJECT: Green Stormwater Infrastructure Project, CIP Project No. ST0121,
Contract Change Order Authorization and Budget Transfer
Prepared by: Vatsal Patel, Assistant Public Works Director/City Engineer
EXECUTIVE SUMMARY:
The City Council will consider approval of a resolution increasing the contract change order
authority of the City Manager by $50,000 to compensate the contractor, Suulutaaq, Inc., for
needed sidewalk improvements related to the Green Stormwater Infrastructure Project, CIP
Project No. ST0121. To fund the increased costs, the City Council will also consider a budget
transfer of $50,000 in Transportation Development Act funds available in the Citywide Bicycle
and Pedestrian Improvements Project, CIP No. ST0517.
STAFF RECOMMENDATION:
Adopt the Resolution Approving Contract Change Orders W ith Suulutaaq, Inc. for the Green
Stormwater Infrastructure Project, CIP Project No. ST0121, and approve the budget change.
FINANCIAL IMPACT:
The sidewalk improvements add $50,000 to the Green Stormwater Infrastructure Project in
eligible Transportation Development Act (TDA) costs. Staff recommends a budget transfer
from the Citywide Bicycle and Pedestrian Improvements Project, CIP No. ST0517, to allocate
$50,000 in available TDA funds to the Dublin Green Stormwater Infrastructure Project for this
purpose. There is no impact to the General Fund.
DESCRIPTION:
On June 25, 2024, the City Council adopted Resolution No. 67-24 awarding a construction
contract of $2,501,546 to Suulutaaq, Inc. for the Green Stormwater Infrastructure Project, CIP
Project No. ST0121 (Project), and authorizing the City Manager to approve change orders up
to a contingency amount of $250,000 for a total potential construction contract amount of
$2,751,546.
44
Page 2 of 3
The Project is under construction and approximately 90% complete. The contractor has
completed grading activities, bioretention basin construction, storm drainage, pathway paving,
fencing, and sidewalk enhancements along Amador Valley Boulevard. Remaining activities
include final planting and landscaping maintenance, punch list corrections, and final closeout.
The current contact change order amount of $250,000 will be utilized during closeout on a
handful of unforeseen conditions that were identified through construction of the Project. These
include:
Presence of a set of fiber optic lines that was discovered in the same alignment of the
proposed storm drain system, which required additional excavation to expose the fiber
optic lines prior to the installation of the storm drain piping into the bioretention basin;
Location of Kinder Morgan high pressure gas lines that required a revision of the plans
to include raising and re-aligning the storm drain pipe upstream, beyond the Project
limits, to meet the required clearance for such lines;
Additional grading and installation of an overside drain into the bioretention basin
needed to manage erosion caused by offsite runoff accumulation from the wet weather
in late fall of 2025; and
Presence of a 15-inch storm drain that required exposure and potholing to determine if it
was still active or could be abandoned.
In addition, certain sidewalk improvements totaling approximately $50,000 were needed on
Amador Valley Boulevard in the vicinity of the Project and were added to the contractor’s
scope. The cost of this additional work is eligible for reimbursement through TDA funds
allocated to the City by the Metropolitan Transportation Commission in September 2024.
These funds were awarded for various bicycle and pedestrian improvements, including
sidewalk improvements at Amador Valley Boulevard, and are currently sitting in the Citywide
Bicycle and Pedestrian Improvements Project, CIP No. ST0517 .
The budget transfer of $50,000 to the Green Stormwater Infrastructure Project, in addition to
approval of an increase to the City Manager’s contract change order authority, will allow for
completion of the Project for a total construction contract cost of $2,801,546.
STRATEGIC PLAN INITIATIVE:
None.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
The City Council Agenda was posted. A copy of this report was sent to Suulutaaq, Inc.
ATTACHMENTS:
1) Resolution Approving Contract Change Orders W ith Suulutaaq, Inc. for the Green
Stormwater Infrastructure Project, CIP No. ST0121
2) CIP No. ST0121
45
Page 3 of 3
3) CIP No. ST0517
4) Budget Change Form
46
Attachment 1
Reso. No. XX-26, Item X.X, Adopted XX/XX/2026 Page 1 of 2
RESOLUTION NO. XX – 26
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING CONTRACT CHANGE ORDERS WITH SUULUTAAQ, INC. FOR THE GREEN
STORMWATER INFRASTRUCTURE PROJECT, CIP PROJECT NO. ST0121
WHEREAS, on June 25, 2024, the City Council adopted Resolution No. 67 -24, awarding a
construction contract of $2,501,546 to Suulutaaq, In c. for the Green Stormwater Infrastructure
Project, CIP Project No.ST0121 (Project), and authorizing the City Manager to approve change
orders up to a contingency amount of $250,000 for a total potential construction contract amount
to $2,751,546; and
WHEREAS, the Project is under construction and approximately 90% complete; and
WHEREAS, several unforeseen conditions impacted the construction cost and completion
time of the Project; and
WHEREAS, to compensate the contractor for the additional costs as a result of the
unforeseen conditions, Staff requests that the City Council authorize an additional $50,000 of
change order authority to the City Manager; and
WHEREAS, improvement of the existing sidewalk on Amador Valley Boulevard, in the
vicinity of the Iron Horse Regional Trail, Iron Horse Nature Park and Open Space Project, and the
Green Stormwater Infrastructure Project, was also included as part of the Project; and
WHEREAS, the total approved change order authority will increase up to $300,000 and will
increase the total potential construction cost to $2,801,546 ; and
WHEREAS, no additional City funds are requested and the proposed budget transfer will
utilize previously allocated TDA funds for eligible sidewalk improvements; and
WHEREAS, the remaining change order costs can be accommodated within the Project’s
existing contingency.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby authorize the City Manager, or designee, to approve up to $300,000 in Contract Change
Orders with Suulutaaq, Inc. for the Green Stormwater Infrastructure Project, CIP Project No.
