HomeMy WebLinkAbout7.2 Five-Year Capital Improvement Program 2024-2029 Update STAFF REPORT CITY COUNCIL Page 1 of 8 Agenda Item 7.2 DATE: June 17, 2025 TO: Honorable Mayor and City Councilmembers FROM: Colleen Tribby, City Manager SUBJECT: Five-Year Capital Improvement Program 2024-2029 Update Prepared by: Michael Boitnott, CIP Manager EXECUTIVE SUMMARY: The City Council will consider adopting an update to the Five-Year Capital Improvement Program 2024-2029, which includes capital project funding from Fiscal Year 2024-25 through Fiscal Year 2028-29. STAFF RECOMMENDATION: Adopt the Resolution Adopting the Five-Year Capital Improvement Program 2024-2029 Update. FINANCIAL IMPACT: The Five-Year Capital Improvement Program 2024-2029 Update includes appropriations totaling $37,612,791 in Fiscal Year 2024-25 and $32,339,941 in Fiscal Year 2025-26. These appropriations are included in the Capital Improvement Program section of the Fiscal Year 2025-26 Budget. DESCRIPTION: Each year, the City Council updates and adopts the City’s Five-Year Capital Improvement Program (CIP). On April 15, 2025, the City Council received a report on the preliminary Five- Year CIP 2024-2029 Update and provided comments and direction to Staff, including direction to reanalyze the CIP with a focus on projects funded fully or partially by the General Fund. On June 3, 2025, the City Council received a report on the General Fund projects within the CIP and provided direction on Fiscal Year 2025 -26 revisions to the CIP. This report incorporates City Council direction from the previous meetings. The CIP represents the City’s capital investment program and addresses the City’s public infrastructure needs through Fiscal Year 2028-29. Projects in the CIP are identified in the following major categories: General Improvements, Public Art, Parks, Streets, and Future 712 Page 2 of 8 Projects. The Future Projects category identifies projects that are beyond the current CIP timeframe, for which a funding source may or may not be identified. The table and graph below summarize 2024-2029 CIP expenditure budgets by project category: Table 1. Total CIP Expenditure Budgets by Project Category Category 2024-25 2025-26 2026-27 2027-28 2028-29 Five-Year General $10,075,459 $5,702,000 $500,000 $1,500,000 $200,000 $17,977,459 Public Art $780,000 $300,000 $250,000 - - $1,330,000 Parks $2,516,985 $6,050,941 $2,928,654 $1,100,000 $5,150,000 $17,746,580 Streets $24,240,347 $20,287,000 $12,542,000 $15,942,000 $5,292,000 $78,303,347 Total $37,612,791 $32,339,941 $16,220,654 $18,542,000 $10,642,000 $115,357,386 Figure 1. CIP Expenditure Budget % by Project Category General Improvements The General Improvements category includes 23 projects. There are no new General Improvements projects proposed in the CIP Update, however, there are proposed budget changes to the following projects:  Audio Visual System Upgrade (GI0421). The FY 2025-26 expenditure budget includes a $250,000 increase from the Information Techology Fund to account for expanded project scope and increased equipment costs.  Dublin Arts Center (GI0120). The FY 2025-26 expenditure budget includes a total increase of $1,000,000, which includes $500,000 from the Equipment Replacement Fund, $250,000 from the Information Technology Fund, and $250,000 from the General Fund Reserve. The new funding is for additional technology infrastructure, building modifications to support relocation of the Parks and Community Services Department, and repair and General 16%Public Art 1% Parks 15% Streets 68% 713 Page 3 of 8 replacement of building components that have exceeded their useful life.  Resiliency and Disaster Preparedness Improvements (GI0221). On June 17, 2025, under a separate item on the meeting agenda, the City Council will consider approving construction contracts and an associated $660,000 General Fund budget increase for the repair of two landslides that occurred due to very heavy rains that started in late December 2022 and extended into early January 2023. If the $660,000 budget change is approved by the City Council, the CIP will be edited to incorporate this funding increase. To potentially offset some of this cost, Staff applied for grant funding through the Federal Emergency Management Agency and the California Office of Emergency Services and will sub mit costs to the organizations, who will determine which project expenditures are eligible for reimbursement of up to 75% of the costs. In addition to the project updates listed above, the following General Improvements projects have been removed from the CIP based upon input received from the City Council on April 15 and June 3 and/or Staff reevaluation. Any unspent funds budgeted to these projects will be returned to their respective funding sources:  Marquee Signs project (GI0124). On June 3, the City Council discussed this project and asked Staff to reevaluate it. Staff now recommends removing the project from the CIP. The existing marquee signs at the Shannon Community Center and at the Senior Center will continue to be operated and maintained as long as feasible with operating budget funds. Staff will evaluate whether, at the end of their useful lives, these signs should be removed or replaced.  Shade Structures at Various Facilities and Parks project (GINEW01). This was a proposed new General Fund project in the preliminary CIP. On June 3, the City Council recommended this project be removed from the CIP. Public Art The Public Art category includes three projects. There are no new Public Art projects proposed in the CIP Update, however, there is a budget change reflected in the following project:  Camp Parks Sign (PA0121). On April 1, 2025, the City Council approved a budget increase of $280,000 of Public Art Funds and approved a construction contract for the project. The additional expenditure budget included fund balance transfer from the following completed projects: Don Biddle Community Park Art (PA0217) and Heritage Park Public Art (PA0222). Parks The Parks category includes 16 projects. There are no new Parks projects proposed in the CIP Update, however there are budget changes to the following projects:  Fallon Sports Park Baseball Field G Upgrades (PK0225). The FY 2025-26 expenditure budget includes a new General Fund appropriation of $250,000 for additional spectator seating. This represents a $250,000 reduction of new funding based on the City Council’s direction on June 3, 2025.  Iron Horse Nature Park and Open Space (PK0422). On February 18, 2025, the City 714 Page 4 of 8 Council approved a $33,800 budget increase for the Iron Horse Nature Park and Open Space project (PK0422) for benches and picnic tables. The CIP also proposes to move $2,778,654 of Unidentified Funding from FY 2025-26 to FY 2026-27 for this project. Phase 1 of the project is currently underway and is anticipated to be completed in 2025.  Kolb Park Renovation (PK0224). The CIP includes a proposed budget reduction of $475,000 of General Fund. On June 3, 2025, the City Council directed Staff to revisit the project scope, timing, and potential phasing, but to proceed with replacing the restroom building at Kolb, which is estimated at $475,000. This General Fund funding will be transferred from the Kolb Park Renovation Project to the Restroom Replacement project (PK0321). It is anticipated that the Restroom Replacement project will be in construction earlier than Kolb Park.  Restroom Replacement (PK0321). The CIP includes a budget increase of $475,000 of General Fund, reflecting the transfer from the Kolb Park project (PK0224). The increased funding is in addition to $1,000,000 in existing funding. The project will replace the existing restroom buildings at Alamo Creek Park, Mape Memorial Park, and Kolb Park. Streets The Streets category includes 16 projects. There are no new Streets projects proposed in the CIP Update, however there are proposed budget changes to the following projects:  Annual Street Resurfacing (ST0117). The FY 2024-25 expenditure budget includes an increase of $103,324 from the Department of Resources Recycling and Recovery (CalRecycle) Rubberized Pavement Grant Program which will be used for the 2026 resurfacing construction.  Citywide Bicycle and Pedestrian Improvements (ST0517). The FY 2024-25 expenditure budget includes funding from two grants. The City was awarded $286,445 in Transportation Development Act funding by the Metropolitan Transportation Commission for pedestrian and trail improvements along Amador Valley Boulevard at the Iron Horse Regional Trail. The City also received $400,000 in funding from the Alameda County Health Services Department through the Enhancing Vision 2026 (EV2026) Fund for the Regional Street Mid-Block Crossing project.  Dublin Boulevard Extension – Fallon Road to North Canyons Parkway (ST0216). On January 14, 2025, the City Council approved a $250,000 budget increase from the General Fund Designated Reserves for a consulting services agreement with Gray-Bowen-Scott.  Iron Horse Trail Bridge at Dublin Boulevard (ST0118). On February 18, 2025, the City Council approved a $50,000 budget increase from the General Fund for additional consultant work on the project.  Village Parkway Reconstruction (ST0323). The FY 2024-25 expenditure budget includes $9,150,000 of State Transportation Improvement Program (STIP) grant funding that was approved by the California Transportation Commission in April. On November 5, 2024, the City Council approved a $5,000,000 General Fund Designated Reserves appropriation to the project. There is no longer any Unidentified Funding shown in the CIP for this project. In addition to the project updates listed above, the following projects have been removed from the CIP based upon input received from the City Council on April 15 and June 3 and/or Staff reevaluation. All unspent funds will be returned to their respective funding sources. 715 Page 5 of 8  City Entrance Monument Signs (ST0319). The replacement sign at Kimball Avenue and Village Parkway will be included in the Village Parkway Reconstruction project (ST0323). The remaining four locations have been left in the City Entrance Signs project and moved to the Future Projects category.  Citywide Storm Drain Improvements (ST0124). The planning phase of this project can be accomplished through funds available in the operating budget. Any capital improvement recommendations resulting from the planning phase will be referred to the City Council for future consideration.  San Ramon Road Landscape Renovation (ST0218). Existing street landscaping on San Ramon Road, between Acosta Boulevard and Silvergate Drive, will continue to be maintained through the operating budget. Funding Sources Funding for the CIP comes from a variety of sources, which is summarized in Table 2 and Figure 2 below. Table 2. CIP Funding Sources Category 2024-25 2025-26 2026-27 2027-28 2028-29 Five-Year General Fund $5,580,823 $18,221,900 $5,200,000 $1,850,000 $1,850,000 $32,702,723 Special Revenues/ Assessment District $21,147,819 $7,550,100 $4,842,000 $4,942,000 $3,442,000 $41,923,919 Public Art Fund $780,000 $300,000 $250,000 - - $1,330,000 Traffic Impact Fees $816,320 - - - - $816,320 Public Facility Fees $1,563,505 $2,490,941 - - - $4,054,446 Internal Service Funds $7,621,000 $3,777,000 $650,000 $2,600,000 $5,350,000 $19,998,000 Other (1) $103,324 - - $9,150,000 - $9,253,324 Unidentified - - $5,278,654 - - $5,278,654 TOTAL $37,612,791 $32,339,941 $16,220,654 $18,542,000 $10,642,000 $115,357,386 (1) Other Category includes funding from developer- and other-agency funds 716 Page 6 of 8 Figure 2. CIP Funding Source % Approximately 4.2% or $4.9 million of the CIP costs are funded by Transportation Impact Fees and Public Facilities Fees. Completion of projects funded by impact fees is contingent upon development proceeding as estimated and fees being collected as projected. The timing of projects funded by this source may need to be reevaluated if there is a slowdown in projected development activities. Approximately 36.3% or $41.9 million of CIP costs are funded by Special Revenues. Of this amount, $25.4 million is from State Gas Taxes (Highway Users Tax Account or HUTA ), SB1 Road Maintenance and Rehabilitation Account (RMRA), and Measure B/BB Sales Tax. General Fund Contributions The General Fund contributions to the CIP account for approximately 28.3% or $32.7 million of the five-year costs. The following is a list of CIPs funded or partially funded by the General Fund:  Alamo Creek Park and Assessment District - Fence Replacement  Annual Street Resurfacing  Audio Visual System Upgrade  Citywide Bicycle and Pedestrian Improvements  Citywide Energy Improvements  Citywide Signal Communications Upgrade  Civic Center Rehabilitation  Condition Assessment of Water Features  Downtown Dublin Street Grid Network 717 Page 7 of 8  Downtown Dublin Town Square Park  Dublin Arts Center  Dublin Boulevard Extension - Fallon Road to North Canyons Parkway  Dublin Standard Plans & Details Update  Electric Vehicle (EV) Charging Stations  Facilities Parking Lot Resurfacing  Fallon Sports Park - Baseball Field G Upgrades  Financial System Replacement  Forest Park  Green Stormwater Infrastructure  Iron Horse Nature Park and Open Space  Iron Horse Trail Bridge at Dublin Boulevard  Irrigation System Upgrades  IT Infrastructure Improvements  Kolb Park Renovation  Library Tenant Improvements  Marquee Signs  Municipal Fiber  Parks Playground Replacement  Resiliency and Disaster Preparedness Improvements  Restrooms Replacement  San Ramon Road Trail Lighting  Situational Awareness Camera Program  Sunday School Barn Flooring  Village Parkway Reconstruction  Waste Enclosures Upgrades Future Projects The Future Projects category identifies projects that are beyond the current CIP timeframe, for which a funding source may or may not yet be identified. The total cost of all projects beyond the CIP timeframe is estimated at $205.6 million. Future Projects are listed below. General Improvements ($3,575,000) • Corporation Yard Equipment Wash Pad • Electric Vehicle Charging Stations (Future phase) • Waste Enclosures Upgrades (Future phase) Parks ($25,850,000) • Downtown Dublin Town Square Park (Future phase) • Sports Courts Resurfacing (Future phase) • Dublin Sports Grounds - Phase 5 Renovation • Emerald Glen Recreation & Aquatic Complex - Phase 2 Streets ($176,432,306) • Dublin Boulevard Extension (Unfunded portions of current project, Future phase) 718 Page 8 of 8 • Downtown Dublin Street Grid Network (Future phase) • City Entrance Signs • Eastern Dublin Transportation Impact Fee (Fee program projects) • Western Dublin Transportation Impact Fee (Fee program projects) Annual Budget Impact Some CIP projects will have an impact on the operating budget due to ongoing maintenance costs. Table 3 provides a summary of additional annual funding from the General Fund. These expenses are not reflective of other infrastructure improvements, such as additional streets, street landscape, and streetlight maintenance that is necessary because of new development. Table 3. Annual Operating Costs Project 2024-25 2025-26 2026-27 2027-28 2028-29 Dublin Arts Center - $400,000 $800,000 $800,000 $800,000 Library Tenant Improvements - - $8,000 $8,000 $8,000 Situational Awareness Camera Program - $20,000 $20,000 $20,000 $20,000 Forest Park - $50,000 $75,000 $75,000 $75,000 Iron Horse Nature Park & Open Space - $150,000 $150,000 $460,000 $460,000 Wallis Ranch Community Park - $340,000 $340,000 $340,000 $340,000 Iron Horse Tail Bridge at Doublin Blvd. $80,000 $100,000 $100,000 $100,000 $100,000 TOTAL $80,000 $1,060,000 $1,493,000 $1,803,000 $1,803,000 A resolution adopting the Five-Year CIP 2024-2029 Update is included as Attachment 1, with the CIP Update document included as Attachment 2. To improve transparency, Staff is utilizing a new capital budgeting software, ClearGov, to produce this year’s Five-Year CIP Update document. Upon adoption by the City Council, a web-based online version and interactive map showing locations of each project will be available to the public. Staff anticipates making additional revisions to the content and format of the online version to further enhance its usability and readability. STRATEGIC PLAN INITIATIVE: The Five-Year Capital Improvement Program 2024-2029 Update reflects priorities established in the City’s Two-Year Strategic Plan. NOTICING REQUIREMENTS/PUBLIC OUTREACH: The City Council Agenda was posted. ATTACHMENTS: 1) Resolution Adopting the Five-Year Capital Improvement Program 2024-2029 Update 2) Five-Year Capital Improvement Program 2024-2029 Update 719 Attachment 1 Reso. No. XX-25, Item 7.2, Adopted 06/17/2025 Page 1 of 1 RESOLUTION NO. XX – 25 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN ADOPTING THE FIVE-YE AR CAPITAL IMPROVEMENT PROGRAM 2024 – 2029 UPDATE WHEREAS, each year, the City Council updates and adopts the City’s Five-Year Capital Improvement Program, which addresses the City’s public infrastructure and facility needs in the following areas: General Improvements, Public Art, Parks, Streets, and Future Projects; and WHEREAS, the City Manager has presented the Five-Year Capital Improvement Program 2024-2029 Update; and WHEREAS, on April 23, 2024, the Planning Commission reviewed the Five-Year Capital Improvement Program 2024-2029 and has determined the public works projects to be constructed are in conformance with the City of Dublin General Plan. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby take the following actions: 1. Adopt the Five-Year Capital Improvement Program 2024-2029 Update; and 2. Confirm that the items scheduled for implementation in Fiscal Year 2025-26 shall be included in the Capital Budget of the City’s updated Budget for Fiscal Year 2025-26. PASSED, APPROVED AND ADOPTED this 17th day of June 2025, by the following vote: AYES: NOES: ABSENT: ABSTAIN: ______________________________ Mayor ATTEST: _________________________________ City Clerk 720 Attachment 2 721 TABLE OF CONTENTS Inside Cover 4 Summary Schedules 5 Summary - All Project Types or Program Areas 6 Summary - All Funds 7 Capital Projects 12 General Improvements 13 Audio Visual System Upgrade 16 Citywide Energy Improvements 18 Civic Center Elevator Modernization 20 Civic Center Exterior Glazing, Sealing & Painting 22 Civic Center Rehabilitation 24 Condition Assessment of Water Features 26 Corporation Yard Equipment Wash Pad 28 Dublin Arts Center 30 Dublin Standard Plans & Details Update 32 Electric Vehicle (EV) Charging Stations 34 Exterior Painting at Various Facilities 36 Facilities Parking Lot Resurfacing 38 Financial System Replacement 40 Irrigation System Upgrades 42 IT Infrastructure Improvement 44 Library Tenant Improvements 46 Municipal Fiber 48 Resiliency and Disaster Preparedness Improvements 50 Roof Replacement at Various City Facilities 52 Shannon Community Center Play Yard 54 Situational Awareness Camera Program 56 The Wave Pool Replastering 58 Waste Enclosures Upgrades 60 Parks 62 Alamo Creek Park and Assessment District - Fence Replacement 64 Don Biddle Community Park 66 Downtown Dublin Town Square Park 68 Dublin Sports Grounds Rehabilitation 70 Fallon Sports Park - Artificial Turf Field Replacement 72 Fallon Sports Park - Phase 3 74 Fallon Sports Park Baseball Field G Upgrades 76 Forest Park 78 Iron Horse Nature Park and Open Space 80 Kolb Park Renovation 82 Parks Playground Replacement 84 Persimmon Drive Pedestrian Path Rehabilitation 86 Restrooms Replacement 88 722 Sports Courts Resurfacing 90 Sunday School Barn Flooring 92 Wallis Ranch Community Park 94 Public Art 96 Camp Parks Sign 97 Downtown Dublin 99 Outdoor Murals 101 Streets 103 Amador Plaza Road Bicycle and Pedestrian Improvements 106 Annual Street Resurfacing 108 Citywide Bicycle and Pedestrian Improvements 111 Citywide Signal Communications Upgrade 114 Downtown Dublin Street Grid Network 117 Dublin Boulevard Extension - Fallon Road to North Canyons Parkway 119 Dublin Ranch Streetlight Improvements 122 Golden Gate Drive Intersection Improvements - Dublin Blvd and St. Patrick Way 124 Green Stormwater Infrastructure 126 Iron Horse Trail Bridge at Dublin Boulevard 128 San Ramon Road Trail Lighting 131 Tassajara Road Improvements - North Dublin Ranch Drive to Quarry Lane School 133 Tassajara Road Realignment and Widening - Fallon Road to North City Limit 135 Traffic Signal and Roadway Safety Improvements 137 Traffic Signal Re-Lamping 139 Village Parkway Reconstruction 141 Unfunded - Future Projects 143 City Entrance Signs 144 Dublin Sports Grounds - Phase 5 Renovation 145 Eastern Dublin Transportation Impact Fee 146 Emerald Glen Recreation and Aquatic Complex - Phase 2 147 Western Dublin Transportation Impact Fee 148 723 Table of ContentsInside Cover 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 4 724 Summary Schedules Highlights The following schedule provides an overview of the nancial information contained in the Five-Year Capital Improvement Program 2024-2029 Update. The rst summary schedule highlights expenditures by program area for all projects and identies the nance category used for the projects.  The following nancial schedules provide information by major program area (General Improvements, Public Art, Parks, and Streets), as well as separate schedules listing Unfunded or Future Projects.  Additional details about each project are in the corresponding program area.   