HomeMy WebLinkAboutReso 87-25 Item 5.3 Accepting the Annual Street Resurfacing - 2024 Slurry Seal Project CIP No. ST011Reso. No. 87-25, Item 5.3, Adopted 10/21/2025 Page 1 of 2
RESOLUTION NO. 87 - 25
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
ACCEPTING THE ANNUAL STREET RESURFACING - 2024 SLURRY SEAL PROJECT, CIP NO.
ST0117
WHEREAS, on April 16, 2024, the City entered into a Construction Contract with American
Asphalt Repair & Resurfacing Co., Inc. for the Annual Street Resurfacing –2024 Slurry Seal Project,
CIP No. ST0117; and
WHEREAS, on October 15, 2024, the City approved Resolution No. 117-24 that increased the
project contingency amount to $185,000 and authorized the City Manager to approve contract
change orders up to said $185,000 contingency amount; and
WHEREAS, the project resurfaced multiple street segments with a slurry seal treatment that
will prolong the life of the existing pavement surface; and
WHEREAS, said improvements have been completed in accordance with plans and
specifications, and any approved modifications thereof, to the satisfaction of the City Engineer of
the City of Dublin; and
WHEREAS, as a condition of the contract, American Asphalt Repair & Resurfacing Co., Inc. is
required to warranty the improvements for a period of one year following the completion of the work
and maintain a maintenance bond in the amount of 10% of the final contract value.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby
accept the Annual Street Resurfacing –2024 Slurry Seal Project, CIP No. ST0117, and authorize Staff
to file a Notice of Completion with Alameda County.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize
the City Manager, or designee, to release the retention, if after 35 days of filing the Notice of
Completion there are no subcontractor claims.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize
the City Manager, or designee, to release the maintenance bond at the end of the one-year warranty
period.
{Signatures on the following page}
Docusign Envelope ID: B9A3CE8E-30D5-4FE4-B0C0-9B466EA9C939
Reso. No. 87-25, Item 5.3, Adopted 10/21/2025 Page 2 of 2
PASSED, APPROVED AND ADOPTED this 21st day of October 2025, by the following vote:
AYES: Councilmembers Josey, McCorriston, Morada, Qaadri and Mayor Hu
NOES:
ABSENT:
ABSTAIN:
______________________________
Mayor
ATTEST:
_________________________________
City Clerk
Docusign Envelope ID: B9A3CE8E-30D5-4FE4-B0C0-9B466EA9C939