HomeMy WebLinkAbout5.3 Iron Horse Nature Park and Open Space Phase 1 Project, CIP No. PK0422 – Contract Change Order Authorization
STAFF REPORT
CITY COUNCIL
Page 1 of 3
Agenda Item 5.3
DATE: November 4, 2025
TO: Honorable Mayor and City Councilmembers
FROM: Colleen Tribby, City Manager
SUBJECT:
Iron Horse Nature Park and Open Space Phase 1 Project, CIP No.
PK0422 – Contract Change Order Authorization
Prepared by: Andrew Russell, Public Works Director
EXECUTIVE SUMMARY:
The City Council will consider increasing the contract change order authority of the City
Manager by $240,000 for the Iron Horse Nature Park and Open Space Phase 1 Project, CIP
No. PK0422. This will enable a change to the contract with Goodfellow Bros. California, LLC to
compensate the contractor for costs due schedule delays associated with environmental
resource agency restrictions and permitting, as well as for additional work requested by the
City.
STAFF RECOMMENDATION:
Adopt the Resolution Authorizing the City Manager to Approve Contract Change Orders with
Goodfellow Bros. California, LLC for the Iron Horse Nature Park and Open Space Phase 1
Project, CIP No. PK0422.
FINANCIAL IMPACT:
The total additional cost associated with schedule delays and additional work is estimated at
$240,000. Sufficient funds are available within the Iron Horse Nature Park and Open Space
Project (CIP No. PK0422) to cover these expenses.
DESCRIPTION:
On October 17, 2023, the City Council awarded a construction contract of $3,324,491 to
Goodfellow Bros. California, LLC for the Iron Horse Nature Park and Open Space Phase 1
Project, CIP No. PK0422, and authorized the City Manager to approve change orders up to a
contingency amount of $335,000 (Resolution No. 108-23). On November 19, 2024, the City
Council authorized the City Manager to approve change orders up to an additional contingency
amount of $400,000, which brought the total change order authorization to $735,000 and a
total potential construction contract amount to $4,059,491 (Resolution 133-24).
25
Page 2 of 3
The Iron Horse Nature Park and Open Space Phase 1 Project is under construction and
approximately 90% complete. The contractor has completed grading activities and
contaminated soil removal, bridge and culvert construction, pathway paving, and
enhancements to Stagecoach Park. Remaining activities include wetland restoration, final
planting and landscaping, installation of remaining park furniture, fencing at Amador Valley
Boulevard, and punch list corrections and final project closeout.
Work in and around the regulated streams and wetlands is restricted by the permits from three
resource agencies: the Regional Water Quality Control Board, the U.S. Army Corps of
Engineers, and the California Department of Fish and Wildlife. Although pre-application
engagement was conducted and permit applications were submitted to the agencies in April
2023, the final permit to construct was not issued to the City until September 2024. Because
activities within the regulated areas are limited to the dry season, the project schedule was
updated and work within the jurisdictional areas was delayed until mid-April 2025. In November
2024, the City Council approved a $400,000 increase in contract change order authority, which
addressed additional contractor overhead cost associated with the construction delay and
increased project costs due to increased material costs, storage costs, and construction of a
new haul road necessary to avoid the streams and wetlands.
To date, three project change orders totaling $703,312 have been approved, as follows:
Change Order 1 - $136,057 for additional costs for deleterious soil testing protocols,
asbestos mitigation during railroad trestle bridge removal, and initial time-related
overhead due to regulatory agency delay of work from April 29, 2024, to May 31, 2024.
Change Order 2 - $373,719 for additional costs related to working beyond 2024 due to
unanticipated resource agency permit restrictions and material storage costs; increased
costs for the arch bridge culvert due to decreased soil bearing pressure ; and
Stagecoach Park improvements (privacy fence, irrigation, grading, air relief valve , and
drainage at trees).
Change Order 3 - $193,536 for additional negotiated costs for time-related overhead
due to regulatory agency delay of work from June 1, 2024, to August 16, 2024.
The impact of the regulatory agency permit delay is greater than initially anticipated. In addition
to delayed schedule, the means and methods required of the contractor created inefficiencies
that resulted in extra work and increased costs, as follows:
A single haul route in and out of the project work area to avoid the streams and
wetlands, instead of circular access as was originally planned, resulted in increased
contractor time and costs.