Table of ContentsSummary Schedules 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 5 725 Summary - All Project Types or Program Areas General Improvements Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total General Improvements $51,990,029 $10,075,459 $5,702,000 $500,000 $1,500,000 $200,000 $3,575,000 $73,542,488 Parks Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total Parks $58,120,397 $2,516,985 $6,050,941 $2,928,654 $1,100,000 $5,150,000 $5,500,000 $81,366,977 Public Art Historical FY2025 FY2026 FY2027FY2028FY2029Future Total Total Public Art $1,150,450$780,000$300,000$250,000 $0 $0 $0 $2,480,450 Streets Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total Streets $100,999,208$24,240,347$20,287,000 $12,542,000 $15,942,000$5,292,000 $105,422,306 $284,724,861 Unfunded - Future Projects HistoricalFY2025FY2026FY2027FY2028FY2029 Future Total Total Unfunded - Future Projects $0 $0 $0 $0 $0 $0$91,360,000 $91,360,000 Table of ContentsSummary - All Project Types or Program Areas 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 6 726 Summary - All Funds 1001 - General Fund Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 1001 - General Fund $19,518,017 $3,585,594 $7,321,900 $1,950,000 $1,850,000 $1,850,000 $3,575,000 $39,650,511 1101 - General Fund Designated Reserve Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 1101 - General Fund Designated Reserve $34,425,052 $1,995,229 $10,900,000 $3,250,000 $0 $0 $0 $50,570,281 2201 - State Gas Tax Historical FY2025 FY2026 FY2027 FY2028 FY2029Future Total Total 2201 - State Gas Tax $7,818,041$750,000$723,100$850,000$650,000$650,000 $0$11,441,141 2203 - Transportation Development Act Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2203 - Transportation Development Act $210,000 $286,445 $0 $0 $0 $0 $0 $496,445 2204 - Measure B Sales Tax - Local Streets Fund (Alameda CTC) Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2204 - Measure B Sales Tax - Local Streets Fund (Alameda CTC) $3,131,619 $0 $0 $0 $0 $0 $0 $3,131,619 2205 - Measure B Sales Tax - Bike & Ped. Fund (Alameda CTC) Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2205 - Measure B Sales Tax - Bike & Ped. Fund (Alameda CTC) $842,900 $0 $0 $0 $0 $0 $0 $842,900 2207 - Transportation for Clean Air Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2207 - Transportation for Clean Air $954,190 $128,000 $0 $0 $0 $0 $0 $1,082,190 2212 - Vehicle Registration Fee (Alameda CTC) HistoricalFY2025 FY2026FY2027FY2028FY2029Future Total Total 2212 - Vehicle Registration Fee (Alameda CTC) $1,738,356$35,040$1,854,000 $0 $0 $0 $0 $3,627,396 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $5,187,620 $2,120,000 $550,000 $1,050,000 $250,000 $250,000 $0 $9,407,620 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) Historical FY2025 FY2026 FY2027 FY2028 FY2029Future Total Total 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) $1,366,372$948,228$275,000$650,000$250,000$250,000 $0 $3,739,600 Table of ContentsSummary - All Funds 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 7 727 2216 - Measure B Grants Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2216 - Measure B Grants $82,500 $0 $0 $0 $0 $0 $0 $82,500 2217 - Measure BB Grants Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2217 - Measure BB Grants $6,619,824 $872,000 $1,053,000 $0 $1,215,000 $0 $0 $9,759,824 2218 - Measure RR Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2218 - Measure RR $1,500,000 $0 $0 $0 $0 $0 $0 $1,500,000 2220 - Road Maint. & Rehab Account (RMRA) Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2220 - Road Maint. & Rehab Account (RMRA) $6,819,983 $2,745,000 $2,250,000 $2,250,000 $2,250,000 $2,250,000 $0 $18,564,983 2304 - Local Recycling Programs Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2304 - Local Recycling Programs $160,000 $0 $0 $0 $0 $0 $0 $160,000 2403 - State Park Grant Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2403 - State Park Grant $2,294,000 $0 $0 $0 $0 $0 $0 $2,294,000 2703 - Landscape District Dougherty 1986-1 Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2703 - Landscape District Dougherty 1986- 1 $400,000 $0 $0 $0 $0 $0 $0 $400,000 2704 - Landscape District Santa Rita 1997-1 Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2704 - Landscape District Santa Rita 1997- 1 $195,000 $0 $0 $0 $0 $0 $0 $195,000 2705 - Street Light District East Dublin 1999-1 Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2705 - Street Light District East Dublin 1999-1 $927,517 $42,000 $42,000 $42,000 $42,000 $42,000 $0 $1,137,517 2801 - Public Art Fund Historical FY2025 FY2026 FY2027FY2028FY2029Future Total Total 2801 - Public Art Fund $1,150,450$780,000$300,000$250,000 $0 $0 $0 $2,480,450 2811 - Cable TV Facilities Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2811 - Cable TV Facilities $0 $300,000 $0 $0 $0 $0 $0 $300,000 Table of ContentsSummary - All Funds 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 8 728 2920 - Federal Grants - General Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2920 - Federal Grants - General $0 $127,230 $0 $0 $0 $0 $0 $127,230 2921 - State Grants - General Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2921 - State Grants - General $1,380,000 $193,876 $0 $0 $0 $0 $0 $1,573,876 2922 - Tri-Valley Transportation Council Grants Historical FY2025FY2026FY2027FY2028FY2029Future Total Total 2922 - Tri-Valley Transportation Council Grants $2,050,000$12,200,000 $0 $0 $0 $0 $0 $14,250,000 2923 - Alameda County Grant Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2923 - Alameda County Grant $0 $400,000 $0 $0 $0 $0 $0 $400,000 2924 - VRF (ACTC) Grants Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 2924 - VRF (ACTC) Grants $0 $0 $803,000 $0 $285,000 $0 $0 $1,088,000 4100 - Public Facility Fees Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4100 - Public Facility Fees $44,639,675 $1,563,505 $2,490,941 $0 $0 $0 $4,500,000 $53,194,121 4300 - Eastern Dublin Transportation Impact Fee Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4300 - Eastern Dublin Transportation Impact Fee $200,000 $0 $0 $0 $0 $0 $0 $200,000 4301 - Eastern Dublin Transportation Impact Fee Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4301 - Eastern Dublin Transportation Impact Fee $11,390,675 $0 $0 $0 $0 $0 $0 $11,390,675 4302 - Eastern Dublin Transportation Impact Fee Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4302 - Eastern Dublin Transportation Impact Fee $1,737,585 $0 $0 $0 $0 $0 $0 $1,737,585 4303 - Trafc Impact Fee - Category 3 Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4303 - Trafc Impact Fee - Category 3 $409,263 $0 $0 $0 $0 $0 $0 $409,263 4304 - Western Dublin Transportation Impact Fee Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4304 - Western Dublin Transportation Impact Fee $1,747,969 $816,320 $0 $0 $0 $0 $0 $2,564,289 Table of ContentsSummary - All Funds 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 9 729 4305 - Trafc Impact Fee - Dougherty Valley Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4305 - Trafc Impact Fee - Dougherty Valley $5,464,338 $0 $0 $0 $0 $0 $0 $5,464,338 4306 - Tri-Valley Transportation Development Fee Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4306 - Tri-Valley Transportation Development Fee $6,003,017 $0 $0 $0 $0 $0 $0 $6,003,017 4309 - Mitigation Contributions Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4309 - Mitigation Contributions $45,980 $0 $0 $0 $0 $0 $0 $45,980 4401 - Dublin Crossing Development Fee Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 4401 - Dublin Crossing Development Fee $1,000,000 $0 $0 $0 $0 $0 $0 $1,000,000 6205 - Internal Service Fund - Facilities Replacement Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 6205 - Internal Service Fund - Facilities Replacement $3,073,638 $7,150,000 $2,600,000 $650,000 $2,600,000 $5,350,000 $1,000,000 $22,423,638 6305 - Internal Service Fund - Equipment Replacement Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 6305 - Internal Service Fund - Equipment Replacement $777,300 $0 $500,000 $0 $0 $0 $0 $1,277,300 6605 - IT Fund Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 6605 - IT Fund $1,150,000 $471,000 $677,000 $0 $0 $0 $0 $2,298,000 7102 - Energy Improve. Lease Bond Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 7102 - Energy Improve. Lease Bond $20,656,074 $0 $0 $0 $0 $0 $0 $20,656,074 9901 - Other County Reimbursement Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 9901 - Other County Reimbursement $2,335,687 $0 $0 $0 $0 $0 $0 $2,335,687 9997 - Other Historical FY2025FY2026FY2027 FY2028FY2029Future Total Total 9997 - Other $0$103,324 $0 $0$9,150,000 $0 $0 $9,253,324 9998 - Unidentied Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 9998 - Unidentied $0 $0 $0 $5,278,654 $0 $0 $105,422,306 $110,700,960 Table of ContentsSummary - All Funds 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 10 730 9999 - Developer Built Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Total 9999 - Developer Built $12,857,142 $0 $0 $0 $0 $0 $0 $12,857,142 Unidentied HistoricalFY2025FY2026FY2027FY2028FY2029 Future Total Total Unidentied $0 $0 $0 $0 $0 $0$91,360,000 $91,360,000 Table of ContentsSummary - All Funds 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 11 731 Capital Projects Table of ContentsCapital Projects 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 12 732 General Improvements FY25 - FY29 General Improvements Projects (including Historical, Future) Audio Visual System Upgrade $1,671,040 2.27% Citywide Energy Improvements $25,513,970 34.69% Civic Center Elevator Modernization $900,000 1.22% Civic Center Exterior Glazing, Sealing & Painting $4,750,000 6.46% Civic Center Rehabilitation $2,236,730 3.04% Condition Assessment of Water Features $50,000 0.07% Corporation Yard Equipment Wash Pad $475,000 0.65% Dublin Arts Center $15,397,035 20.94% Dublin Standard Plans & Details Update $142,500 0.19% Electric Vehicle (EV) Charging Stations $727,459 0.99% Exterior Painting at Various Facilities $785,000 1.07% Facilities Parking Lot Resurfacing $1,000,000 1.36% Financial System Replacement $2,515,000 3.42% Irrigation System Upgrades $1,840,000 2.50% IT Infrastructure Improvement $1,243,600 1.69% Library Tenant Improvements $4,835,665 6.58% Municipal Fiber $140,000 0.19% Resiliency and Disaster Preparedness Improvements $2,754,189 3.75% Roof Replacement at Various City Facilities $655,000 0.89% Shannon Community Center Play Yard $200,000 0.27% Situational Awareness Camera Program $585,000 0.80% $52M$52M$52M $10M$10M $10M $6M$6M$6M $500K$500K $500K $2M$2M$2M $200K$200K $200K $4M$4M $4M Historical 2025 2026 2027 2028 2029 Future 0 $20M $40M $60M Table of ContentsGeneral Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 13 733 The Wave Pool Replastering $2,000,000 2.72% Waste Enclosures Upgrades $3,125,000 4.25% Summary of Requests Project No. / Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total GI0421 Audio Visual System Upgrade $473,040 $771,000 $427,000 $0 $0 $0 $0 $1,671,040 GI0121 Citywide Energy Improvements $23,013,970 $1,500,000 $1,000,000 $0 $0 $0 $0 $25,513,970 GI0001 Civic Center Elevator Modernization $0 $0 $900,000 $0 $0 $0 $0 $900,000 GI0125 Civic Center Exterior Glazing, Sealing & Painting $0 $4,250,000 $500,000 $0 $0 $0 $0 $4,750,000 GI0122 Civic Center Rehabilitation $2,031,730 $205,000 $0 $0 $0 $0 $0 $2,236,730 GI0225 Condition Assessment of Water Features $0 $50,000 $0 $0 $0 $0 $0 $50,000 GI0003 Corporation Yard Equipment Wash Pad $0 $0 $0 $0 $0 $0 $475,000 $475,000 GI0120 Dublin Arts Center $14,397,035 $0 $1,000,000 $0 $0 $0 $0 $15,397,035 GI0123 Dublin Standard Plans & Details Update $142,500 $0 $0 $0 $0 $0 $0 $142,500 GI0219 Electric Vehicle (EV) Charging Stations $230,000 $197,459 $0 $0 $0 $0 $300,000 $727,459 GI0223 Exterior Painting at Various Facilities $785,000 $0 $0 $0 $0 $0 $0 $785,000 GI0325 Facilities Parking Lot Resurfacing $0 $500,000 $500,000 $0 $0 $0 $0 $1,000,000 GI0319 Financial System Replacement $2,515,000 $0 $0 $0 $0 $0 $0 $2,515,000 GI0224 Irrigation System Upgrades $1,840,000 $0 $0 $0 $0 $0 $0 $1,840,000 GI0117 IT Infrastructure Improvement $1,243,600 $0 $0 $0 $0 $0 $0 $1,243,600 GI0521 Library Tenant Improvements $2,835,665 $2,000,000 $0 $0 $0 $0 $0 $4,835,665 GI0323 Municipal Fiber $140,000 $0 $0 $0 $0 $0 $0 $140,000 GI0221 Resiliency and Disaster Preparedness Improvements $1,102,189 $277,000 $1,375,000 $0 $0 $0 $0 $2,754,189 GI0423 Roof Replacement at $655,000 $0 $0 $0 $0 $0 $0 $655,000 Table of ContentsGeneral Improvements 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 14 734 Project No. / Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total Various City Facilities GI000 4 Shannon Community Center Play Yard $0 $0 $0 $0 $0 $200,000 $0 $200,000 GI0523 Situational Awareness Camera Program $585,000 $0 $0 $0 $0 $0 $0 $585,000 GI0006 The Wave Pool Replastering $0 $0 $0 $500,000 $1,500,000 $0 $0 $2,000,000 GI0425 Waste Enclosures Upgrades $0 $325,000 $0 $0 $0 $0 $2,800,000 $3,125,000 Total Summary of Requests $51,989,729 $10,075,459 $5,702,000 $500,000 $1,500,000 $200,000 $3,575,000 $73,542,188 Table of ContentsGeneral Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 15 735 Audio Visual System Upgrade Overview Project Number GI0421 Description This project provides for the planning, design, and construction of the audio visual-system upgrades in Ambrose Hall and adjoining conference room at Shannon Community Center, Alamilla Springs Ballroom at the Senior Center, Program Room at the Dublin Library, Emergency Operations Center, and Bray Community Room. These upgrades will include replacement of equipment to improve the service quality for rentals, meetings, corporate events, and staff use. In addition to those major staff/public AV facilities, smaller, citywide staff conference room hardware will be modernized, replaced, and/or updated. All these upgrades will bring the City’s audio-visual systems up to current industry standards and ADA compliance. Capital Cost Historical $473K FY2025 Budget $771K Total Budget (all years) $1.2M Project Total (to date) $1.67M Funding Sources Historical $473K FY2025 Budget $771K Total Budget (all years) $1.2M Project Total (to date) $1.67M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9600 - Equipment $342,790 $313,000 $330,000 $0 $0 $0 $0 $985,790 9200 - Contract Services $107,026 $330,000 $67,000 $0 $0 $0 $0 $504,026 9500 - Miscellaneous $0 $128,000 $30,000 $0 $0 $0 $0 $158,000 9100 - Salaries & Benefits $23,224 $0 $0 $0 $0 $0 $0 $23,224 Total $473,040 $771,000 $427,000 $0 $0 $0 $0 $1,671,040 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6605 - IT Fund $0 $471,000 $427,000 $0 $0 $0 $0 $898,000 1001 - General Fund $473,040 $0 $0 $0 $0 $0 $0 $473,040 2811 - Cable TV Facilities $0 $300,000 $0 $0 $0 $0 $0 $300,000 Total $473,040 $771,000 $427,000 $0 $0 $0 $0 $1,671,040 Table of ContentsAudio Visual System Upgrade 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 16 736 Operational Costs FY2025 Budget $20K Total Budget (all years) $20K Project Total $20K Project Timeline ●07/1/2025 The preliminary designs are complete and implementation began in 2024 with an anticipated completion in 2027. Table of ContentsAudio Visual System Upgrade 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 17 737 Citywide Energy Improvements Overview Project Number GI0121 Description This project provides for the planning (Investment Grade Audit), design, and construction of various energy upgrades, efciency improvements, lighting upgrades, energy generation, solar photovoltaic (PV) systems, and energy storage projects at facilities, parks, street rights-of-way, and other City-owned property.  The project includes lighting and controls upgrades at Mape Memorial Park, Alamo Creek Park, Ted Faireld Park, Bray Commons Park, Dolan Park, Emerald Glen Park, Fallon Sports Park, Heritage Park, and Shannon Park, as well as interior and exterior building lighting and controls upgrades at the Library, Corp Yard, Heritage Park and Museums facilities, Shannon Community Center, and Fire Stations 16, 17, and 18, and The Wave.  The conversion of approximately 1,626 streetlights in the East Ranch Street Light Assessment District (1999-1) to LED is also included.  There will be various mechanical, HVAC and controls upgrades at the following facilities: Library, Senior Center, Heritage Park and Museums, The Wave, and Fire Stations 16, 17, and 18.   Renewable, resiliency, and disaster preparedness improvements to prepare for future PG&E Public Safety Power Shutoff events and other emergency events will be provided with back-up generators at the Library, Shannon Community Center, Civic Center, Fire Stations 16, 17, and 18, while battery back-up or hydrogen fuel cell resiliency will be provided at 22 major street intersections throughout the city.  Solar PV and EV charging will be provided at Dublin Sports Grounds and Public Safety Complex.  Solar PV with battery energy storage systems will be provided at the Civic Center, The Wave, Corp Yard, and Senior Center.  Solar PV will be provided at the Library, Fallon Sports Park, and Fire Stations 17 and 18.  The new solar PV and replacement HVAC systems on the Library roof require a portion of the roof to be replaced, and to support the additional solar PV canopies at the Civic Center, portions of the parking lot will be recongured. Capital Cost Historical $23M FY2025 Budget $1.5M Total Budget (all years) $2.5M Project Total (to date) $25.5M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $22,766,850 $1,320,000 $930,000 $0 $0 $0 $0 $25,016,850 9200 - Contract Services $212,514 $150,000 $50,000 $0 $0 $0 $0 $412,514 9100 - Salaries & Benefits $34,406 $30,000 $20,000 $0 $0 $0 $0 $84,406 9500 - Miscellaneous $500 $0 $0 $0 $0 $0 $0 $500 Total $23,014,270 $1,500,000 $1,000,000 $0 $0 $0 $0 $25,514,270 Table of ContentsCitywide Energy Improvements 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 18 738 Funding Sources Historical $23M FY2025 Budget $1.5M Total Budget (all years) $2.5M Project Total (to date) $25.5M Operational Costs FY2025 Budget $0 Total Budget (all years) $85K Project Total $85K Project Timeline ●07/1/2025 The project is currently in various stages of design or construction. Construction is anticipated to be completed in 2027. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 7102 - Energy Improve. Lease Bond $20,656,074 $0 $0 $0 $0 $0 $0 $20,656,074 1001 - General Fund $1,497,120 $600,000 $400,000 $0 $0 $0 $0 $2,497,120 6205 - Internal Service Fund - Facilities Replacement $0 $900,000 $600,000 $0 $0 $0 $0 $1,500,000 2705 - Street Light District East Dublin 1999-1 $860,776 $0 $0 $0 $0 $0 $0 $860,776 Total $23,013,970 $1,500,000 $1,000,000 $0 $0 $0 $0 $25,513,970 Table of ContentsCitywide Energy Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 19 739 Civic Center Elevator Modernization Overview Project Number GI0001 Description This project will provide for the design and construction to upgrade the three existing elevators located within Civic Center (two at City Hall and one at Dublin Arts Center). Most elevators are built to provide about 30 to 40 years of service. The modernization process will include upgrading the critical parts of the elevators in order for them to accommodate new technology, have better performance, less energy consumption, and improved safety. This upgrade will also include the replacement of the interior panels and controls within the elevator cars.  Capital Cost FY2025 Budget $0 Total Budget (all years) $900K Project Total $900K Funding Sources FY2025 Budget $0 Total Budget (all years) $900K Project Total $900K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $0 $0 $750,000 $0 $0 $0 $0 $750,000 9200 - Contract Services $0 $0 $100,040 $0 $0 $0 $0 $100,040 9600 - Equipment $0 $0 $25,000 $0 $0 $0 $0 $25,000 9100 - Salaries & Benefits $0 $0 $24,960 $0 $0 $0 $0 $24,960 Total $0 $0 $900,000 $0 $0 $0 $0 $900,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $0 $0 $900,000 $0 $0 $0 $0 $900,000 Total $0 $0 $900,000 $0 $0 $0 $0 $900,000 Table of ContentsCivic Center Elevator Modernization 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 20 740 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 This project will begin in 2026. Table of ContentsCivic Center Elevator Modernization 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 21 741 Civic Center Exterior Glazing, Sealing & Painting Overview Project Number GI0125 Description This project will provide for design and construction for the sealing of the exterior natural stone veneer, concrete masonry block, reinstallation and replacement of the glazing in the window systems, and replacement of the caulked joints in the architectural metal panels and stonework at Civic Center. The work on the Dublin Art Center “DAC” side of Civic Center will be done in conjunction with DAC improvements. The project will also paint the accent trim colors inside City Hall and the exterior surfaces of the building that are not stone or architectural panels. Buildings should be sealed approximately every 10 years and caulking replaced every 30 years to maintain the exterior's appearance and to prevent damage caused by moisture inltration.  