ST0121.
{Signatures on the following page}
47
Reso. No. XX-26, Item X.X, Adopted XX/XX/2026 Page 2 of 2
PASSED, APPROVED AND ADOPTED this 3rd day of March 2026, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
______________________________
Mayor
ATTEST:
_________________________________
City Clerk
48
$2,333,670 $275,000 $0 $300,000 $0 $0 $0
$847,053 $115,000 $0 $120,000 $0 $0 $0
$96,340 $30,000 $0 $30,000 $0 $0 $0
$12,000 $0 $0 $0 $0 $0 $0
Table of ContentsGreen Stormwater Infrastructure
2024-2029 Five-Year Capital Improvement Program Update | DublinPage 123
Attachment 2
49
⚪
⚪
⚪
⚪
⚪
$2,335,687 $0 $0 $0 $0 $0 $0
$953,376 $420,000 $0 $450,000 $0 $0 $0
Table of ContentsGreen Stormwater Infrastructure
2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 124 50
$3,173,298 $1,861,445 $2,381,000 $525,000 $525,000 $525,000 $0
$1,314,668 $555,000 $200,000 $200,000 $200,000 $200,000 $0
$127,372 $50,728 $20,000 $20,000 $20,000 $20,000 $0
$40,034 $7,500 $5,000 $5,000 $5,000 $5,000 $0
Table of ContentsCitywide Bicycle and Pedestrian Improvements
2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 108
Attachment 3
51
⚪
⚪
⚪
⚪
$1,471,600 $630,000 $250,000 $250,000 $250,000 $250,000 $0
$601,872 $698,228 $250,000 $250,000 $250,000 $250,000 $0
$0 $355,000 $250,000 $250,000 $250,000 $250,000 $0
$135,000 $0 $1,053,000 $0 $0 $0 $0
$858,000 $105,000 $0 $0 $0 $0 $0
$0 $0 $803,000 $0 $0 $0 $0
$726,000 $0 $0 $0 $0 $0 $0
$510,000 $0 $0 $0 $0 $0 $0
$210,000 $286,445 $0 $0 $0 $0 $0
$0 $400,000 $0 $0 $0 $0 $0
$142,900 $0 $0 $0 $0 $0 $0
Table of ContentsCitywide Bicycle and Pedestrian Improvements
2024-2029 Five-Year Capital Improvement Program Update | DublinPage 109 52
⚪
Table of ContentsCitywide Bicycle and Pedestrian Improvements
2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 110 53
Budget Change Reference #:
From Un-Appropriated Reserves Budget Transfer Between Funds X
From Designated Reserves Other
Account Amount Account Amount
ST0517.9400.9401 $(50,000)$(50,000) ST0121.9400.9401 $50,000
$(50,000) ST0121-2203 $50,000
3/3/2026
Posted By:Date:
As Presented at the City Council Meeting
**********Finance Use Only**********
Improvement of the existing sidewalk on Amador Valley Boulevard, in vicinity of the Iron Horse Regional Trail, Iron Horse
Nature Park and Open Space Project, and the Green Stormwater Infrastructure Project, was included as part of the Project.
The costs of the sidewalk improvements are eligible for reimbursement from Transportation Development Act funds. To seek
reimbursement of these costs, Staff recommends a budget transfer of $50,000 from Transportation Development Act funds
as part of the Citywide Bicycle and Pedestrian Improvements Project, CIP No. ST0517, to the Dublin Green Stormwater
Infrastructure Project, CIP Project No. ST0121.
REASON FOR BUDGET CHANGE
FISCAL YEAR 2025-26
BUDGET CHANGE FORM
DECREASE BUDGET AMOUNT INCREASE BUDGET AMOUNT
(Old) ST0517 - Citywide Bicycle and Pedestrian
Improvements - Transportation Development Act
City Council's Approval Required
(New) ST0121 - Green Stormwater Infrastructure
Attachment 4