The inability to excavate spoils and immediately place them into the path prism (former
railroad areas) and inability to store spoils onsite for future work created costs
associated with additional off-haul of materials approximately six months later.
Additional hydroseed application was required in and around the wetland areas.
26
Page 3 of 3
The pushing of the project schedule moved contractor wages from 2024 to 2025 rates
and extended the contractor’s overhead costs.
Additionally, project costs also increased due to the following Staff-requested additional work
items:
Installation of additional two-rail wooden fences along Amador Valley Boulevard and a
pathway entrance to Stagecoach Park.
Installation of traffic detector loops at Amador Valley Boulevard.
Painting of the exposed timber elements at railroad amenity shade structure.
To compensate the contractor for work described above, Staff requests that the City Council
authorize an additional $240,000 of change order authority to the City Manager. This will bring
the total authorized change order authority to $9 75,000 and will increase the total potential
construction cost to $4,299,491. There are sufficient funds available in the project budget to
accommodate the increased change order authorization.
STRATEGIC PLAN INITIATIVE:
None.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
The City Council Agenda was posted, and a copy of this report was sent to Goodfellow Bros.
California, LLC.
ATTACHMENTS:
1) Resolution Authorizing the City Manager to Approve Contract Change Orders with
Goodfellow Bros. California, LLC for the Iron Horse Nature Park and Open Space Phase 1
Project, CIP No. PK0422
2) CIP No. PK0422
27
Attachment 1
Reso. No. XX-25, Item X.X, Adopted XX/XX/2025 Page 1 of 2
RESOLUTION NO. XX – 25
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
AUTHORIZING THE CITY MANAGER TO APPROVE CONTRACT CHANGE ORDERS WITH
GOODFELLOW BROS. CALIFORNIA, LLC FOR THE IRON HORSE NATURE PARK AND
OPEN SPACE PHASE 1 PROJECT, CIP NO. PK0422
WHEREAS, on October 17, 2023, the City Council adopted Resolution No. 108 -23,
Approving the Plans and Specifications, Waiving a Minor Bid Irregularity, and Awarding a Contract
to Goodfellow Bros. California, LLC for the Iron Horse Nature Park and Open Space Phase 1
Project, CIP No. PK0422; and
WHEREAS, through Resolution No. 108-23 the City Council authorized the City Manager
or designee to approve contract change orders based on appropriated funds designated for the
Project, up to the contingency amount of $335,000; and
WHEREAS, on November 19, 2024, the City Council adopted Resolution No. 133-24,
Authorizing the City Manager to Approve Contract Change Orders with Goodfellow Bros.
California, LLC for the Iron Horse Nature Park and Open Space Phase 1 Project, CIP No. PK0422,
increasing the project contingency by $400,000 to compensate the contractor for delays
associated with various resource agency permits, and which increased the total change order
authority to $735,000; and
WHEREAS, the impact of the regulatory agency permit delay is greater than previously
estimated, which resulted in additional work and increased construction costs; and
WHEREAS, there are also City-requested work items that resulted in additional work and
increase construction costs; and
WHEREAS, sufficient budget is available in the Iron Horse Nature Park and Open Space
Project, CIP No. PK0422, to increase the project contingency by $2 40,000, thereby facilitating
payment for the delay and additional work costs.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby authorize the City Manager, or designee, to approve contract change orders with
Goodfellow Bros. California, LLC up to the revised contingency amount of $975,000 and increase
the construction contract total to $4,299,491.
{Signatures on the following page}
28
Reso. No. XX-25, Item X.X, Adopted XX/XX/2025 Page 2 of 2
PASSED, APPROVED AND ADOPTED this 4th day of November 2025, by the following
vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
______________________________
Mayor
ATTEST:
_________________________________
City Clerk
29
$2,446,027 $1,248,800 $2,235,941 $2,778,654 $0 $0 $0
$2,381,226 $196,505 $0 $0 $0 $0 $0
$365,500 $0 $255,000 $0 $0 $0 $0
$210,247 $52,000 $0 $0 $0 $0 $0
Table of ContentsIron Horse Nature Park and Open Space
2024-2029 Five-Year Capital Improvement Program Update | DublinPage 79
Attachment 2
30
⚪
$3,056,000 $1,463,505 $2,490,941 $0 $0 $0 $0
$0 $0 $0 $2,778,654 $0 $0 $0
$2,294,000 $0 $0 $0 $0 $0 $0
$53,000 $33,800 $0 $0 $0 $0 $0