The design of the Civic Center clock tower exterior cladding replacement was added to this project and will begin in 2025. This work will include: demolish and discard existing exterior stone and metal cladding; repair up to 30% of the existing light gauge metal framing; install new stone and metal cladding over new weather resistant barrier, sheathing, adhesive, stucco and lath; remove existing electrical and lighting system; install new electrical and lighting system; remove, remediate, store and reinstall existing clock faces. Capital Cost FY2025 Budget $4.25M Total Budget (all years) $4.75M Project Total $4 .75M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $0 $3,650,000 $500,000 $0 $0 $0 $0 $4,150,000 9200 - Contract Services $0 $450,000 $0 $0 $0 $0 $0 $450,000 9100 - Salaries & Benefits $0 $150,000 $0 $0 $0 $0 $0 $150,000 Total $0 $4,250,000 $500,000 $0 $0 $0 $0 $4,750,000 Table of ContentsCivic Center Exterior Glazing, Sealing & Painting 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 22 742 Funding Sources FY2025 Budget $4.25M Total Budget (all years) $4.75M Project Total $4 .75M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The project is currently in design development with the progressive design-build contractor. Construction is anticipated to begin in 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $0 $4,250,000 $500,000 $0 $0 $0 $0 $4,750,000 Total $0 $4,250,000 $500,000 $0 $0 $0 $0 $4,750,000 Table of ContentsCivic Center Exterior Glazing, Sealing & Painting 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 23 743 Civic Center Rehabilitation Overview Project Number GI0122 Description This project provides for the planning, design, and construction of various rehabilitation and renovation projects at Civic Center.  Projects may include: renovation of all restrooms, showers, kitchenettes, and the employee break room; modications to conference rooms; lighting and ceiling replacement; site improvements to the parking lot area and surrounding walkways of the Civic Center; plaza and landscaping improvements; building security evaluation and upgrades; repainting; and Americans with Disabilities Act (ADA) and Code upgrades. Interior repainting in select areas was completed during construction of the Civic Center HVAC and Roof Replacement project, and minor parking lot and walkway improvements are anticipated to be designed and constructed in conjunction with the Dublin Arts Center project. This project also includes the partitioning of three spaces into six on the second oor of the Civic Center.   This project is funded by General Fund Reserves. Other potential funding sources for the building security upgrades may include Federal and State public safety grants.  Capital Cost Historical $2.03M FY2025 Budget $205K Total Budget (all years) $205K Project Total (to date) $2.24M Funding Sources Historical $2.03M FY2025 Budget $205K Total Budget (all years) $205K Project Total (to date) $2.24M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $1,425,000 $100,000 $0 $0 $0 $0 $0 $1,525,000 9200 - Contract Services $511,590 $100,000 $0 $0 $0 $0 $0 $611,590 9100 - Salaries & Benefits $80,140 $0 $0 $0 $0 $0 $0 $80,140 9500 - Miscellaneous $15,000 $5,000 $0 $0 $0 $0 $0 $20,000 Total $2,031,730 $205,000 $0 $0 $0 $0 $0 $2,236,730 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1101 - General Fund Designated Reserve $2,031,730 $205,000 $0 $0 $0 $0 $0 $2,236,730 Total $2,031,730 $205,000 $0 $0 $0 $0 $0 $2,236,730 Table of ContentsCivic Center Rehabilitation 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 24 744 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The project is currently in various stages of design or construction. Interior repainting in select areas was completed during construction of the Civic Center HVAC and Roof Replacement project, and minor parking lot and walkway improvements are being constructed in conjunction with the Dublin Arts Center project. The partitioning of three spaces into six on the second oor of the Civic Center is complete.  Table of ContentsCivic Center Rehabilitation 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 25 745 Condition Assessment of Water Features Overview Project Number GI0225 Description This project is a comprehensive condition assessment for outdoor water features including fountains and splash pads at Civic Center, Shannon Center, Emerald Glen Park, Senior Center, and Devany Square. This includes examining the structural integrity, plumbing systems, water quality, and overall functionality. Through detailed inspections and evaluations, potential issues such as wear and tear, corrosion, or outdated technology can be identied. Following this assessment, a strategic project can be developed to address the ndings. This may include developing plans for either replacing the existing water features with modern and sustainable designs, incorporating advanced water circulation systems, or considering other alternatives that align with the evolving needs and preferences of the community.  Capital Cost FY2025 Budget $50K Total Budget (all years) $50K Project Total $50K Funding Sources FY2025 Budget $50K Total Budget (all years) $50K Project Total $50K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9200 - Contract Services $0 $45,000 $0 $0 $0 $0 $0 $45,000 9100 - Salaries & Benefits $0 $5,000 $0 $0 $0 $0 $0 $5,000 Total $0 $50,000 $0 $0 $0 $0 $0 $50,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $0 $50,000 $0 $0 $0 $0 $0 $50,000 Total $0 $50,000 $0 $0 $0 $0 $0 $50,000 Table of ContentsCondition Assessment of Water Features 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 26 746 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The planning phase for the Civic Center fountain will begin in 2025. Table of ContentsCondition Assessment of Water Features 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 27 747 Corporation Yard Equipment Wash Pad Overview Project Number GI0003 Description This project will provide for design and construction of a vehicle and equipment wash pad at the Corporation Yard. The wash pad will capture wash water and solid wastes separate the uids from solids lter the and lter the uids prior to discharge or storage for reuse. The wash pad will reduce water usage and ensure equipment is maintained using best management practices required by the Municipal Regional Stormwater Permit and EPA.  Capital Cost FY2025 Budget $0 Total Budget (all years) $0 Future $475K Project Total $475K Funding Sources FY2025 Budget $0 Total Budget (all years) $0 Future $475K Project Total $475K Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $0 $0 $0 $0 $0 $0 $315,000 $315,000 9200 - Contract Services $0 $0 $0 $0 $0 $0 $125,000 $125,000 9100 - Salaries & Benefits $0 $0 $0 $0 $0 $0 $35,000 $35,000 Total $0 $0 $0 $0 $0 $0 $475,000 $475,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $0 $0 $0 $0 $0 $0 $475,000 $475,000 Total $0 $0 $0 $0 $0 $0 $475,000 $475,000 Table of ContentsCorporation Yard Equipment Wash Pad 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 28 748 Project Timeline ●07/1/2025 The project will begin in 2030. Table of ContentsCorporation Yard Equipment Wash Pad 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 29 749 Dublin Ar ts Center Overview Project Number GI0120 Description This project provides for the design and improvements of an approximately 13,000-square-foot Cultural Arts Center on the rst oor of the Civic Center, which was formerly occupied by Dublin Police Services. The Parks & Recreation Master Plan identies a Cultural Arts Center that will serve as a multi-use facility that affords cultural, educational, and social opportunities for the community. The Cultural Arts Center will include: an Art gallery, Black Box theater space; multi-purpose art and music classrooms; a dance studio; and restrooms. The project also provides for the replacement of the heating, ventilation, and air conditioning (HVAC) systems, HVAC controls, roof replacement, major upgrades to the main telecommunication room, and the relocation of the Parks and Community Services Department ofces to the second oor of the Dublin Arts Center. Capital Cost Historical $14.4M FY2025 Budget $0 Total Budget (all years) $1M Project Total (to date) $15.4M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $9,700,317 $0 $1,000,000 $0 $0 $0 $0 $10,700,317 9200 - Contract Services $3,678,519 $0 $0 $0 $0 $0 $0 $3,678,519 9600 - Equipment $800,000 $0 $0 $0 $0 $0 $0 $800,000 9100 - Salaries & Benefits $199,945 $0 $0 $0 $0 $0 $0 $199,945 9500 - Miscellaneous $18,254 $0 $0 $0 $0 $0 $0 $18,254 Total $14,397,035 $0 $1,000,000 $0 $0 $0 $0 $15,397,035 Table of ContentsDublin Arts Center 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 30 750 Funding Sources Historical $14.4M FY2025 Budget $0 Total Budget (all years) $1M Project Total (to date) $15.4M Operational Costs FY2025 Budget $0 Total Budget (all years) $2.8M Project Total $2.8M Project Timeline ●07/1/2025 The project is currently under construction and is anticipated to be substantially completed in 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1101 - General Fund Designated Reserve $6,964,197 $0 $250,000 $0 $0 $0 $0 $7,214,197 4100 - Public Facility Fees $5,889,200 $0 $0 $0 $0 $0 $0 $5,889,200 6205 - Internal Service Fund - Facilities Replacement $1,543,638 $0 $0 $0 $0 $0 $0 $1,543,638 6305 - Internal Service Fund - Equipment Replacement $0 $0 $500,000 $0 $0 $0 $0 $500,000 6605 - IT Fund $0 $0 $250,000 $0 $0 $0 $0 $250,000 Total $14,397,035 $0 $1,000,000 $0 $0 $0 $0 $15,397,035 Table of ContentsDublin Arts Center 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 31 751 Dublin Standard Plans & Details Update Overview Project Number GI0123 Description This project will update the City’s Standard Plans, Details and Specications utilized by the Public Works Department for design and construction of public improvements within the City’s right-of-way and properties. These Standards are necessary for consistency to provide guidance to designers, and to specify the current requirements for public infrastructure to be constructed and maintained by the City. The Standards require periodic update and revision to be aligned with current industry practice, changes in materials and construction methods, as well as to be compliant with local, State, and federal goals and requirements, such as the Storm Water Municipal Regional Permit and accessibility requirements of the ADA .   Capital Cost Historical $143K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $143K Funding Sources Historical $143K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $143K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9200 - Contract Services $124,608 $0 $0 $0 $0 $0 $0 $124,608 9100 - Salaries & Benefits $15,392 $0 $0 $0 $0 $0 $0 $15,392 9500 - Miscellaneous $2,500 $0 $0 $0 $0 $0 $0 $2,500 Total $142,500 $0 $0 $0 $0 $0 $0 $142,500 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $142,500 $0 $0 $0 $0 $0 $0 $142,500 Total $142,500 $0 $0 $0 $0 $0 $0 $142,500 Table of ContentsDublin Standard Plans & Details Update 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 32 752 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The project is currently in plan review and is anticipated to be completed in 2025. Table of ContentsDublin Standard Plans & Details Update 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 33 753 Electric Vehicle (EV) Charging Stations Overview Project Number GI0219 Description This project provides for the design and construction of at least two electric vehicle (EV) charging spaces at The Wave, at Emerald Glen Park and the underground infrastructure for future expansion. Additionally, two direct-current (DC) EV fast chargers will be installed at the Dublin Sports Grounds. In future years, the project could provide for design and construction of EV charging spaces at other City facilities. Staff will apply for grant funding for the charging units; agencies typically fund conduits, wiring, and electrical panel upgrades as local/match contribution to grant funding.  Capital Cost Historical $230K FY2025 Budget $197K Total Budget (all years) $197K Future $300K Project Total (to date) $727K Funding Sources Historical $230K FY2025 Budget $197K Total Budget (all years) $197K Future $300K Project Total (to date) $727K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $92,181 $197,459 $0 $0 $0 $0 $110,000 $399,640 9600 - Equipment $94,107 $0 $0 $0 $0 $0 $100,000 $194,107 9200 - Contract Services $30,211 $0 $0 $0 $0 $0 $75,000 $105,211 9100 - Salaries & Benefits $12,620 $0 $0 $0 $0 $0 $15,000 $27,620 9500 - Miscellaneous $881 $0 $0 $0 $0 $0 $0 $881 Total $230,000 $197,459 $0 $0 $0 $0 $300,000 $727,459 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $0 $0 $0 $0 $0 $0 $300,000 $300,000 1101 - General Fund Designated Reserve $212,000 $70,229 $0 $0 $0 $0 $0 $282,229 2920 - Federal Grants - General $0 $127,230 $0 $0 $0 $0 $0 $127,230 2207 - Transportation for Clean Air $18,000 $0 $0 $0 $0 $0 $0 $18,000 Total $230,000 $197,459 $0 $0 $0 $0 $300,000 $727,459 Table of ContentsElectric Vehicle (EV) Charging Stations 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 34 754 Operational Costs FY2025 Budget $0 Total Budget (all years) $1.5K Project Total $1.5K Project Timeline ●07/1/2025 Installation of the EV charges at The Wave is complete. The City received an Energy Efciency Conservation Block Grant from the U.S. Department of Energy, which partially funded the installation of the two DC EV fast chargers at the Dublin Sports Grounds., and the installation is anticipated to be completed in 2025. Table of ContentsElectric Vehicle (EV) Charging Stations 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 35 755 Exterior Painting at Various Facilities Overview Project Number GI0223 Description This project provides for the design and construction to paint the exterior and make minor repairs at various City facilities. Buildings should be painted approximately every 10 years to maintain the structures' appearance and to prevent damage caused by moisture inltration. This project will include work at the following locations: Heritage Museum, Old St. Raymond's Church, Kolb House, Senior Center, Fire Stations 16, 17, and 18, The Wave, and the Library. These improvements will be designed and constructed in conjunction with the Civic Center Exterior Glazing, Sealing & Painting project. Capital Cost Historical $785K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $785K Funding Sources Historical $785K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $785K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $605,000 $0 $0 $0 $0 $0 $0 $605,000 9200 - Contract Services $150,048 $0 $0 $0 $0 $0 $0 $150,048 9100 - Salaries & Benefits $29,952 $0 $0 $0 $0 $0 $0 $29,952 Total $785,000 $0 $0 $0 $0 $0 $0 $785,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $785,000 $0 $0 $0 $0 $0 $0 $785,000 Total $785,000 $0 $0 $0 $0 $0 $0 $785,000 Table of ContentsExterior Painting at Various Facilities 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 36 756 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The project is currently in design development with the progressive design-build contractor. Construction is anticipated to begin in 2025. Table of ContentsExterior Painting at Various Facilities 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 37 757 Facilities Parking Lot Resurfacing Overview Project Number GI0325 Description This project provides for the design and construction to resurface parking lots at various City facilities and make renovations to accommodate the newest ADA and parking lot standards. This project will include work at the following locations: Alamo Creek Park, Emerald Glen Park, Senior Center, and Shannon Community Center.  Capital Cost FY2025 Budget $500K Total Budget (all years) $1M Project Total $1M Funding Sources FY2025 Budget $500K Total Budget (all years) $1M Project Total $1M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $0 $340,000 $340,000 $0 $0 $0 $0 $680,000 9200 - Contract Services $0 $140,000 $140,000 $0 $0 $0 $0 $280,000 9100 - Salaries & Benefits $0 $20,000 $20,000 $0 $0 $0 $0 $40,000 Total $0 $500,000 $500,000 $0 $0 $0 $0 $1,000,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $0 $500,000 $500,000 $0 $0 $0 $0 $1,000,000 Total $0 $500,000 $500,000 $0 $0 $0 $0 $1,000,000 Table of ContentsFacilities Parking Lot Resurfacing 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 38 758 Project Timeline ●07/1/2025 The project started design in 2024 and will be incorporated into the 2026 Annual Street Resurfacing project for Alamo Creek Park and Emerald Glen Park. The parking lots at Senior Center and Shannon Community Center will be evaluated and preliminary engineering is anticipated to begin in 2026. Table of ContentsFacilities Parking Lot Resurfacing 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 39 759 Financial System Replacement Overview Project Number GI0319 Description This project provides for the replacement of the City's Enterprise Resource Planning (ERP) system and other related technological projects that support the City Council’s initiative to “Become a 24/7 City Hall to Enhance Resident and Business Engagement.” This includes the OpenGov nancial transparency software and upgrades to the City’s Laserche document management software.  The City's ERP system serves as the primary software platform for Finance, Human Resources, Public Works, Community Development, and all other core transactions. The outgoing system was implemented in Fiscal Year 2008-09 and has reached the end of its 10-year lifespan. Capital Cost Historical $2.52M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $2.52M Funding Sources Historical $2.52M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $2.52M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9600 - Equipment $1,511,821 $0 $0 $0 $0 $0 $0 $1,511,821 9200 - Contract Services $1,002,679 $0 $0 $0 $0 $0 $0 $1,002,679 9500 - Miscellaneous $500 $0 $0 $0 $0 $0 $0 $500 Total $2,515,000 $0 $0 $0 $0 $0 $0 $2,515,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $1,860,000 $0 $0 $0 $0 $0 $0 $1,860,000 6305 - Internal Service Fund - Equipment Replacement $655,000 $0 $0 $0 $0 $0 $0 $655,000 Total $2,515,000 $0 $0 $0 $0 $0 $0 $2,515,000 Table of ContentsFinancial System Replacement 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 40 760 Operational Costs FY2025 Budget $240K Total Budget (all years) $240K Project Total $240K Project Timeline ●07/1/2025 The implementation started in spring 2021. The Finance Module went live in July 2022, the Human Resources and Payroll modules went live in April 2023, and the Permitting and Licensing modules went live in July 2024. The complete transition to the new ERP system is expected in Fiscal Year 2024- 25, with technical conguration and training continuing throughout the year. Table of ContentsFinancial System Replacement 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 41 761 Irrigation System Upgrades Overview Project Number GI0224 Description This project will include the planning, design and installation of approximately sixty new irrigation controllers along streets, parks and facilities. System-wide communication upgrades with the Central Irrigation System will improve water conservation in response to daily weather conditions. Additionally, consultant services will be utilized to improve system optimization including site specic scheduling for up to twenty-ve of the City's large landscapes. A series of training sessions will be held with the City's Maintenance Division to ensure the ongoing operation of the system.  The $1.38 million identied as "State Grant" is from the State of California - Department of Water Resources Urban Community Drought Relief Grant, which was awarded to Alameda County Flood Control and Water Conservation District, Zone 7, as part of a grant application that included several projects from local sponsors in the Livermore-Amador Valley. All activities to implement the project must be completed by December 31, 2026, to be eligible for State Grant funding.  Capital Cost Historical $1.84M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $1.84M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $721,000 $0 $0 $0 $0 $0 $0 $721,000 9600 - Equipment $650,000 $0 $0 $0 $0 $0 $0 $650,000 9200 - Contract Services $350,000 $0 $0 $0 $0 $0 $0 $350,000 9100 - Salaries & Benefits $104,000 $0 $0 $0 $0 $0 $0 $104,000 9500 - Miscellaneous $15,000 $0 $0 $0 $0 $0 $0 $15,000 Total $1,840,000 $0 $0 $0 $0 $0 $0 $1,840,000 Table of ContentsIrrigation System Upgrades 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 42 762 Funding Sources Historical $1.84M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $1.84M Operational Costs FY2025 Budget $45K Total Budget (all years) $45K Project Total $45K Project Timeline ●07/1/2025 The improvement agreement to replace the controller was awarded June 3, 2025, and the project is currently in construction. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2921 - State Grants - General $1,380,000 $0 $0 $0 $0 $0 $0 $1,380,000 1001 - General Fund $460,000 $0 $0 $0 $0 $0 $0 $460,000 Total $1,840,000 $0 $0 $0 $0 $0 $0 $1,840,000 Table of ContentsIrrigation System Upgrades 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 43 763 IT Infrastructure Improvement Overview Project Number GI0117 Description This project allows for the replacement and upgrade of aging network hardware as well as the implementation of centralized Information Technology management tools that will increase efciency in City operations.  Capital Cost Historical $1.24M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $1.24M Funding Sources Historical $1.24M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $1.24M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9600 - Equipment $666,391 $0 $0 $0 $0 $0 $0 $666,391 9200 - Contract Services $302,886 $0 $0 $0 $0 $0 $0 $302,886 9400 - Repairs/Improvements $273,644 $0 $0 $0 $0 $0 $0 $273,644 9500 - Miscellaneous $679 $0 $0 $0 $0 $0 $0 $679 Total $1,243,600 $0 $0 $0 $0 $0 $0 $1,243,600 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6605 - IT Fund $1,150,000 $0 $0 $0 $0 $0 $0 $1,150,000 1101 - General Fund Designated Reserve $93,600 $0 $0 $0 $0 $0 $0 $93,600 Total $1,243,600 $0 $0 $0 $0 $0 $0 $1,243,600 Table of ContentsIT Infrastructure Improvement 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 44 764 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 This project is ongoing. Equipment will be replaced as it reaches the end of its useful life. Table of ContentsIT Infrastructure Improvement 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 45 765 Library Tenant Improvements Overview Project Number GI0521 Description This project provides for the design and construction of tenant improvements to the Dublin Library, including completion of 5,150 square feet of currently unoccupied space within the library building. The 37,000 square-foot library building was completed in Fiscal Year 2002-03, however only 30,000 square feet was occupied. In Fiscal Year 2016-17, a tenant improvement project was completed which opened an additional 1,850 square feet of space adjacent to the children's area. This project will open the remaining 5,150 square feet of building area for library and community use. Improvements will include: a large ex space; new small group study rooms; expansion of the children’s area; modication of shelving and xtures; carpet replacement; repainting; and the refurbishing of select systems and interior surfaces.  Capital Cost Historical $2.84M FY2025 Budget $2M Total Budget (all years) $2M Project Total (to date) $4 .84M Funding Sources Historical $2.84M FY2025 Budget $2M Total Budget (all years) $2M Project Total (to date) $4 .84M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $2,260,270 $1,300,000 $0 $0 $0 $0 $0 $3,560,270 9200 - Contract Services $492,885 $560,000 $0 $0 $0 $0 $0 $1,052,885 9100 - Salaries & Benefits $62,510 $140,000 $0 $0 $0 $0 $0 $202,510 9500 - Miscellaneous $20,000 $0 $0 $0 $0 $0 $0 $20,000 Total $2,835,665 $2,000,000 $0 $0 $0 $0 $0 $4,835,665 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $90,000 $2,000,000 $0 $0 $0 $0 $0 $2,090,000 4100 - Public Facility Fees $1,745,665 $0 $0 $0 $0 $0 $0 $1,745,665 1001 - General Fund $1,000,000 $0 $0 $0 $0 $0 $0 $1,000,000 Total $2,835,665 $2,000,000 $0 $0 $0 $0 $0 $4,835,665 Table of ContentsLibrary Tenant Improvements 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 46 766 Operational Costs FY2025 Budget $0 Total Budget (all years) $8K Project Total $8K Project Timeline ●07/1/2025 Planning and preliminary design began in Fiscal Year 2023-24 and schematic design started in 2024. Construction is anticipated to begin in 2026. Table of ContentsLibrary Tenant Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 47 767 Municipal Fiber Overview Project Number GI0323 Description This project provides for the planning, design, and construction to improve and extend the existing City Information Technology ber optic network cabling and infrastructure by laying the foundation for future high speed networking capability and improve existing City facilities' networking speed and reliability by interconnecting City facilities from Civic Center to Heritage Park and Museums, Shannon Community Center, Senior Center, and the Corp Yard. An approximate 13- mile loop is anticipated to connect these facilities. This project will also assist in improving Trafc Operations with faster ber optic networks that support smart and adaptive trafc software. Additionally, Dublin Police Services' ability and effectiveness in crime prevention will be enhanced with faster connections to the situational awareness cameras, license plate readers, and major intersection video streaming. Lastly, this project will improve Citywide Wi-Fi access, performance, and security. Capital Cost Historical $140K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $140K Funding Sources Historical $140K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $140K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9200 - Contract Services $119,200 $0 $0 $0 $0 $0 $0 $119,200 9100 - Salaries & Benefits $20,800 $0 $0 $0 $0 $0 $0 $20,800 Total $140,000 $0 $0 $0 $0 $0 $0 $140,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $140,000 $0 $0 $0 $0 $0 $0 $140,000 Total $140,000 $0 $0 $0 $0 $0 $0 $140,000 Table of ContentsMunicipal Fiber 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 48 768 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The preliminary planning phase began in 2022 with identifying the locations citywide of existing infrastructure. A Request for Proposals will be issued in 2025 for consulting services for the development of a ve-year ber optic master plan and feasibility study, which will assess the existing City network infrastructure and the required build out. Table of ContentsMunicipal Fiber 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 49 769 Resiliency and Disaster Preparedness Improvements Overview Project Number GI0221 Description Beginning in the end of December 2022 through the rst few weeks of 2023, Dublin and most of California experienced damage due to a series of rain fall events that were declared a major disaster in Alameda County by the President on January 17, 2023. The City experienced damage at various sites, including street rights-of-way, parks and open space, and facilities and buildings. This project provide for the planning, design, environmental permitting, if necessary, and construction to make the repairs at various sites impacted. The following locations and types of repairs have been identied:  Dougherty Hills Open Space, Crossridge Road Trailhead – slide repair Dublin Boulevard, between Inspiration Drive and Silvergate Drive – slide repair Mape Memorial Park – Pathway Relocation Koopman Canyon Creek at Shannon Community Center/San Ramon Road – channel and culvert improvements Martin Canyon Creek at Silvergate Drive - channel improvements Koopman Canyon Creek at Fenwick Court - trash rack repair and channel improvements Clark Canyon Creek at Padre Way - track rack repair and channel improvements The City has applied for grants for this project through the Federal Emergency Management Agency (FEMA) and California Ofce of Emergency Services (CalOES). Capital Cost Historical $1.1M FY2025 Budget $277K Total Budget (all years) $1.65M Project Total (to date) $2.75M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $825,000 $0 $1,000,000 $0 $0 $0 $0 $1,825,000 9200 - Contract Services $223,000 $277,000 $300,000 $0 $0 $0 $0 $800,000 9100 - Salaries & Benefits $54,189 $0 $75,000 $0 $0 $0 $0 $129,189 Total $1,102,189 $277,000 $1,375,000 $0 $0 $0 $0 $2,754,189 Table of ContentsResiliency and Disaster Preparedness Improvements 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 50 770 Funding Sources Historical $1.1M FY2025 Budget $277K Total Budget (all years) $1.65M Project Total (to date) $2.75M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The clean-up effort immediately following the storm events are complete and the preliminary engineering for the permanent repair began in Fiscal Year 2023-24. The project is currently in the preliminary engineering, design, or construction phases. A construction contract for the Mape Memorial Park Pathway Relocation project was awarded in May 2025 and construction began in June 2025. The two slide repair projects are anticipated to begin construction in summer 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $1,102,189 $277,000 $1,375,000 $0 $0 $0 $0 $2,754,189 Total $1,102,189 $277,000 $1,375,000 $0 $0 $0 $0 $2,754,189 Table of ContentsResiliency and Disaster Preparedness Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 51 771 Roof Replacement at Various City Facilities Overview Project Number GI0423 Description This project provides for the design and construction of roof replacement or partial roof replacement at various City facilities. Typically, a roof has a 20-30-year service life depending on the roof type. This project will include work at the following locations: Heritage Museum, Old St. Raymond's Church, Senior Center, and Fire Station 16.  These improvements will be designed and constructed in conjunction with the Civic Center Exterior Glazing, Sealing & Painting project. Capital Cost Historical $655K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $655K Funding Sources Historical $655K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $655K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $550,000 $0 $0 $0 $0 $0 $0 $550,000 9200 - Contract Services $75,048 $0 $0 $0 $0 $0 $0 $75,048 9100 - Salaries & Benefits $29,952 $0 $0 $0 $0 $0 $0 $29,952 Total $655,000 $0 $0 $0 $0 $0 $0 $655,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $655,000 $0 $0 $0 $0 $0 $0 $655,000 Total $655,000 $0 $0 $0 $0 $0 $0 $655,000 Table of ContentsRoof Replacement at Various City Facilities 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 52 772 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The project is currently in design development with the progressive design-build contractor. Construction is anticipated to begin in 2025. Table of ContentsRoof Replacement at Various City Facilities 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 53 773 Shannon Community Center Play Yard Overview Project Number GI0004 Description This project will provide for design and construction of the replacement of the poured-in-place safety surfacing at the preschool playground at the Shannon Community Center Preschool. The surfacing will create a modern, safe, and stimulating environment that aligns with the evolving needs of our community's preschool-aged children. Capital Cost FY2025 Budget $0 Total Budget (all years) $200K Project Total $200K Funding Sources FY2025 Budget $0 Total Budget (all years) $200K Project Total $200K Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $0 $0 $0 $0 $0 $130,000 $0 $130,000 9200 - Contract Services $0 $0 $0 $0 $0 $55,000 $0 $55,000 9100 - Salaries & Benefits $0 $0 $0 $0 $0 $15,000 $0 $15,000 Total $0 $0 $0 $0 $0 $200,000 $0 $200,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $0 $0 $0 $0 $0 $200,000 $0 $200,000 Total $0 $0 $0 $0 $0 $200,000 $0 $200,000 Table of ContentsShannon Community Center Play Yard 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 54 774 Project Timeline ●07/1/2025 The project will begin in 2028. Table of ContentsShannon Community Center Play Yard 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 55 775 Situational Awareness Camera Program Overview Project Number GI0523 Description This project will provide 40 situational awareness cameras at 10 locations to cover known gaps within the City. These cameras will be strategically located along major corridors and arteries to maximize observation of Dublin’s many entrance and exit points into and out of town. These cameras will be valuable technological resources that assist in criminal investigations and the apprehension of law violators within the City. Capital Cost Historical $585K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $585K Funding Sources Historical $585K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $585K Operational Costs FY2025 Budget $0 Total Budget (all years) $80K Project Total $80K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $533,000 $0 $0 $0 $0 $0 $0 $533,000 9200 - Contract Services $44,928 $0 $0 $0 $0 $0 $0 $44,928 9100 - Salaries & Benefits $7,072 $0 $0 $0 $0 $0 $0 $7,072 Total $585,000 $0 $0 $0 $0 $0 $0 $585,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $585,000 $0 $0 $0 $0 $0 $0 $585,000 Total $585,000 $0 $0 $0 $0 $0 $0 $585,000 Table of ContentsSituational Awareness Camera Program 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 56 776 Project Timeline ●07/1/2025 The project is in various stages of design and construction with two cameras installed in FY 2024-25. Table of ContentsSituational Awareness Camera Program 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 57 777 The Wave Pool Replastering Overview Project Number GI0006 Description This project will provide for the design and construction to replace the pool plaster at The Wave Indoor Pool, Outdoor Sport Pool, and Aquatic Play Structure. Capital Cost FY2025 Budget $0 Total Budget (all years) $2M Project Total $2M Funding Sources FY2025 Budget $0 Total Budget (all years) $2M Project Total $2M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $0 $0 $0 $0 $1,310,000 $0 $0 $1,310,000 9200 - Contract Services $0 $0 $0 $430,000 $120,000 $0 $0 $550,000 9100 - Salaries & Benefits $0 $0 $0 $70,000 $70,000 $0 $0 $140,000 Total $0 $0 $0 $500,000 $1,500,000 $0 $0 $2,000,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $0 $0 $0 $500,000 $1,500,000 $0 $0 $2,000,000 1001 - General Fund $0 $0 $0 $0 $0 $0 $0 $0 Total $0 $0 $0 $500,000 $1,500,000 $0 $0 $2,000,000 Table of ContentsThe Wave Pool Replastering 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 58 778 Project Timeline ●07/1/2025 The project will begin in FY 2026-27. Table of ContentsThe Wave Pool Replastering 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 59 779 Waste Enclosures Upgrades Overview Project Number GI0425 Description This project provides for the design and construction to replace or upgrade waste enclosures at various City facilities. The rst location to be upgraded will be at Civic Center, serving City Hall and the Dublin Arts Center. Other locations for future upgrades include Senior Center, Shannon Community Center, Library, Dublin Sports Grounds, Emerald Glen Park, and Fire Stations 16, 17, and 18. Capital Cost FY2025 Budget $325K Total Budget (all years) $325K Future $2.8M Project Total $3.13M Funding Sources FY2025 Budget $325K Total Budget (all years) $325K Future $2.8M Project Total $3.13M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $0 $213,000 $0 $0 $0 $0 $1,840,000 $2,053,000 9200 - Contract Services $0 $89,000 $0 $0 $0 $0 $760,000 $849,000 9100 - Salaries & Benefits $0 $23,000 $0 $0 $0 $0 $200,000 $223,000 Total $0 $325,000 $0 $0 $0 $0 $2,800,000 $3,125,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $0 $131,124 $0 $0 $0 $0 $2,800,000 $2,931,124 2921 - State Grants - General $0 $193,876 $0 $0 $0 $0 $0 $193,876 Total $0 $325,000 $0 $0 $0 $0 $2,800,000 $3,125,000 Table of ContentsWaste Enclosures Upgrades 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 60 780 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The design for the Civic Center location began in 2024 and will be constructed as a part of the Citywide Energy Improvements Project beginning in late 2025. Table of ContentsWaste Enclosures Upgrades 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 61 781 Parks FY25 - FY29 Parks Projects (including Historical, Future) Alamo Creek Park and Assessment District - Fence Replacement $850,000 1.04% Don Biddle Community Park $24,824,005 30.51% Downtown Dublin Town Square Park $4,611,565 5.67% Dublin Sports Grounds Rehabilitation $3,650,000 4.49% Fallon Sports Park - Articial Turf Field Replacement $2,250,000 2.77% Fallon Sports Park - Phase 3 $9,623,000 11.83% Fallon Sports Park Baseball Field G Upgrades $400,000 0.49% Forest Park $3,538,947 4.35% Iron Horse Nature Park and Open Space $12,169,900 14.96% Kolb Park Renovation $2,425,000 2.98% Parks Playground Replacement $1,109,560 1.36% Persimmon Drive Pedestrian Path Rehabilitation $195,000 0.24% Restrooms Replacement $1,475,000 1.81% Sports Courts Resurfacing $2,100,000 2.58% Sunday School Barn Flooring $385,000 0.47% Wallis Ranch Community Park $11,760,000 14.45% $58M$58M$58M $3M$3M$3M $6M$6M $6M $3M$3M$3M $1M$1M $1M $5M$5M $5M $6M$6M $6M Historical 2025 2026 2027 2028 2029 Future 0 $25M $50M $75M Summary of Requests Project No. / Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total PK012 2 Alamo Creek Park and Assessment District - Fence Replacement $850,000 $0 $0 $0 $0 $0 $0 $850,000 Table of ContentsParks 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 62 782 Project No. / Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total PK0115 Don Biddle Community Park $24,824,005 $0 $0 $0 $0 $0 $0 $24,824,005 PK022 1 Downtown Dublin Town Square Park $106,885 $4,680 $0 $0 $0 $0 $4,500,000 $4,611,565 PK000 2 Dublin Sports Grounds Rehabilitation $0 $0 $0 $150,000 $600,000 $2,900,000 $0 $3,650,000 PK000 3 Fallon Sports Park - Artificial Turf Field Replacement $0 $0 $0 $0 $0 $2,250,000 $0 $2,250,000 PK0119 Fallon Sports Park - Phase 3 $9,623,000 $0 $0 $0 $0 $0 $0 $9,623,000 PK022 5 Fallon Sports Park Baseball Field G Upgrades $0 $150,000 $250,000 $0 $0 $0 $0 $400,000 PK032 2 Forest Park $2,798,947 $740,000 $0 $0 $0 $0 $0 $3,538,947 PK042 2 Iron Horse Nature Park and Open Space $5,403,000 $1,497,305 $2,490,941 $2,778,654 $0 $0 $0 $12,169,900 PK022 4 Kolb Park Renovation $450,000 $0 $1,975,000 $0 $0 $0 $0 $2,425,000 PK012 4 Parks Playground Replacement $1,109,560 $0 $0 $0 $0 $0 $0 $1,109,560 PK012 3 Persimmon Drive Pedestrian Path Rehabilitation $195,000 $0 $0 $0 $0 $0 $0 $195,000 PK0321 Restrooms Replacement $1,000,000 $0 $475,000 $0 $0 $0 $0 $1,475,000 PK000 4 Sports Courts Resurfacing $0 $0 $600,000 $0 $500,000 $0 $1,000,000 $2,100,000 PK012 5 Sunday School Barn Flooring $0 $125,000 $260,000 $0 $0 $0 $0 $385,000 PK042 1 Wallis Ranch Community Park $11,760,000 $0 $0 $0 $0 $0 $0 $11,760,000 Total Summary of Requests $58,120,397 $2,516,985 $6,050,941 $2,928,654 $1,100,000 $5,150,000 $5,500,000 $81,366,977 Table of ContentsParks 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 63 783 Alamo Creek Park and Assessment District - Fence Replacement Overview Project Number PK0122 Description This project provides for the design and construction of replacement fencing at Alamo Creek Park and for replacement and repair of fencing along Alamo Creek within the Dougherty Road Landscape and Lighting District No. 1986-1. Most of the existing tubular steel fencing has reached the end of its service life and needs to be replaced or repaired. In addition to the park fencing, the existing decorative concrete masonry walls within the park, which include integrated tubular steel fence elements, will be evaluated, repaired as needed, and repainted.  The project will also include evaluation and selecting replacement or repair of the tubular steel fencing that is maintained by the Dougherty Road Landscape and Lighting District No. 1986-1. The subject fencing is located along Fall Creek Road, Wildwood Road, and Willow Creek Drive. Funding for this portion of the project is provided from funding reserves that were collected from District No. 1986-1.   Capital Cost Historical $850K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $850K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9300 - Land/Right-of-way $747,500 $0 $0 $0 $0 $0 $0 $747,500 9200 - Contract Services $53,751 $0 $0 $0 $0 $0 $0 $53,751 9100 - Salaries & Benefits $41,600 $0 $0 $0 $0 $0 $0 $41,600 9400 - Improvements $7,149 $0 $0 $0 $0 $0 $0 $7,149 Total $850,000 $0 $0 $0 $0 $0 $0 $850,000 Table of ContentsAlamo Creek Park and Assessment District - Fence Replacement 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 64 784 Funding Sources Historical $850K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $850K Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The project is currently in design. Construction is anticipated to begin in late 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $450,000 $0 $0 $0 $0 $0 $0 $450,000 2703 - Landscape District Dougherty 1986-1 $400,000 $0 $0 $0 $0 $0 $0 $400,000 Total $850,000 $0 $0 $0 $0 $0 $0 $850,000 Table of ContentsAlamo Creek Park and Assessment District - Fence Replacement 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 65 785 Don Biddle Community Park Overview Project Number PK0115 Description This project provides for the design and construction of a 30-acre community park in the Boulevard Development within the Dublin Crossing Specic Plan. The park is located between Dublin Boulevard, Scarlett Drive, Horizon Parkway, and Columbus Street and will be built by the Boulevard Developer. The project includes tennis courts, basketball courts, a picnic and barbeque area, a great lawn (multi-use lawn area), playgrounds, parent paddock, community garden, a specimen tree, upgraded playground equipment, and other amenities.  In accordance with the Dublin Crossing Development Agreement, the Developer is responsible for project costs up to $12,857,142. The City is responsible for reimbursing the Developer for project costs that exceed that amount. City funding will come from Public Facility Fee Funds. Capital Cost Historical $24.8M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $24 .8M Funding Sources Historical $24.8M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $24 .8M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $19,328,720 $0 $0 $0 $0 $0 $0 $19,328,720 9200 - Contract Services $2,932,161 $0 $0 $0 $0 $0 $0 $2,932,161 9500 - Miscellaneous $2,043,221 $0 $0 $0 $0 $0 $0 $2,043,221 9100 - Salaries & Benefits $519,903 $0 $0 $0 $0 $0 $0 $519,903 Total $24,824,005 $0 $0 $0 $0 $0 $0 $24,824,005 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9999 - Developer Built $12,857,142 $0 $0 $0 $0 $0 $0 $12,857,142 4100 - Public Facility Fees $9,866,863 $0 $0 $0 $0 $0 $0 $9,866,863 1101 - General Fund Designated Reserve $2,100,000 $0 $0 $0 $0 $0 $0 $2,100,000 Total $24,824,005 $0 $0 $0 $0 $0 $0 $24,824,005 Table of ContentsDon Biddle Community Park 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 66 786 Operational Costs FY2025 Budget $1.14M Total Budget (all years) $1.14M Project Total $1.14M Project Timeline ●01/9/2018 The conceptual plan was approved by the City Council on January 9, 2018. ●10/2/2018 On October 2, 2018, the City Council provided direction to use $600,000 of Community Benet Funds for the inclusion of a specimen tree and upgraded playground equipment in the park design.  ●09/24/2022 The park opened on September 24, 2022. ●07/1/2025 Work at the southwest limits of the park adjacent Scarlett Drive extension should be completed in 2026. Table of ContentsDon Biddle Community Park 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 67 787 Downtown Dublin Town Square Park Overview Project Number PK0221 Description This project provides for the planning of a new Town Square, in accordance with the main principles of the Downtown Dublin Preferred Vision, which was approved  by the City Council on November 5, 2019. The Town Square is a one-acre park and plaza that will serve as Downtown Dublin's gathering place, which may include a  market promenade, outdoor dining, and event space, and will be located one block north of Dublin Boulevard in the Dublin Place shopping center along the proposed  extension of Golden Gate Drive.  Possible future funding sources are development impact fees, community facilities district nancing, or other assessment district funding. Capital Cost Historical $107K FY2025 Budget $4.68K Total Budget (all years) $4 .68K Future $4.5M Project Total (to date) $4 .61M Funding Sources Historical $107K FY2025 Budget $4.68K Total Budget (all years) $4 .68K Future $4.5M Project Total (to date) $4 .61M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9300 - Land/Right-of-way $0 $0 $0 $0 $0 $0 $2,400,000 $2,400,000 9400 - Improvements $0 $0 $0 $0 $0 $0 $1,440,000 $1,440,000 9200 - Contract Services $75,000 $0 $0 $0 $0 $0 $550,000 $625,000 9100 - Salaries & Benefits $31,885 $4,680 $0 $0 $0 $0 $110,000 $146,565 Total $106,885 $4,680 $0 $0 $0 $0 $4,500,000 $4,611,565 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 4100 - Public Facility Fees $0 $0 $0 $0 $0 $0 $4,500,000 $4,500,000 1001 - General Fund $106,885 $4,680 $0 $0 $0 $0 $0 $111,565 Total $106,885 $4,680 $0 $0 $0 $0 $4,500,000 $4,611,565 Table of ContentsDowntown Dublin Town Square Park 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 68 788 Operational Costs FY2025 Budget $40K Total Budget (all years) $40K Project Total $40K Project Timeline ●07/1/2025 The project will be planned in conjunction with the review of the developer’s application. Table of ContentsDowntown Dublin Town Square Park 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 69 789 Dublin Sports Grounds Rehabilitation Overview Project Number PK0002 Description This project will provide for the design and construction to renovate the easterly ball elds at the Dublin Sports Grounds. The improvements may include dugout covers/shelter, fence repairs, backstop replacement, replacement of the core booths and storage at the elds. Additionally, the dugouts and bullpen openings will be recongured. The project will also include the replacement of the westerly restroom and the addition of concrete walkways. Capital Cost FY2025 Budget $0 Total Budget (all years) $3.65M Project Total $3.65M Funding Sources FY2025 Budget $0 Total Budget (all years) $3.65M Project Total $3.65M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $0 $0 $0 $575,040 $1,900,000 $0 $2,475,040 9200 - Contract Services $0 $0 $0 $125,040 $0 $790,000 $0 $915,040 9100 - Salaries & Benefits $0 $0 $0 $24,960 $24,960 $210,000 $0 $259,920 Total $0 $0 $0 $150,000 $600,000 $2,900,000 $0 $3,650,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $0 $0 $0 $150,000 $600,000 $2,900,000 $0 $3,650,000 Total $0 $0 $0 $150,000 $600,000 $2,900,000 $0 $3,650,000 Table of ContentsDublin Sports Grounds Rehabilitation 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 70 790 Project Timeline ●07/1/2025 This project is anticipated to begin in 2026. Table of ContentsDublin Sports Grounds Rehabilitation 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 71 791 Fallon Spor ts Park - Ar ticial Turf Field Replacement Overview Project Number PK0003 Description This project will provide for the design and construction to replace the four articial turf sports elds at Fallon Sports Park. The lifespan of articial turf sports elds can vary depending on factors such as the quality of the turf, the level of usage, maintenance practices, and environmental conditions. Depending upon continued use and maintenance, the articial turf is anticipated to need replacement in Fiscal Year 2028-29. Capital Cost FY2025 Budget $0 Total Budget (all years) $2.25M Project Total $2.25M Funding Sources FY2025 Budget $0 Total Budget (all years) $2.25M Project Total $2.25M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $0 $0 $0 $0 $1,550,000 $0 $1,550,000 9200 - Contract Services $0 $0 $0 $0 $0 $600,000 $0 $600,000 9100 - Salaries & Benefits $0 $0 $0 $0 $0 $100,000 $0 $100,000 Total $0 $0 $0 $0 $0 $2,250,000 $0 $2,250,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $0 $0 $0 $0 $0 $2,250,000 $0 $2,250,000 Total $0 $0 $0 $0 $0 $2,250,000 $0 $2,250,000 Table of ContentsFallon Sports Park - Artificial Turf Field Replacement 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 72 792 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 This project is anticipated to begin in 2028. Table of ContentsFallon Sports Park - Artificial Turf Field Replacement 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 73 793 Fallon Spor ts Park - Phase 3 Overview Project Number PK0119 Description Fallon Sports Park is a 60-acre community park bordered by Fallon Road, Central Parkway, Lockhart Street and Gleason Drive. Phases 1 and 2 of the park have been completed and Phase 3 represents the nal phase of park development. The Phase 3 project provides for the design and construction of the remaining 14 acres of Fallon Sports Park, referred to as the Upper Terrace. On December 17, 2019, City Council approved the concept design that includes a cricket eld, two ballelds, sand volleyball courts and multi-sport batting cages. In September 2022 the City Council authorized the use of construction contingency to install perimeter fencing/netting at the cricket eld. Capital Cost Historical $9.62M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $9.62M Funding Sources Historical $9.62M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $9.62M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $8,100,000 $0 $0 $0 $0 $0 $0 $8,100,000 9200 - Contract Services $1,268,000 $0 $0 $0 $0 $0 $0 $1,268,000 9100 - Salaries & Benefits $225,000 $0 $0 $0 $0 $0 $0 $225,000 9500 - Miscellaneous $30,000 $0 $0 $0 $0 $0 $0 $30,000 Total $9,623,000 $0 $0 $0 $0 $0 $0 $9,623,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 4100 - Public Facility Fees $9,523,000 $0 $0 $0 $0 $0 $0 $9,523,000 1101 - General Fund Designated Reserve $100,000 $0 $0 $0 $0 $0 $0 $100,000 Total $9,623,000 $0 $0 $0 $0 $0 $0 $9,623,000 Table of ContentsFallon Sports Park - Phase 3 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 74 794 Operational Costs FY2025 Budget $530K Total Budget (all years) $530K Project Total $530K Project Timeline ●10/22/2022 Construction was substantially complete in late summer 2022 and park opening ceremony was held in October 2022. ●07/1/2025 The project was completed in June 2024, and is currently in the closeout phase. Table of ContentsFallon Sports Park - Phase 3 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 75 795 Fallon Spor ts Park Baseball Field G Upgrades Overview Project Number PK0225 Description The project provides for the planning, design, and construction of an aluminum 60-foot high agpole at the southwest corner of the baseball diamond behind the First Base side bullpen to accommodate a 10-foot x 15-foot United States Flag and California State Flag, as well as a light to top of pole. Future improvements may include eld fence screening/padding with advertising, Public Address System, Wi-Fi system (to facilitate streaming games), bleachers/seating for 250-350 people, new scoreboard, at a new location, and Gate/Fence access control. Capital Cost FY2025 Budget $150K Total Budget (all years) $400K Project Total $400K Funding Sources FY2025 Budget $150K Total Budget (all years) $400K Project Total $400K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $92,500 $190,000 $0 $0 $0 $0 $282,500 9200 - Contract Services $0 $50,000 $50,000 $0 $0 $0 $0 $100,000 9100 - Salaries & Benefits $0 $5,000 $10,000 $0 $0 $0 $0 $15,000 9500 - Miscellaneous $0 $2,500 $0 $0 $0 $0 $0 $2,500 Total $0 $150,000 $250,000 $0 $0 $0 $0 $400,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $0 $150,000 $250,000 $0 $0 $0 $0 $400,000 Total $0 $150,000 $250,000 $0 $0 $0 $0 $400,000 Table of ContentsFallon Sports Park Baseball Field G Upgrades 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 76 796 Operational Costs FY2025 Budget $0 Total Budget (all years) $2.5K Project Total $2.5K Project Timeline ●02/4/2025 City Council directed Staff to begin work on the project at the February 4, 2025 meeting. ●07/1/2025 The agpole portion of the project is complete. The planning phase for seating/bleachers is anticipated to begin in FY 2025-26. Table of ContentsFallon Sports Park Baseball Field G Upgrades 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 77 797 Forest Park Overview Project Number PK0322 Description This project provides for the planning, design, and construction of a 2.0-acre neighborhood square in the Jordan Ranch Development. The neighborhood square will be designed in accordance with the Neighborhood Square Standards contained in the Parks and Recreation Master Plan. Capital Cost Historical $2.8M FY2025 Budget $740K Total Budget (all years) $740K Project Total (to date) $3.54M Funding Sources Historical $2.8M FY2025 Budget $740K Total Budget (all years) $740K Project Total (to date) $3.54M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $1,904,749 $715,000 $0 $0 $0 $0 $0 $2,619,749 9200 - Contract Services $493,940 $25,000 $0 $0 $0 $0 $0 $518,940 9500 - Miscellaneous $282,680 $0 $0 $0 $0 $0 $0 $282,680 9100 - Salaries & Benefits $117,578 $0 $0 $0 $0 $0 $0 $117,578 Total $2,798,947 $740,000 $0 $0 $0 $0 $0 $3,538,947 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 4100 - Public Facility Fees $2,798,947 $100,000 $0 $0 $0 $0 $0 $2,898,947 1001 - General Fund $0 $350,000 $0 $0 $0 $0 $0 $350,000 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) $0 $250,000 $0 $0 $0 $0 $0 $250,000 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $0 $40,000 $0 $0 $0 $0 $0 $40,000 Total $2,798,947 $740,000 $0 $0 $0 $0 $0 $3,538,947 Table of ContentsForest Park 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 78 798 Operational Costs FY2025 Budget $0 Total Budget (all years) $275K Project Total $275K Project Timeline ●07/1/2024 The planning phase began in Fiscal Year 2021-22 and the conceptual plan was approved by the City Council in December 2022. The project is currently in design and construction will start in 2024. Midyear appropriation of $390,000 approved by City Council on July 16, 2024. ●07/1/2025 The project is currently in construction and anticipated to be completed before the end of 2025. Table of ContentsForest Park 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 79 799 Iron Horse Nature Park and Open Space Overview Project Number PK0422 Description This project provides for the planning, design, and construction of 12.13 acres of a nature park and open space adjacent to the Iron Horse Regional Trail, from the Dublin/San Ramon city limit to the conuence of Alamo and South San Ramon Creeks, that may be developed in partnership with Zone 7 Water Agency. The park size could increase to over 20 acres of usable parkland when combined with adjacent Zone 7 Water Agency property. The park will be designed in accordance with the Iron Horse Nature Park and Open Space Master Plan, which was approved by the City Council on October 1, 2013. The City has already acquired 12.13 acres and the balance of the parkland would be accessible through an easement and operational agreement with Zone 7 Water Agency. The City will continue to pursue the acquisition of the Alameda County portion of the Iron Horse Regional Trail corridor to add to the City's portion of the parkland. The Phase I improvements will provide a trail connection to Stagecoach Park, the installation of a shade structure over a picnic area, as well as replacement benches and picnic tables. In addition to Public Facilities Fee, possible funding sources are additional statewide grants or federal grants for projects that provide non-motorized infrastructure and enhancements that promote new or alternate access to parks, waterways, outdoor recreational pursuits, and forested or other natural environments to encourage health-related active transportation and opportunities for residents and trail users to reconnect with nature, such as Active Transportation Program grants or Proposition 68. Capital Cost Historical $5.4M FY2025 Budget $1.5M Total Budget (all years) $6.77M Project Total (to date) $12.2M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $2,446,027 $1,248,800 $2,235,941 $2,778,654 $0 $0 $0 $8,709,422 9200 - Contract Services $2,381,226 $196,505 $0 $0 $0 $0 $0 $2,577,731 9500 - Miscellaneous $365,500 $0 $255,000 $0 $0 $0 $0 $620,500 9100 - Salaries & Benefits $210,247 $52,000 $0 $0 $0 $0 $0 $262,247 Total $5,403,000 $1,497,305 $2,490,941 $2,778,654 $0 $0 $0 $12,169,900 Table of ContentsIron Horse Nature Park and Open Space 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 80 800 Funding Sources Historical $5.4M FY2025 Budget $1.5M Total Budget (all years) $6.77M Project Total (to date) $12.2M Operational Costs FY2025 Budget $0 Total Budget (all years) $1.22M Project Total $1.22M Project Timeline ●07/1/2025 Planning and design for Phase 1 began in Fiscal Year 2021-22 and construction was awarded and work began in spring 2024. Phase 1 construction is anticipated to be completed in late 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 4100 - Public Facility Fees $3,056,000 $1,463,505 $2,490,941 $0 $0 $0 $0 $7,010,446 9998 - Unidentified $0 $0 $0 $2,778,654 $0 $0 $0 $2,778,654 2403 - State Park Grant $2,294,000 $0 $0 $0 $0 $0 $0 $2,294,000 1001 - General Fund $53,000 $33,800 $0 $0 $0 $0 $0 $86,800 Total $5,403,000 $1,497,305 $2,490,941 $2,778,654 $0 $0 $0 $12,169,900 Table of ContentsIron Horse Nature Park and Open Space 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 81 801 Kolb Park Renovation Overview Project Number PK0224 Description This project will provide for the planning, design, and construction to renovate the 4.86-acre Kolb Park.  The planning phase of the project will evaluate and prioritize the improvements, focusing on the replacement of aging infrastructure and amenities.  The improvements will be consistent with the Parks and Recreation Master Plan and may include the replacement of the play equipment, site furnishings, picnic areas, drinking fountains, tot lot fencing, parcourse equipment stations, signage, refresh the shade structure, relevel the existing paver and decomposed granite pathways, and refresh the landscaping. Staff will look for opportunities to incorporate Green Stormwater Infrastructure within the park as a part of the renovation. Capital Cost Historical $450K FY2025 Budget $0 Total Budget (all years) $1.98M Project Total (to date) $2.43M Funding Sources Historical $450K FY2025 Budget $0 Total Budget (all years) $1.98M Project Total (to date) $2.43M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $0 $1,825,000 $0 $0 $0 $0 $1,825,000 9200 - Contract Services $425,040 $0 $75,040 $0 $0 $0 $0 $500,080 9500 - Miscellaneous $0 $0 $50,000 $0 $0 $0 $0 $50,000 9100 - Salaries & Benefits $24,960 $0 $24,960 $0 $0 $0 $0 $49,920 Total $450,000 $0 $1,975,000 $0 $0 $0 $0 $2,425,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $450,000 $0 $1,975,000 $0 $0 $0 $0 $2,425,000 Total $450,000 $0 $1,975,000 $0 $0 $0 $0 $2,425,000 Table of ContentsKolb Park Renovation 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 82 802 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The planning phase of the project will evaluate and prioritize the improvements, focusing on the replacement of aging infrastructure and amenities. and will begin in 2025. Table of ContentsKolb Park Renovation 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 83 803 Parks Playground Replacement Overview Project Number PK0124 Description This project provides for the planning, design, and construction of the replacement of playground equipment at various parks. Based on the results of annual inspections and regular maintenance records, all City parks will be evaluated for the need to replace play equipment at the end of their useful life. The rst phase will be at Emerald Glen Park (Near Splash Pad Ages 5-12) and Ted Faireld Park (Ages 2-5 and 5-12). Capital Cost Historical $1.11M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $1.11M Funding Sources Historical $1.11M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $1.11M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $850,000 $0 $0 $0 $0 $0 $0 $850,000 9200 - Contract Services $120,000 $0 $0 $0 $0 $0 $0 $120,000 9100 - Salaries & Benefits $118,560 $0 $0 $0 $0 $0 $0 $118,560 9500 - Miscellaneous $21,000 $0 $0 $0 $0 $0 $0 $21,000 Total $1,109,560 $0 $0 $0 $0 $0 $0 $1,109,560 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $1,109,560 $0 $0 $0 $0 $0 $0 $1,109,560 Total $1,109,560 $0 $0 $0 $0 $0 $0 $1,109,560 Table of ContentsParks Playground Replacement 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 84 804 Project Timeline ●07/1/2025 The planning will begin in 2025. Table of ContentsParks Playground Replacement 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 85 805 Persimmon Drive Pedestrian Path Rehabilitation Overview Project Number PK0123 Description This project will provide for the removal and replacement of approximately 1,250 linear feet of asphalt pathway along Persimmon Drive between Gleason Drive and Central Parkway. The asphalt concrete surface has experienced distress due to soil expansion, the encroachment of tree roots, and some slope creep along the adjacent Tassajara Creek bank. Capital Cost Historical $195K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $195K Funding Sources Historical $195K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $195K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $150,000 $0 $0 $0 $0 $0 $0 $150,000 9200 - Contract Services $29,920 $0 $0 $0 $0 $0 $0 $29,920 9100 - Salaries & Benefits $15,080 $0 $0 $0 $0 $0 $0 $15,080 Total $195,000 $0 $0 $0 $0 $0 $0 $195,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2704 - Landscape District Santa Rita 1997-1 $195,000 $0 $0 $0 $0 $0 $0 $195,000 Total $195,000 $0 $0 $0 $0 $0 $0 $195,000 Table of ContentsPersimmon Drive Pedestrian Path Rehabilitation 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 86 806 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2024 Design began in spring 2023 in conjunction with the Annual Street Resurfacing Project. The project is currently in design and construction is anticipated to begin in 2024. ●07/1/2025 Construction of the asphalt pathway resurfacing along Persimmon Drive was completed in 2024. The project is currently in the closeout phase and is anticipated to be completed in 2025. Table of ContentsPersimmon Drive Pedestrian Path Rehabilitation 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 87 807 Restrooms Replacement Overview Project Number PK0321 Description This project provides for the planning, design, and construction to replace the existing restrooms at Kolb Park, Alamo Creek Park and Mape Memorial Park. To bring the restrooms up to current accessibility standards and codes, the existing restroom buildings will be demolished and replaced with pre-engineered restroom buildings.  Capital Cost Historical $1M FY2025 Budget $0 Total Budget (all years) $475K Project Total (to date) $1.48M Funding Sources Historical $1M FY2025 Budget $0 Total Budget (all years) $475K Project Total (to date) $1.48M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $807,000 $0 $400,000 $0 $0 $0 $0 $1,207,000 9200 - Contract Services $152,000 $0 $57,000 $0 $0 $0 $0 $209,000 9100 - Salaries & Benefits $33,380 $0 $16,620 $0 $0 $0 $0 $50,000 9500 - Miscellaneous $7,620 $0 $1,380 $0 $0 $0 $0 $9,000 Total $1,000,000 $0 $475,000 $0 $0 $0 $0 $1,475,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $1,000,000 $0 $475,000 $0 $0 $0 $0 $1,475,000 Total $1,000,000 $0 $475,000 $0 $0 $0 $0 $1,475,000 Table of ContentsRestrooms Replacement 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 88 808 Project Timeline ●07/1/2025 The project is currently in design and construction is anticipated to begin in 2026. Table of ContentsRestrooms Replacement 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 89 809 Spor ts Courts Resurfacing Overview Project Number PK0004 Description This project will provide for the design and construction to resurface the tennis and basketball courts. Courts generally have a seven-to-ten-year useful life prior to needing to be resurfaced. The sports courts at Emerald Glen Park would be the rst sites to be resurfaced followed by those at Fallon Sports Park. Capital Cost FY2025 Budget $0 Total Budget (all years) $1.1M Future $1M Project Total $2.1M Funding Sources FY2025 Budget $0 Total Budget (all years) $1.1M Future $1M Project Total $2.1M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $0 $400,000 $0 $330,000 $0 $655,000 $1,385,000 9200 - Contract Services $0 $0 $160,000 $0 $135,000 $0 $275,000 $570,000 9100 - Salaries & Benefits $0 $0 $40,000 $0 $35,000 $0 $70,000 $145,000 Total $0 $0 $600,000 $0 $500,000 $0 $1,000,000 $2,100,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 6205 - Internal Service Fund - Facilities Replacement $0 $0 $600,000 $0 $500,000 $0 $1,000,000 $2,100,000 Total $0 $0 $600,000 $0 $500,000 $0 $1,000,000 $2,100,000 Table of ContentsSports Courts Resurfacing 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 90 810 Project Timeline ●07/1/2025 The project will start design in 2025. Table of ContentsSports Courts Resurfacing 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 91 811 Sunday School Barn Flooring Overview Project Number PK0125 Description This project provides for the design and construction to renovate the existing wood oor inside the Sunday School Barn at Heritage Park. The original wood oors are not adequate for the types and frequency of use that the building is experiencing. The project is intended to preserve the look and historic fabric of the original wood that is believed to be from the late 1800’s while ensuring the structural integrity and nish of the oor are adequate for the current and planned uses of the barn. Capital Cost FY2025 Budget $125K Total Budget (all years) $385K Project Total $385K Funding Sources FY2025 Budget $125K Total Budget (all years) $385K Project Total $385K Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $0 $200,000 $0 $0 $0 $0 $200,000 9200 - Contract Services $0 $100,040 $25,040 $0 $0 $0 $0 $125,080 9100 - Salaries & Benefits $0 $24,960 $24,960 $0 $0 $0 $0 $49,920 9500 - Miscellaneous $0 $0 $10,000 $0 $0 $0 $0 $10,000 Total $0 $125,000 $260,000 $0 $0 $0 $0 $385,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $0 $125,000 $260,000 $0 $0 $0 $0 $385,000 Total $0 $125,000 $260,000 $0 $0 $0 $0 $385,000 Table of ContentsSunday School Barn Flooring 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 92 812 Project Timeline ●07/1/2025 The design will start design in FY 2025-26. Table of ContentsSunday School Barn Flooring 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 93 813 Wallis Ranch Community Park Overview Project Number PK0421 Description The Wallis Ranch Community Park consists of three separate parcels totaling 8.85 acres in the Wallis Ranch Development. The project will provide for the design and construction of a community park and will be designed to the Community Park Standards contained in the Parks and Recreation Master Plan. Park amenities include play areas, picnic facilities, turf area, lighted tennis, pickle ball, and basketball facilities, natural area, restrooms, pathways, lighting, dog park, and irrigation and landscaping. Capital Cost Historical $11.8M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $11.8M Funding Sources Historical $11.8M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $11.8M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $9,224,172 $0 $0 $0 $0 $0 $0 $9,224,172 9200 - Contract Services $1,356,421 $0 $0 $0 $0 $0 $0 $1,356,421 9500 - Miscellaneous $987,205 $0 $0 $0 $0 $0 $0 $987,205 9100 - Salaries & Benefits $192,202 $0 $0 $0 $0 $0 $0 $192,202 Total $11,760,000 $0 $0 $0 $0 $0 $0 $11,760,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 4100 - Public Facility Fees $11,760,000 $0 $0 $0 $0 $0 $0 $11,760,000 1001 - General Fund $0 $0 $0 $0 $0 $0 $0 $0 Total $11,760,000 $0 $0 $0 $0 $0 $0 $11,760,000 Table of ContentsWallis Ranch Community Park 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 94 814 Operational Costs FY2025 Budget $0 Total Budget (all years) $1.05M Project Total $1.05M Project Timeline ●07/1/2025 Design started in spring 2021 and construction began in October 2023. The project is currently under construction and is anticipated to open in 2025. Table of ContentsWallis Ranch Community Park 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 95 815 Public Art FY25 - FY29 Public Art Projects (including Historical, Future) Camp Parks Sign $780,450 31.46% Downtown Dublin $1,500,000 60.47% Outdoor Murals $200,000 8.06% $1M$1M$1M $780K$780K $780K $300K$300K $300K $250K$250K $250K 000 000 000 Historical 2025 2026 2027 2028 2029 Future 0 $500K $1,000K $1,500K Summary of Requests Project No. / Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total PA0121 Camp Parks Sign $500,450 $280,000 $0 $0 $0 $0 $0 $780,450 PA0123 Downtown Dublin $650,000 $300,000 $300,000 $250,000 $0 $0 $0 $1,500,000 PA0125 Outdoor Murals $0 $200,000 $0 $0 $0 $0 $0 $200,000 Total Summary of Requests $1,150,450 $780,000 $300,000 $250,000 $0 $0 $0 $2,480,450 Table of ContentsPublic Art 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 96 816 Camp Parks Sign Overview Project Number PA0121 Description This project includes the restoration and relocation of the historic Camp Parks entrance sign from its current location at approximately 201 Dougherty Road to the new entrance at Camp Parks Boulevard and Dougherty Road. The original sign was designed by artist/architect Bruce Goff in the 1940s and is eligible for the National Register. Rehabilitation will be in accordance with standards and guidelines per the U.S. Department of the Interior National Park Service.  Capital Cost Historical $500K FY2025 Budget $280K Total Budget (all years) $280K Project Total (to date) $780K Funding Sources Historical $500K FY2025 Budget $280K Total Budget (all years) $280K Project Total (to date) $780K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $300,000 $280,000 $0 $0 $0 $0 $0 $580,000 9200 - Contract Services - Engineering/Architecture $165,000 $0 $0 $0 $0 $0 $0 $165,000 9100 - Salaries & Benefits - Planning $25,450 $0 $0 $0 $0 $0 $0 $25,450 9500 - Miscellaneous $10,000 $0 $0 $0 $0 $0 $0 $10,000 Total $500,450 $280,000 $0 $0 $0 $0 $0 $780,450 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2801 - Public Art Fund $500,450 $280,000 $0 $0 $0 $0 $0 $780,450 Total $500,450 $280,000 $0 $0 $0 $0 $0 $780,450 Table of ContentsCamp Parks Sign 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 97 817 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 The design process began in winter 2022. The project is currently in construction and is anticipated to be completed by the end of 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total General Maintenance $0 $0 $0 $0 $0 $0 $0 $0 Total $0 $0 $0 $0 $0 $0 $0 $0 Table of ContentsCamp Parks Sign 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 98 818 Downtown Dublin Overview Project Number PA0123 Description This project provides for public art commissions in Downtown Dublin. The project includes a comprehensive review of existing Downtown Dublin planning documents and the Public Art Master Plan, as well as the development of a guide for public art in the Downtown. Capital Cost Historical $650K FY2025 Budget $300K Total Budget (all years) $850K Project Total (to date) $1.5M Funding Sources Historical $650K FY2025 Budget $300K Total Budget (all years) $850K Project Total (to date) $1.5M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $300,000 $300,000 $300,000 $250,000 $0 $0 $0 $1,150,000 9500 - Miscellaneous $250,000 $0 $0 $0 $0 $0 $0 $250,000 9200 - Contract Services - Engineering/Architecture $75,040 $0 $0 $0 $0 $0 $0 $75,040 9100 - Salaries & Benefits - Planning $24,960 $0 $0 $0 $0 $0 $0 $24,960 Total $650,000 $300,000 $300,000 $250,000 $0 $0 $0 $1,500,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2801 - Public Art Fund $650,000 $300,000 $300,000 $250,000 $0 $0 $0 $1,500,000 Total $650,000 $300,000 $300,000 $250,000 $0 $0 $0 $1,500,000 Table of ContentsDowntown Dublin 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 99 819 Operational Costs FY2025 Budget $0 Total Budget (all years) $5K Project Total $5K Project Timeline ●07/1/2025 The planning phase began in 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total General Maintenance $0 $0 $0 $5,000 $0 $0 $0 $5,000 Total $0 $0 $0 $5,000 $0 $0 $0 $5,000 Table of ContentsDowntown Dublin 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 100 820 Outdoor Murals Overview Project Number PA0125 Description This project will include painting of Public Art Murals at sites including, but not limited to generator enclosures at Civic Center, Library, Don Biddle Community Park and the Dublin Arts Center, as well as, utility enclosures, and others. The exact locations are not yet determined, and any project sites would be subject to review by the Heritage and Cultural Arts Commission and approval by the City Council.  Capital Cost FY2025 Budget $200K Total Budget (all years) $200K Project Total $200K Funding Sources FY2025 Budget $200K Total Budget (all years) $200K Project Total $200K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Repairs/Improvements $0 $150,000 $0 $0 $0 $0 $0 $150,000 9500 - Miscellaneous $0 $35,000 $0 $0 $0 $0 $0 $35,000 9100 - Salaries & Benefits - Planning $0 $15,000 $0 $0 $0 $0 $0 $15,000 Total $0 $200,000 $0 $0 $0 $0 $0 $200,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2801 - Public Art Fund $0 $200,000 $0 $0 $0 $0 $0 $200,000 Total $0 $200,000 $0 $0 $0 $0 $0 $200,000 Table of ContentsOutdoor Murals 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 101 821 Operational Costs FY2025 Budget $1K Total Budget (all years) $1K Project Total $1K Project Timeline ●07/1/2025 This project is currently in the planning stages with a future mural on the generator enclosure adjacent to the Dublin Public Library. Artist and artwork selection is anticipated to be completed by the end of 2025 with mural installation in 2026. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total General Maintenance $0 $1,000 $0 $0 $0 $0 $0 $1,000 Total $0 $1,000 $0 $0 $0 $0 $0 $1,000 Table of ContentsOutdoor Murals 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 102 822 Streets FY25 - FY29 Streets Projects (including Historical, Future) Amador Plaza Road Bicycle and Pedestrian Improvements $1,413,649 0.50% Annual Street Resurfacing $38,133,862 13.39% Citywide Bicycle and Pedestrian Improvements $11,986,045 4.21% Citywide Signal Communications Upgrade $6,939,427 2.44% Downtown Dublin Street Grid Network $21,428,020 7.53% Dublin Boulevard Extension - Fallon Road to North Canyons Parkway $126,414,018 44.40% Dublin Ranch Streetlight Improvements $276,741 0.10% Golden Gate Drive Intersection Improvements - Dublin Blvd and St. Patrick Way $4,451,640 1.56% Green Stormwater Infrastructure $4,159,063 1.46% Iron Horse Trail Bridge at Dublin Boulevard $14,054,439 4.94% San Ramon Road Trail Lighting $173,461 0.06% Tassajara Road Improvements - North Dublin Ranch Drive to Quarry Lane School $15,000,000 5.27% Tassajara Road Realignment and Widening - Fallon Road to North City Limit $12,777,416 4.49% Trafc Signal and Roadway Safety Improvements $170,000 0.06% Trafc Signal Re-Lamping $647,080 0.23% Village Parkway Reconstruction $26,700,000 9.38% $101M$101M$101M $24M$24M$24M $20M$20M $20M $13M$13M $13M $16M$16M $16M $5M$5M$5M $105M$105M $105M Historical 2025 2026 2027 2028 2029 Future 0 $50M $100M $150M Table of ContentsStreets 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 103 823 Summary of Requests Project No. / Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total ST081 5 Amador Plaza Road Bicycle and Pedestrian Improvement s $1,413,649 $0 $0 $0 $0 $0 $0 $1,413,649 ST0117 Annual Street Resurfacing $15,530,538 $4,603,324 $4,500,000 $4,500,000 $4,500,000 $4,500,000 $0 $38,133,862 ST051 7 Citywide Bicycle and Pedestrian Improvement s $4,655,372 $2,474,673 $2,606,000 $750,000 $750,000 $750,000 $0 $11,986,045 ST071 3 Citywide Signal Communicati ons Upgrade $4,260,387 $825,040 $1,854,000 $0 $0 $0 $0 $6,939,427 ST022 1 Downtown Dublin Street Grid Network $219,030 $8,990 $0 $0 $0 $0 $21,200,000 $21,428,020 ST021 6 Dublin Boulevard Extension - Fallon Road to North Canyons Parkway $30,741,712 $11,450,000 $0 $0 $0 $0 $84,222,306 $126,414,018 ST041 7 Dublin Ranch Streetlight Improvement s $66,741 $42,000 $42,000 $42,000 $42,000 $42,000 $0 $276,741 ST042 3 Golden Gate Drive Intersection Improvement s - Dublin Blvd and St. Patrick Way $135,320 $816,320 $0 $3,500,000 $0 $0 $0 $4,451,640 ST0121 Green Stormwater Infrastructure $3,289,063 $420,000 $0 $450,000 $0 $0 $0 $4,159,063 ST0118 Iron Horse Trail Bridge at Dublin Boulevard $14,004,439 $50,000 $0 $0 $0 $0 $0 $14,054,439 ST051 4 San Ramon Road Trail Lighting $173,461 $0 $0 $0 $0 $0 $0 $173,461 ST0119 Tassajara Road Improvement s - North Dublin Ranch Drive to Quarry Lane School $13,500,000 $1,500,000 $0 $0 $0 $0 $0 $15,000,000 Table of ContentsStreets 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 104 824 Project No. / Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total ST0116 Tassajara Road Realignment and Widening - Fallon Road to North City Limit $11,777,416 $1,000,000 $0 $0 $0 $0 $0 $12,777,416 ST012 3 Traffic Signal and Roadway Safety Improvement s $170,000 $0 $0 $0 $0 $0 $0 $170,000 ST022 3 Traffic Signal Re-Lamping $512,080 $0 $135,000 $0 $0 $0 $0 $647,080 ST032 3 Village Parkway Reconstructio n $550,000 $1,050,000 $11,150,000 $3,300,000 $10,650,000 $0 $0 $26,700,000 Total Summary of Requests $100,999,208 $24,240,347 $20,287,000 $12,542,000 $15,942,000 $5,292,000 $105,422,306 $284,724,861 Table of ContentsStreets 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 105 825 Amador Plaza Road Bicycle and Pedestrian Improvements Overview Project Number ST0815 Description This two-phase project provides for the design and construction of pedestrian, bicycle, and vehicular improvements along Amador Plaza Road between Dublin Boulevard and Amador Valley Boulevard. The rst phase included the installation of two mid-block crosswalks with pedestrian warning lights and construction of a raised concrete median at the southern Safeway/Dublin Place driveway. The second phase will include construction of an exclusive southbound right turn lane on Amador Plaza Road at Dublin Boulevard.  Capital Cost Historical $1.41M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $1.41M Funding Sources Historical $1.41M FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $1.41M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $1,035,862 $0 $0 $0 $0 $0 $0 $1,035,862 9200 - Contract Services $228,371 $0 $0 $0 $0 $0 $0 $228,371 9300 - Land/Right-of-way $126,000 $0 $0 $0 $0 $0 $0 $126,000 9100 - Salaries & Benefits $19,416 $0 $0 $0 $0 $0 $0 $19,416 9500 - Miscellaneous $4,000 $0 $0 $0 $0 $0 $0 $4,000 Total $1,413,649 $0 $0 $0 $0 $0 $0 $1,413,649 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 4304 - Western Dublin Transportation Impact Fee $1,413,649 $0 $0 $0 $0 $0 $0 $1,413,649 Total $1,413,649 $0 $0 $0 $0 $0 $0 $1,413,649 Table of ContentsAmador Plaza Road Bicycle and Pedestrian Improvements 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 106 826 Operational Costs FY2025 Budget $0 Total Budget (all years) $5K Project Total $5K Project Timeline ●12/30/2016 The City Council accepted the Phase 1 improvement in December 2016. ●06/15/2018 Phase 2 design began in mid-2018 and construction will occur following acquisition of the right-of-way for these improvements at the former Coco’s site. This project is currently on hold, pending acquisition of the right-of-way for these improvements. Table of ContentsAmador Plaza Road Bicycle and Pedestrian Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 107 827 Annual Street Resurfacing Overview Project Number ST0117 Description This project provides for the design and construction of a variety of pavement resurfacing treatments, from slurry seal to major rehabilitation and reconstruction of streets and resurfacing of bridge decks. The project also includes installation of new or upgrades of existing ADA curb ramps on roads that are reconstructed or receive an asphalt concrete overlay. Streets are selected for improvements based on the City’s Pavement Management System to optimize the pavement condition in relation to the available budget. The City owns and maintains approximately 148 centerline miles of streets.  The Metropolitan Transportation Commission groups Pavement Condition Index (PCI) ratings into the following categories: 80-100 Very Good-Excellent, 70-79 Good, 60-69 Fair, 50-59 At Risk, 25-49 Poor, and 0-24 Failed. The City of Dublin is rated very good with a three-year moving average PCI of 79. Capital Cost Historical $15.5M FY2025 Budget $4.6M Total Budget (all years) $22.6M Project Total (to date) $38.1M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $12,737,648 $3,653,324 $3,550,000 $3,550,000 $3,550,000 $3,550,000 $0 $30,590,972 9200 - Contract Services $2,509,344 $775,000 $775,000 $775,000 $775,000 $775,000 $0 $6,384,344 9100 - Salaries & Benefits $227,235 $167,500 $167,500 $167,500 $167,500 $167,500 $0 $1,064,735 9500 - Miscellaneous $56,311 $7,500 $7,500 $7,500 $7,500 $7,500 $0 $93,811 Total $15,530,538 $4,603,324 $4,500,000 $4,500,000 $4,500,000 $4,500,000 $0 $38,133,862 Table of ContentsAnnual Street Resurfacing 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 108 828 Funding Sources Historical $15.5M FY2025 Budget $4.6M Total Budget (all years) $22.6M Project Total (to date) $38.1M Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●04/1/2025 The City was awarded grant funding from the Department of Resources Recycling and Recovery (CalRecycle) Rubberized Pavement Grant Program in the amount of $103,324 and will be used for a rubberized cape seal treatment that will be constructed in 2026. ●07/1/2025 Construction of the 2024 Overlay, and 2024 Cape Seal projects are complete. Construction began in May 2025 for the 2025 Slurry Seal project. Design is currently underway for the 2026 Street Resurfacing Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2220 - Road Maint. & Rehab Account (RMRA) $4,263,599 $2,350,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $0 $14,613,599 1001 - General Fund $467,999 $1,250,000 $2,086,900 $1,750,000 $1,850,000 $1,850,000 $0 $9,254,899 2201 - State Gas Tax $5,289,941 $700,000 $413,100 $750,000 $650,000 $650,000 $0 $8,453,041 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $2,831,020 $200,000 $0 $0 $0 $0 $0 $3,031,020 2204 - Measure B Sales Tax - Local Streets Fund (Alameda CTC) $1,784,999 $0 $0 $0 $0 $0 $0 $1,784,999 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) $304,500 $0 $0 $0 $0 $0 $0 $304,500 2205 - Measure B Sales Tax - Bike & Ped. Fund (Alameda CTC) $300,000 $0 $0 $0 $0 $0 $0 $300,000 2304 - Local Recycling Programs $160,000 $0 $0 $0 $0 $0 $0 $160,000 9997 - Other $0 $103,324 $0 $0 $0 $0 $0 $103,324 2216 - Measure B Grants $82,500 $0 $0 $0 $0 $0 $0 $82,500 4309 - Mitigation Contributions $45,980 $0 $0 $0 $0 $0 $0 $45,980 Total $15,530,538 $4,603,324 $4,500,000 $4,500,000 $4,500,000 $4,500,000 $0 $38,133,862 Table of ContentsAnnual Street Resurfacing 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 109 829 project and the preliminary engineering began for the 2027 Street Resurfacing project. Improvements are typically constructed each year between spring and fall. Table of ContentsAnnual Street Resurfacing 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 110 830 Citywide Bicycle and Pedestrian Improvements Overview Project Number ST0517 Description This project includes planning, design, and construction of improvements to various pedestrian and bicycle facilities throughout the City, including pedestrian/bicycle bridges and annual sidewalk repair. This project includes design and construction of improvements recommended in the updated Bicycle and Pedestrian Plan, which was adopted by the City Council on January 10, 2023, as well as the Safe Routes to School improvements. The project also includes an update to the Americans with Disabilities Act (ADA) Transition Plan and implementation of Public Right-of-way Accessibility Guidelines (PROWAG). The plan update will include a review of City buildings, parks, and rights-of-way. Capital Cost Historical $4.66M FY2025 Budget $2.47M Total Budget (all years) $7.33M Project Total (to date) $12M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $3,173,298 $1,861,445 $2,381,000 $525,000 $525,000 $525,000 $0 $8,990,743 9200 - Contract Services $1,314,668 $555,000 $200,000 $200,000 $200,000 $200,000 $0 $2,669,668 9100 - Salaries & Benefits $127,372 $50,728 $20,000 $20,000 $20,000 $20,000 $0 $258,100 9500 - Miscellaneous $40,034 $7,500 $5,000 $5,000 $5,000 $5,000 $0 $67,534 Total $4,655,372 $2,474,673 $2,606,000 $750,000 $750,000 $750,000 $0 $11,986,045 Table of ContentsCitywide Bicycle and Pedestrian Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 111 831 Funding Sources Historical $4.66M FY2025 Budget $2.47M Total Budget (all years) $7.33M Project Total (to date) $12M Operational Costs FY2025 Budget $12K Total Budget (all years) $12K Project Total $12K Project Timeline ●01/10/2023 Adopted updated Bicycle and Pedestrian Plan. ●07/1/2024 In July 2024, the City was awarded $400,000 in funding from Alameda County Health Services Department through the Enhancing Vision 2026 (EV2026) Fund and will be used for the Regional Street Mid-block Crossing project. ●09/25/2024 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $1,471,600 $630,000 $250,000 $250,000 $250,000 $250,000 $0 $3,101,600 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) $601,872 $698,228 $250,000 $250,000 $250,000 $250,000 $0 $2,300,100 2220 - Road Maint. & Rehab Account (RMRA) $0 $355,000 $250,000 $250,000 $250,000 $250,000 $0 $1,355,000 2217 - Measure BB Grants $135,000 $0 $1,053,000 $0 $0 $0 $0 $1,188,000 1001 - General Fund $858,000 $105,000 $0 $0 $0 $0 $0 $963,000 2924 - VRF (ACTC) Grants $0 $0 $803,000 $0 $0 $0 $0 $803,000 2212 - Vehicle Registration Fee (Alameda CTC) $726,000 $0 $0 $0 $0 $0 $0 $726,000 2204 - Measure B Sales Tax - Local Streets Fund (Alameda CTC) $510,000 $0 $0 $0 $0 $0 $0 $510,000 2203 - Transportation Development Act $210,000 $286,445 $0 $0 $0 $0 $0 $496,445 2923 - Alameda County Grant $0 $400,000 $0 $0 $0 $0 $0 $400,000 2205 - Measure B Sales Tax - Bike & Ped. Fund (Alameda CTC) $142,900 $0 $0 $0 $0 $0 $0 $142,900 Total $4,655,372 $2,474,673 $2,606,000 $750,000 $750,000 $750,000 $0 $11,986,045 Table of ContentsCitywide Bicycle and Pedestrian Improvements 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 112 832 On September 25, 2024, Staff was notied that the City was awarded $286,445 in Transportation Development Act (TDA) funding after approval by the Metropolitan Transportation Commission (MTC) in March 2025, which will be used for pedestrian and trail improvements along Amador Valley Boulevard and at the Iron Horse Regional Trail crossing. ●05/22/2025 On May 22, 2025 Alameda CTC awarded grant funding in the amount of $1,053,000 in Measure BB funds and $803,000 in VRF funds for San Ramon Road and Amador Valley Boulevard intersection improvements, which will be allocated in Fiscal Year 2025-26. ●07/1/2025 The Safe Routes to School improvements at the intersections of Central Parkway at Aspen Street and Hibernia Drive, Grafton Street at Antone Way, and Amador Valley Boulevard at Burton Street are anticipated to be completed late 2025. The Downtown Dublin pedestrian crossing improvements on Regional Street is anticipated to begin construction in summer 2025. The ADA Transition Plan update, funded by the General Fund, is anticipated to be completed in 2026. Table of ContentsCitywide Bicycle and Pedestrian Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 113 833 Citywide Signal Communications Upgrade Overview Project Number ST0713 Description This project provides for the continued upgrades of the trafc signal communications system and includes the replacement of signal controllers, conict monitors, and battery backup units, as well as managing ongoing signal operations of coordinated corridors. In Fiscal Years 2019-20 and 2020-21, the project further expanded the trafc communications network, connecting trafc signals on Dublin Boulevard, San Ramon Road, Fallon Road and Tassajara Road. The project will provide for the installation of new conduits, removal of the existing copper communication cables, and installation of new ber optic cables on Dublin Boulevard. The project will also expand the adaptive trafc signal system along key corridors and will connect existing and new public safety infrastructure, such as situational awareness cameras and automated license plate recognition cameras, to the high-speed ber optic communications system. Capital Cost Historical $4.26M FY2025 Budget $825K Total Budget (all years) $2.68M Project Total (to date) $6.94M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $2,897,725 $540,000 $1,854,000 $0 $0 $0 $0 $5,291,725 9200 - Contract Services $1,220,200 $225,000 $0 $0 $0 $0 $0 $1,445,200 9100 - Salaries & Benefits $132,442 $55,040 $0 $0 $0 $0 $0 $187,482 9500 - Miscellaneous $4,900 $5,000 $0 $0 $0 $0 $0 $9,900 9600 - Equipment $5,120 $0 $0 $0 $0 $0 $0 $5,120 Total $4,260,387 $825,040 $1,854,000 $0 $0 $0 $0 $6,939,427 Table of ContentsCitywide Signal Communications Upgrade 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 114 834 Funding Sources Historical $4.26M FY2025 Budget $825K Total Budget (all years) $2.68M Project Total (to date) $6.94M Operational Costs FY2025 Budget $10K Total Budget (all years) $10K Project Total $10K Project Timeline ●06/30/2020 Updated Travel Demand Model to provide trafc ow projections on arterial and collector roadways, analyzed future land use and transportation network changes. ●04/30/2021 The update to the City's Travel Demand Forecasting Model to provide trafc ow projections on the arterial and collector roadways, as well as analyze future land use development proposals and transportation network changes is complete. The City Council adopted a Resolution establishing CEQA transportation thresholds of signicance for Vehicle Miles Traveled (VMT). Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2212 - Vehicle Registration Fee (Alameda CTC) $752,356 $35,040 $1,854,000 $0 $0 $0 $0 $2,641,396 1101 - General Fund Designated Reserve $1,420,149 $0 $0 $0 $0 $0 $0 $1,420,149 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $400,000 $750,000 $0 $0 $0 $0 $0 $1,150,000 2220 - Road Maint. & Rehab Account (RMRA) $654,320 $40,000 $0 $0 $0 $0 $0 $694,320 2204 - Measure B Sales Tax - Local Streets Fund (Alameda CTC) $248,640 $0 $0 $0 $0 $0 $0 $248,640 4300 - Eastern Dublin Transportation Impact Fee $200,000 $0 $0 $0 $0 $0 $0 $200,000 4304 - Western Dublin Transportation Impact Fee $199,000 $0 $0 $0 $0 $0 $0 $199,000 6305 - Internal Service Fund - Equipment Replacement $122,300 $0 $0 $0 $0 $0 $0 $122,300 2201 - State Gas Tax $104,000 $0 $0 $0 $0 $0 $0 $104,000 1001 - General Fund $79,851 $0 $0 $0 $0 $0 $0 $79,851 2207 - Transportation for Clean Air $79,771 $0 $0 $0 $0 $0 $0 $79,771 Total $4,260,387 $825,040 $1,854,000 $0 $0 $0 $0 $6,939,427 Table of ContentsCitywide Signal Communications Upgrade 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 115 835 ●06/30/2021 In FY 2019-20 and 2020-21, expanded trafc communications network, connected trafc signals on Dublin Boulevard, San Ramon Road, Fallon Road, Tassajara Road. ●07/1/2025 The installation of a conduit pathway between Civic Center and San Ramon Road to accommodate the future ber optic upgrade to city infrastructure is complete. On May 22, 2025, Alameda CTC awarded funding of $1,854,000 in VRF grant funding for the ber optic cable installation on Dublin Boulevard. Design will begin in FY 2025-26. This project is being completed over multiple years and phases. The installation of ber optic cables on Dublin Boulevard between San Ramon Road and Tassajara Road is currently in design, with construction anticipated to begin in summer 2026. Table of ContentsCitywide Signal Communications Upgrade 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 116 836 Downtown Dublin Street Grid Network Overview Project Number ST0221 Description This project provides for the planning of a new Street Grid Network, in accordance with the main principles of the Downtown Dublin Preferred Vision, which was approved by the City Council on November 5, 2019. The Street Grid Network will introduce new streets that will break down the large block format into smaller, walkable-sized blocks between 350 to 450 feet per side. The proposed extension of Golden Gate Drive north from Dublin Boulevard up to Amador Valley Boulevard will become a new main street with the classic Downtown street grid network within street rights-of-way varying between 60 and 90 feet wide. Street infrastructure may include storm drainage, sewer, water, recycled water, communications, gas, and electric utilities, as well as landscaping and irrigation. Street rights-of-way are anticipated to be dedicated by developers. Potential other future funding sources are development impact fees, community facilities district nancing, or other assessment district funding. Capital Cost Historical $219K FY2025 Budget $8.99K Total Budget (all years) $8.99K Future $21.2M Project Total (to date) $21.4M Funding Sources Historical $219K FY2025 Budget $8.99K Total Budget (all years) $8.99K Future $21.2M Project Total (to date) $21.4M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $0 $0 $0 $0 $0 $20,000,000 $20,000,000 9200 - Contract Services $150,000 $0 $0 $0 $0 $0 $1,000,000 $1,150,000 9100 - Salaries & Benefits $69,030 $8,990 $0 $0 $0 $0 $200,000 $278,020 Total $219,030 $8,990 $0 $0 $0 $0 $21,200,000 $21,428,020 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9998 - Unidentified $0 $0 $0 $0 $0 $0 $21,200,000 $21,200,000 1001 - General Fund $219,030 $8,990 $0 $0 $0 $0 $0 $228,020 Total $219,030 $8,990 $0 $0 $0 $0 $21,200,000 $21,428,020 Table of ContentsDowntown Dublin Street Grid Network 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 117 837 Operational Costs FY2025 Budget $15K Total Budget (all years) $15K Project Total $15K Project Timeline ●11/5/2019 Downtown Dublin Preferred Vision approved. ●01/1/2020 The planning phase began in 2020 with the update of the existing City Travel Demand Forecasting Model to provide trafc ow projections on the new roadways, analyze future land use development proposals, and transportation network changes in the Downtown. ●07/1/2025 The project will be planned in conjunction with the review of the developer’s application. Table of ContentsDowntown Dublin Street Grid Network 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 118 838 Dublin Boulevard Extension - Fallon Road to North Canyons Parkway Overview Project Number ST0216 Description This project provides for the environmental review, preliminary engineering, design and construction of the 1.5-mile extension of Dublin Boulevard from Fallon Road to North Canyons Parkway in Livermore. The extension is planned to have four to six travel lanes, bike lanes, a Class 1 bike/multi-use path, sidewalk, curb and gutter, trafc signals, street lighting, landscaped medians, bus stops, and utilities. The preliminary engineering and Environmental Impact Report (EIR) cost allocation between the City of Dublin and City of Livermore is governed by a Memorandum of Understanding approved by the City Council on April 19, 2016. Alameda CTC has assumed the role of implementing agency for the nal design phase of the project working in cooperation with the cities of Dublin and Livermore. The preliminary engineering level cost estimate for this project is currently at $153.6 million, which includes all project mitigation costs and indirect impacts mitigation and is anticipated to be divided among the City of Dublin and the City of Livermore based on street length in each jurisdiction. It is expected that the City of Dublin share will be approximately $126.1 million, and the City of Livermore share will be $27.5 million. The unincorporated Alameda County's costs will be shared between the City of Dublin and City of Livermore with the nal cost allocation to each jurisdiction to be dened by a Cooperative Agreement. The $11.2 million identied as Tri-Valley Transportation Council Grant is an approximate amount, which will be adjusted when the funding agreement is approved. Capital Cost Historical $30.7M FY2025 Budget $11.5M Total Budget (all years) $11.5M Future $84.2M Project Total (to date) $126M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $0 $0 $0 $0 $0 $74,472,415 $74,472,415 9200 - Contract Services $17,051,105 $250,000 $0 $0 $0 $0 $9,549,891 $26,850,996 9300 - Land/Right-of-way $13,324,879 $11,200,000 $0 $0 $0 $0 $0 $24,524,879 9100 - Salaries & Benefits $361,262 $0 $0 $0 $0 $0 $200,000 $561,262 9500 - Miscellaneous $4,466 $0 $0 $0 $0 $0 $0 $4,466 Total $30,741,712 $11,450,000 $0 $0 $0 $0 $84,222,306 $126,414,018 Table of ContentsDublin Boulevard Extension - Fallon Road to North Canyons Parkway 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 119 839 Funding Sources Historical $30.7M FY2025 Budget $11.5M Total Budget (all years) $11.5M Future $84.2M Project Total (to date) $126M Operational Costs FY2025 Budget $0 Total Budget (all years) $145K Project Total $145K Project Timeline ●04/19/2016 MOU between City of Dublin and City of Livermore approved for preliminary engineering and environmental impact report phase. ●08/20/2019 EIR Certied, General Plan and Eastern Dublin Specic Plan amended. ●09/3/2019 Right-of-way established. Ordinance effective 30 days thereafter. ●05/19/2020 Cooperative Agreement with City of Dublin, City of Livermore, and Alameda CTC approved for the design phase. ●02/1/2021 NEPA completed. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9998 - Unidentified $0 $0 $0 $0 $0 $0 $84,222,306 $84,222,306 1101 - General Fund Designated Reserve $20,000,000 $250,000 $0 $0 $0 $0 $0 $20,250,000 2922 - Tri-Valley Transportation Council Grants $0 $11,200,000 $0 $0 $0 $0 $0 $11,200,000 1001 - General Fund $7,290,382 $0 $0 $0 $0 $0 $0 $7,290,382 4302 - Eastern Dublin Transportation Impact Fee $1,737,585 $0 $0 $0 $0 $0 $0 $1,737,585 4301 - Eastern Dublin Transportation Impact Fee $1,033,916 $0 $0 $0 $0 $0 $0 $1,033,916 2217 - Measure BB Grants $439,824 $0 $0 $0 $0 $0 $0 $439,824 2220 - Road Maint. & Rehab Account (RMRA) $240,005 $0 $0 $0 $0 $0 $0 $240,005 Total $30,741,712 $11,450,000 $0 $0 $0 $0 $84,222,306 $126,414,018 Table of ContentsDublin Boulevard Extension - Fallon Road to North Canyons Parkway 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 120 840 ●02/7/2023 Approved agreement with RES Environmental Operating Company, LLC for environmental mitigation services. ●07/1/2025 The project is currently in the design phase with 95% design completion anticipated in fall 2025. Table of ContentsDublin Boulevard Extension - Fallon Road to North Canyons Parkway 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 121 841 Dublin Ranch Streetlight Improvements Overview Project Number ST0417 Description This project provides for the design and repainting of decorative streetlight poles. Repainting of the streetlight poles protects the integrity of the poles and improves aesthetics in the surrounding neighborhood. This project is funded by revenue collected through the Streetlight District assessments. Capital Cost Historical $66.7K FY2025 Budget $42K Total Budget (all years) $210K Project Total (to date) $277K Funding Sources Historical $66.7K FY2025 Budget $42K Total Budget (all years) $210K Project Total (to date) $277K Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9200 - Contract Services $42,386 $34,820 $34,820 $34,820 $34,820 $34,820 $0 $216,486 9100 - Salaries & Benefits $20,295 $6,760 $6,760 $6,760 $6,760 $6,760 $0 $54,095 9500 - Miscellaneous $4,060 $420 $420 $420 $420 $420 $0 $6,160 Total $66,741 $42,000 $42,000 $42,000 $42,000 $42,000 $0 $276,741 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2705 - Street Light District East Dublin 1999-1 $66,741 $42,000 $42,000 $42,000 $42,000 $42,000 $0 $276,741 Total $66,741 $42,000 $42,000 $42,000 $42,000 $42,000 $0 $276,741 Table of ContentsDublin Ranch Streetlight Improvements 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 122 842 Project Timeline ●07/1/2025 The conversion of 1,626 existing streetlights into energy efcient LED in the Dublin Ranch Street Light Assessment District (1999-1) was completed with the Citywide Energy Improvements Project, CIP No. GI0121. Painting of streetlight poles is anticipated to begin in 2026. Table of ContentsDublin Ranch Streetlight Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 123 843 Golden Gate Drive Intersection Improvements - Dublin Blvd and St. Patrick Way Overview Project Number ST0423 Description This project provides for the design and construction of improvements at the intersections of Dublin Boulevard at Golden Gate Drive and St. Patrick Way at Golden Gate Drive. This is a Western Dublin Transportation Impact Fee Program project designed to relieve congestion, reduce greenhouse gases, and is an Active Transportation Solution. The project is identied in the Downtown Dublin Specic Plan and the Bicycle and Pedestrian Plan. The improvements may include a new trafc signal at the intersection of St. Patrick Way and Golden Gate Drive; trafc signal modications at the intersection of Dublin Boulevard at Golden Gate Drive; conversion of signal interconnection from copper to ber optic; signage, striping and markings; necessary green stormwater infrastructure; and utility, pavement, curb, gutter, ADA curb ramps, and sidewalk modications or adjustments. The project will also consider improvements at the BART driveway south of the Enea property. Staff will continue to seek funding opportunities. Capital Cost Historical $135K FY2025 Budget $816K Total Budget (all years) $4.32M Project Total (to date) $4 .45M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $609,000 $0 $2,600,000 $0 $0 $0 $3,209,000 9200 - Contract Services $101,000 $199,000 $0 $750,000 $0 $0 $0 $1,050,000 9100 - Salaries & Benefits $34,320 $8,320 $0 $150,000 $0 $0 $0 $192,640 Total $135,320 $816,320 $0 $3,500,000 $0 $0 $0 $4,451,640 Table of ContentsGolden Gate Drive Intersection Improvements - Dublin Blvd and St. Patrick Way 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 124 844 Funding Sources Historical $135K FY2025 Budget $816K Total Budget (all years) $4.32M Project Total (to date) $4 .45M Operational Costs FY2025 Budget $4K Total Budget (all years) $4K Project Total $4K Project Timeline ●07/1/2025 The project is currently in the preliminary design and planning phase. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9998 - Unidentified $0 $0 $0 $2,500,000 $0 $0 $0 $2,500,000 4304 - Western Dublin Transportation Impact Fee $135,320 $816,320 $0 $0 $0 $0 $0 $951,640 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $0 $0 $0 $600,000 $0 $0 $0 $600,000 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) $0 $0 $0 $400,000 $0 $0 $0 $400,000 Total $135,320 $816,320 $0 $3,500,000 $0 $0 $0 $4,451,640 Table of ContentsGolden Gate Drive Intersection Improvements - Dublin Blvd and St. Patrick Way 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 125 845 Green Stormwater Infrastructure Overview Project Number ST0121 Description This project provides for the planning, design, and construction of various citywide projects that will improve water quality and provide other environmental benets in accordance with the Green Stormwater Infrastructure (GSI) Plan. The GSI Plan and associated projects and trash load reduction requirements are mandated by the Municipal Regional Stormwater Permit (MRP). Projects include stormwater full trash capture device installation throughout the City, and construction of GSI along the Iron Horse Regional Trail corridor, south of Amador Valley Boulevard. The City and Alameda CTC entered into Cooperative Agreements on February 7, 2023 and April 16, 2024 to partner on the design, environmental permitting, and construction phases for a bio-retention and hydromodication management facility along the Iron Horse Regional Trail corridor, south of Amador Valley Boulevard, that satises a portion of the City's GSI requirement and Alameda CTC's project, SR84 Expressway Widening and SR84/I-680 Interchange Improvements.   Construction is anticipated to be complete in summer 2025.  Alameda CTC's share of the costs is 75% of the total, which will be reimbursed to the City after expenditure. Both agencies will enter into a subsequent agreement for the maintenance phase. The "Other County Reimbursement" funding is from Alameda CTC. The design of the Citywide Trash Capture Devices phase of the project is completed and is anticipated to begin construction in summer 2025. Capital Cost Historical $3.29M FY2025 Budget $420K Total Budget (all years) $870K Project Total (to date) $4 .16M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $2,333,670 $275,000 $0 $300,000 $0 $0 $0 $2,908,670 9200 - Contract Services $847,053 $115,000 $0 $120,000 $0 $0 $0 $1,082,053 9100 - Salaries & Benefits $96,340 $30,000 $0 $30,000 $0 $0 $0 $156,340 9500 - Miscellaneous $12,000 $0 $0 $0 $0 $0 $0 $12,000 Total $3,289,063 $420,000 $0 $450,000 $0 $0 $0 $4,159,063 Table of ContentsGreen Stormwater Infrastructure 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 126 846 Funding Sources Historical $3.29M FY2025 Budget $420K Total Budget (all years) $870K Project Total (to date) $4 .16M Operational Costs FY2025 Budget $0 Total Budget (all years) $7.5K Project Total $7.5K Project Timeline ●06/18/2019 Green Stormwater Infrastructure Plan approved. ●07/1/2021 Planning phase began. ●02/7/2023 Cooperative Agreement with Alameda CTC approved for the design and environmental permitting phase. ●04/16/2024 Cooperative Agreement with Alameda CTC approved for the construction phase. ●07/1/2025 Planning for trash capture device installation began in Fiscal Year 2021-22. Staff have identied approximately 80 locations for potential device installation anticipated in summer 2025. Construction of GSI along the Iron Horse Regional Trail corridor began in summer 2024 and is anticipated to be completed in summer 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9901 - Other County Reimbursement $2,335,687 $0 $0 $0 $0 $0 $0 $2,335,687 1101 - General Fund Designated Reserve $953,376 $420,000 $0 $450,000 $0 $0 $0 $1,823,376 Total $3,289,063 $420,000 $0 $450,000 $0 $0 $0 $4,159,063 Table of ContentsGreen Stormwater Infrastructure 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 127 847 Iron Horse Trail Bridge at Dublin Boulevard Overview Project Number ST0118 Description This project provides for the planning, design, and construction of the Iron Horse Trail bridge for bicycles and pedestrians over Dublin Boulevard. The project will construct a 230-foot clear span truss arch bridge consistent with the Iron Horse Trail Feasibility Study and preliminary bridge design, approved by the City Council on November 7, 2017. The bridge will provide safer and easier trail access, including access to and from the Dublin-Pleasanton BART station. The Alameda CTC approved an allocation of $1,294,000 of Measure BB discretionary funds in Fiscal Year 2017-18 for the bridge design and environmental clearance. On June 17, 2019, Alameda CTC approved additional funding in the amount of $4,751,000 of Measure BB and $856,419 of Transportation for Clean Air funds for the construction phase of the project. The project will also receive funding of $1,000,000 for construction from a Developer contribution from the Boulevard Project. In fall of 2020, BART approved $1,500,000 of Measure RR Safe Routes to BART Grant for the construction phase of the project along with $600,000 of Tri- Valley Transportation Council Grants. Capital Cost Historical $14M FY2025 Budget $50K Total Budget (all years) $50K Project Total (to date) $14 .1M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $11,416,979 $0 $0 $0 $0 $0 $0 $11,416,979 9200 - Contract Services $2,419,540 $50,000 $0 $0 $0 $0 $0 $2,469,540 9100 - Salaries & Benefits $155,460 $0 $0 $0 $0 $0 $0 $155,460 9500 - Miscellaneous $12,460 $0 $0 $0 $0 $0 $0 $12,460 Total $14,004,439 $50,000 $0 $0 $0 $0 $0 $14,054,439 Table of ContentsIron Horse Trail Bridge at Dublin Boulevard 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 128 848 Funding Sources Historical $14M FY2025 Budget $50K Total Budget (all years) $50K Project Total (to date) $14 .1M Operational Costs FY2025 Budget $80K Total Budget (all years) $480K Project Total $480K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2217 - Measure BB Grants $6,045,000 $0 $0 $0 $0 $0 $0 $6,045,000 2218 - Measure RR $1,500,000 $0 $0 $0 $0 $0 $0 $1,500,000 4401 - Dublin Crossing Development Fee $1,000,000 $0 $0 $0 $0 $0 $0 $1,000,000 2220 - Road Maint. & Rehab Account (RMRA) $970,000 $0 $0 $0 $0 $0 $0 $970,000 2207 - Transportation for Clean Air $856,419 $0 $0 $0 $0 $0 $0 $856,419 2201 - State Gas Tax $845,040 $0 $0 $0 $0 $0 $0 $845,040 2922 - Tri-Valley Transportation Council Grants $600,000 $0 $0 $0 $0 $0 $0 $600,000 2204 - Measure B Sales Tax - Local Streets Fund (Alameda CTC) $587,980 $0 $0 $0 $0 $0 $0 $587,980 4301 - Eastern Dublin Transportation Impact Fee $500,000 $0 $0 $0 $0 $0 $0 $500,000 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $400,000 $0 $0 $0 $0 $0 $0 $400,000 2205 - Measure B Sales Tax - Bike & Ped. Fund (Alameda CTC) $400,000 $0 $0 $0 $0 $0 $0 $400,000 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) $300,000 $0 $0 $0 $0 $0 $0 $300,000 1101 - General Fund Designated Reserve $0 $50,000 $0 $0 $0 $0 $0 $50,000 1001 - General Fund $0 $0 $0 $0 $0 $0 $0 $0 Total $14,004,439 $50,000 $0 $0 $0 $0 $0 $14,054,439 Table of ContentsIron Horse Trail Bridge at Dublin Boulevard 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 129 849 Project Timeline ●11/7/2017 Iron Horse Trail Feasibility Study and preliminary bridge design approved. ●07/1/2025 The bridge opened on November 23, 2024. Work at the southwest limits adjacent Scarlett Drive extension should be completed in 2026. Table of ContentsIron Horse Trail Bridge at Dublin Boulevard 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 130 850 San Ramon Road Trail Lighting Overview Project Number ST0514 Description This project provides for the design and construction of improvements to the trail light xtures between Silvergate Drive and Alcosta Boulevard. In prior years, the project included installation of tree root barriers and repair of portions of the asphalt concrete trail, which were completed with other CIP Projects (ST0514 - Storm Drain Bypass San Ramon Road, ST0117 - Annual Street Resurfacing, and ST0517 - Citywide Bicycle and Pedestrian Improvements). Capital Cost Historical $173K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $173K Funding Sources Historical $173K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $173K Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $119,891 $0 $0 $0 $0 $0 $0 $119,891 9200 - Contract Services $31,142 $0 $0 $0 $0 $0 $0 $31,142 9100 - Salaries & Benefits $21,378 $0 $0 $0 $0 $0 $0 $21,378 9500 - Miscellaneous $1,050 $0 $0 $0 $0 $0 $0 $1,050 Total $173,461 $0 $0 $0 $0 $0 $0 $173,461 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1001 - General Fund $173,461 $0 $0 $0 $0 $0 $0 $173,461 Total $173,461 $0 $0 $0 $0 $0 $0 $173,461 Table of ContentsSan Ramon Road Trail Lighting 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 131 851 Project Timeline ●06/30/2022 The trail lighting improvement portion of the project was completed in 2022. ●07/1/2025 The remaining pole painting portion of the project will be completed in conjunction with the Dublin Ranch Street Light Improvements, CIP No. ST0417. Table of ContentsSan Ramon Road Trail Lighting 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 132 852 Tassajara Road Improvements - Nor th Dublin Ranch Drive to Quarry Lane School Overview Project Number ST0119 Description This project provides for design and construction to complete the street improvements on Tassajara Road, from North Dublin Ranch Drive to Quarry Lane School. The scope of this project was previously included as part of CIP No. ST0116 - Tassajara Road Realignment & Widening, which included the design and construction of Tassajara Road from North Dublin Ranch Drive to Dublin's northern limit. In Fiscal Year 2018-19, the scope of ST0116 was revised to only include the segment of Tassajara Road north of Fallon Road. The project will improve Tassajara Road to a four-lane arterial standard, with bike lanes, sidewalks, landscaped median, stormwater treatment areas, and other associated street improvements. Portions of the existing roadway have been improved by adjacent development projects and this project will complete the street improvements implementing the General Plan and the Complete Streets Policy. This roadway segment is a project within the Eastern Dublin Transportation Impact Fee program. Preliminary engineering and environmental documentation were completed as part of ST0116. Capital Cost Historical $13.5M FY2025 Budget $1.5M Total Budget (all years) $1.5M Project Total (to date) $15M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $10,340,000 $1,500,000 $0 $0 $0 $0 $0 $11,840,000 9200 - Contract Services $2,169,660 $0 $0 $0 $0 $0 $0 $2,169,660 9300 - Land/Right-of-way $436,300 $0 $0 $0 $0 $0 $0 $436,300 9500 - Miscellaneous $418,000 $0 $0 $0 $0 $0 $0 $418,000 9100 - Salaries & Benefits $136,040 $0 $0 $0 $0 $0 $0 $136,040 Total $13,500,000 $1,500,000 $0 $0 $0 $0 $0 $15,000,000 Table of ContentsTassajara Road Improvements - North Dublin Ranch Drive to Quarry Lane School 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 133 853 Funding Sources Historical $13.5M FY2025 Budget $1.5M Total Budget (all years) $1.5M Project Total (to date) $15M Operational Costs FY2025 Budget $20K Total Budget (all years) $20K Project Total $20K Project Timeline ●07/1/2025 Right-of-way acquisition was completed in mid-2025. The project is currently in design and permitting with resource agencies with construction anticipated to begin in late 2025. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 4306 - Tri-Valley Transportation Development Fee $5,500,000 $0 $0 $0 $0 $0 $0 $5,500,000 4301 - Eastern Dublin Transportation Impact Fee $3,848,020 $0 $0 $0 $0 $0 $0 $3,848,020 4305 - Traffic Impact Fee - Dougherty Valley $1,500,000 $0 $0 $0 $0 $0 $0 $1,500,000 2922 - Tri-Valley Transportation Council Grants $1,450,000 $0 $0 $0 $0 $0 $0 $1,450,000 2201 - State Gas Tax $1,201,980 $0 $0 $0 $0 $0 $0 $1,201,980 2217 - Measure BB Grants $0 $872,000 $0 $0 $0 $0 $0 $872,000 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $0 $500,000 $0 $0 $0 $0 $0 $500,000 2207 - Transportation for Clean Air $0 $128,000 $0 $0 $0 $0 $0 $128,000 Total $13,500,000 $1,500,000 $0 $0 $0 $0 $0 $15,000,000 Table of ContentsTassajara Road Improvements - North Dublin Ranch Drive to Quarry Lane School 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 134 854 Tassajara Road Realignment and Widening - Fallon Road to North City Limit Overview Project Number ST0116 Description The project provides for the planning and preliminary engineering to dene a new roadway alignment, design cross-section, right-of-way, and environmental clearance for Tassajara Road between North Dublin Ranch Drive and the City and Contra Costa County limits. The project also provides for the design and construction of a realigned Tassajara Road from Fallon Road to the northern city limit, which will be coordinated with Contra Costa County. Planning and preliminary engineering costs will be split in accordance with the Memorandum of Understanding, which was approved on September 16, 2014. Costs for the design and construction will be agreed upon and split proportionally with the work within each jurisdiction. The City and Contra Costa County executed a JEPA on September 23, 2020 for Contra Costa County to lead the project design, which started in January 2021. The design and construction of the southerly Tassajara Road segment is included in another Capital Improvement Program project, Tassajara Road Improvements - North Dublin Ranch Drive to Quarry Lane School (ST0119). This project will widen Tassajara Road to a four-lane arterial standard with bike lanes, sidewalks, landscaped median, stormwater treatment areas, and other associated street improvements. Segments of the existing roadway have been improved by adjacent development projects. This project will complete the street improvements and realign the remaining segments of the existing roadway to improve safety and achieve better circulation while adhering to the Complete Streets Policy. The roadway segment is a project within both the Tri-Valley Transportation Council Strategic Expenditure Plan (Project B-8) and the Eastern Dublin Transportation Impact Fee Program. Capital Cost Historical $11.8M FY2025 Budget $1M Total Budget (all years) $1M Project Total (to date) $12.8M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $7,072,476 $1,000,000 $0 $0 $0 $0 $0 $8,072,476 9300 - Land/Right-of-way $1,980,000 $0 $0 $0 $0 $0 $0 $1,980,000 9200 - Contract Services $1,924,149 $0 $0 $0 $0 $0 $0 $1,924,149 9500 - Miscellaneous $495,313 $0 $0 $0 $0 $0 $0 $495,313 9100 - Salaries & Benefits $305,478 $0 $0 $0 $0 $0 $0 $305,478 Total $11,777,416 $1,000,000 $0 $0 $0 $0 $0 $12,777,416 Table of ContentsTassajara Road Realignment and Widening - Fallon Road to North City Limit 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 135 855 Funding Sources Historical $11.8M FY2025 Budget $1M Total Budget (all years) $1M Project Total (to date) $12.8M Operational Costs FY2025 Budget $15K Total Budget (all years) $15K Project Total $15K Project Timeline ●01/1/2015 Planning and preliminary engineering MOU approved Sept 2014 ●09/23/2020 JEPA with Contra Costa County executed for County to take the lead in the design phase. ●01/1/2021 Design began Jan 2021 ●07/1/2025 The project is currently in design. Construction is anticipated to begin in 2027. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 4301 - Eastern Dublin Transportation Impact Fee $6,008,739 $0 $0 $0 $0 $0 $0 $6,008,739 4305 - Traffic Impact Fee - Dougherty Valley $3,964,338 $0 $0 $0 $0 $0 $0 $3,964,338 2922 - Tri-Valley Transportation Council Grants $0 $1,000,000 $0 $0 $0 $0 $0 $1,000,000 2220 - Road Maint. & Rehab Account (RMRA) $692,059 $0 $0 $0 $0 $0 $0 $692,059 4306 - Tri-Valley Transportation Development Fee $503,017 $0 $0 $0 $0 $0 $0 $503,017 4303 - Traffic Impact Fee - Category 3 $409,263 $0 $0 $0 $0 $0 $0 $409,263 2201 - State Gas Tax $200,000 $0 $0 $0 $0 $0 $0 $200,000 Total $11,777,416 $1,000,000 $0 $0 $0 $0 $0 $12,777,416 Table of ContentsTassajara Road Realignment and Widening - Fallon Road to North City Limit 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 136 856 Trafc Signal and Roadway Safety Improvements Overview Project Number ST0123 Description This project will provide for feasibility, design, and construction and modication of trafc signals and roadway safety improvements at locations prioritized and recommended by Local Roadway Safety Plan (LRSP), which was approved in January 2023. Improvements include upgrading the signal equipment such as trafc signal poles/mast arms, vehicle and pedestrian signal heads, signal controllers, cabinet upgrades, streetlighting/safety lighting improvements, signal phasing and timing changes, signing and striping improvements, and other alternatives identied in the LRSP toolbox and under systemic and site recommendations. The project will also provide for evaluating the design and installation of protected intersection elements. Capital Cost Historical $170K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $170K Funding Sources Historical $170K FY2025 Budget $0 Total Budget (all years) $0 Project Total (to date) $170K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9200 - Contract Services $149,200 $0 $0 $0 $0 $0 $0 $149,200 9100 - Salaries & Benefits $20,800 $0 $0 $0 $0 $0 $0 $20,800 Total $170,000 $0 $0 $0 $0 $0 $0 $170,000 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) $85,000 $0 $0 $0 $0 $0 $0 $85,000 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $85,000 $0 $0 $0 $0 $0 $0 $85,000 1001 - General Fund $0 $0 $0 $0 $0 $0 $0 $0 Total $170,000 $0 $0 $0 $0 $0 $0 $170,000 Table of ContentsTraffic Signal and Roadway Safety Improvements 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 137 857 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●01/31/2023 Local Roadway Safety Plan approved. ●07/1/2025 The installation of yellow, retroreective borders at 14 intersections that were identied in the Local Roadway Safety Plan was completed in early 2025. Table of ContentsTraffic Signal and Roadway Safety Improvements 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 138 858 Trafc Signal Re-Lamping Overview Project Number ST0223 Description This project provides for the replacement of the trafc signal and pedestrian signal LED lamps at approximately 78 signalized intersections. The City currently has 98 trafc signals, many of which were installed in 2008, and the LED lamps are reaching the end of their useful life, which is typically eight to 10 years. The City has replaced 20 signalized intersection lamps through on-going maintenance efforts. New LED lamps will ensure proper visibility of vehicle and pedestrian signal heads, which is critical for maintaining safe trafc ow. Capital Cost Historical $512K FY2025 Budget $0 Total Budget (all years) $135K Project Total (to date) $647K Funding Sources Historical $512K FY2025 Budget $0 Total Budget (all years) $135K Project Total (to date) $647K Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $433,760 $0 $130,840 $0 $0 $0 $0 $564,600 9200 - Contract Services $70,000 $0 $0 $0 $0 $0 $0 $70,000 9100 - Salaries & Benefits $8,320 $0 $4,160 $0 $0 $0 $0 $12,480 Total $512,080 $0 $135,000 $0 $0 $0 $0 $647,080 Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 2212 - Vehicle Registration Fee (Alameda CTC) $260,000 $0 $0 $0 $0 $0 $0 $260,000 2201 - State Gas Tax $177,080 $0 $60,000 $0 $0 $0 $0 $237,080 2215 - Measure BB Sales Tax - Bike & Ped. Fund (Alameda CTC) $75,000 $0 $25,000 $0 $0 $0 $0 $100,000 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $0 $0 $50,000 $0 $0 $0 $0 $50,000 Total $512,080 $0 $135,000 $0 $0 $0 $0 $647,080 Table of ContentsTraffic Signal Re-Lamping 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 139 859 Operational Costs FY2025 Budget $0 Total Budget (all years) $0 Project Total $0 Project Timeline ●07/1/2025 Construction is anticipated to be completed in 2026. Table of ContentsTraffic Signal Re-Lamping 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 140 860 Village Parkway Reconstruction Overview Project Number ST0323 Description This project provides for the planning, design, and construction of the replacement of the existing streetscape elements on Village Parkway between Amador Valley Boulevard and the northern city limit (approximately 6,000 linear feet). The project will transform the segment of Village Parkway between Amador Valley Boulevard and Kimball Avenue to a pedestrian and bicycle friendly roadway, which will incorporate complete streets elements such as median islands, bulbouts, decorative or high visibility crosswalks, and street lighting. The work may include the reconstruction of the median island; reconstruction of the roadway base immediately adjacent to the median island; reconstruction necessary for sidewalks improvements, ADA upgrades to curb ramps, curb, and gutter; necessary utility work; landscaping; stormwater improvements; and new pavement for the roadway. The project will also include the replacement of the city entrance monument sign at Village Parkway median at Kimball Avenue, as well as intersection improvements at Village Parkway and Amador Valley Boulevard, including removal of slip lanes, curb ramp upgrades, crosswalk realignment, and trafc signal modication.  Capital Cost Historical $550K FY2025 Budget $1.05M Total Budget (all years) $26.2M Project Total (to date) $26.7M Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 9400 - Improvements $0 $0 $10,000,000 $2,700,000 $9,550,000 $0 $0 $22,250,000 9200 - Contract Services $504,968 $1,000,080 $1,000,000 $510,560 $1,000,000 $0 $0 $4,015,608 9100 - Salaries & Benefits $45,032 $49,920 $64,480 $89,440 $100,000 $0 $0 $348,872 9500 - Miscellaneous $0 $0 $85,520 $0 $0 $0 $0 $85,520 Total $550,000 $1,050,000 $11,150,000 $3,300,000 $10,650,000 $0 $0 $26,700,000 Table of ContentsVillage Parkway Reconstruction 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 141 861 Funding Sources Historical $550K FY2025 Budget $1.05M Total Budget (all years) $26.2M Project Total (to date) $26.7M Operational Costs FY2025 Budget $0 Total Budget (all years) $100K Project Total $100K Project Timeline ●02/20/2024 The City Council approved the Concept Plan on February 20, 2024 and approved the recommendation to add replacement of the neighborhood concrete walls to the project. ●05/22/2025 The project will receive grants funds in the amount of $9,150,000 from the State Transportation Improvement Program, which will be allocated in Fiscal Year 2027-28. On May 22, 2025, Alameda CTC awarded grant funding in the amount of $1,215,000 in Measure BB funds and $285,000 in VRF funds, which will be allocated in Fiscal Year 2027-28. ●07/1/2025 The project is currently in design. Construction is anticipated to begin in 2027. Detailed Breakdown Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total 1101 - General Fund Designated Reserve $550,000 $1,000,000 $10,650,000 $2,800,000 $0 $0 $0 $15,000,000 9997 - Other $0 $0 $0 $0 $9,150,000 $0 $0 $9,150,000 2217 - Measure BB Grants $0 $0 $0 $0 $1,215,000 $0 $0 $1,215,000 2214 - Measure BB Sales Tax - Local Streets Fund (Alameda CTC) $0 $0 $250,000 $200,000 $0 $0 $0 $450,000 2201 - State Gas Tax $0 $50,000 $250,000 $100,000 $0 $0 $0 $400,000 2924 - VRF (ACTC) Grants $0 $0 $0 $0 $285,000 $0 $0 $285,000 1001 - General Fund $0 $0 $0 $200,000 $0 $0 $0 $200,000 Total $550,000 $1,050,000 $11,150,000 $3,300,000 $10,650,000 $0 $0 $26,700,000 Table of ContentsVillage Parkway Reconstruction 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 142 862 Unfunded - Future Projects FY25 - FY29 Unfunded - Future Projects Projects (including Historical, Future) City Entrance Signs $510,000 0.56% Dublin Sports Grounds - Phase 5 Renovation $2,750,000 3.01% Eastern Dublin Transportation Impact Fee $61,750,000 67.59% Emerald Glen Recreation and Aquatic Complex - Phase 2 $17,600,000 19.26% Western Dublin Transportation Impact Fee $8,750,000 9.58% 000 000 000 000 000 000 $91M$91M$91M Historical 2025 2026 2027 2028 2029 Future 0 $25M $50M $75M $100M Summary of Requests Project No. / Category Historical FY2025 FY2026 FY2027 FY2028 FY2029 Future Total S-01 City Entrance Signs $0 $0 $0 $0 $0 $0 $510,000 $510,000 P-01 Dublin Sports Grounds - Phase 5 Renovation $0 $0 $0 $0 $0 $0 $2,750,000 $2,750,000 S-02 Eastern Dublin Transportation Impact Fee $0 $0 $0 $0 $0 $0 $61,750,000 $61,750,000 P-02 Emerald Glen Recreation and Aquatic Complex - Phase 2 $0 $0 $0 $0 $0 $0 $17,600,000 $17,600,000 S-03 Western Dublin Transportation Impact Fee $0 $0 $0 $0 $0 $0 $8,750,000 $8,750,000 Total Summary of Requests $0 $0 $0 $0 $0 $0 $91,360,000 $91,360,000 Table of ContentsUnfunded - Future Projects 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 143 863 City Entrance Signs Overview Project Number S-01 Description This project provides for the design and construction to install City entrance signs at the following six locations: San Ramon Road median at Alcosta Boulevard, Schaefer Ranch Road at Dublin Boulevard, Tassajara Road north of Fallon Road, Dublin Boulevard and San Ramon Road (Downtown gateway), Fallon Road at Dublin Boulevard and at Dublin Boulevard at the eastern city limit. The new signs will conform to the City of Dublin Streetscape Master Plan and will match the existing granite monument signs currently installed within the City. Capital Cost FY2025 Budget $0 Total Budget (all years) $0 Future $510K Project Total $510K Funding Sources FY2025 Budget $0 Total Budget (all years) $0 Future $510K Project Total $510K Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Estimated Costs $0 $0 $0 $0 $0 $0 $510,000 $510,000 Total $0 $0 $0 $0 $0 $0 $510,000 $510,000 Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Unidentified $0 $0 $0 $0 $0 $0 $510,000 $510,000 Total $0 $0 $0 $0 $0 $0 $510,000 $510,000 Table of ContentsCity Entrance Signs 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 144 864 Dublin Sports Grounds - Phase 5 Renovation Overview Project Number P-01 Description This project provides for the design and construction to renovate a portion of the Dublin Sports Grounds. The Phase 5 project encompasses approximately 180,000 square feet, west of Soccer Field #3, and includes installation of a sand channel drainage system, irrigation upgrades and new turf. Capital Cost FY2025 Budget $0 Total Budget (all years) $0 Future $2.75M Project Total $2.75M Funding Sources FY2025 Budget $0 Total Budget (all years) $0 Future $2.75M Project Total $2.75M Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Estimated Costs $0 $0 $0 $0 $0 $0 $2,750,000 $2,750,000 Total $0 $0 $0 $0 $0 $0 $2,750,000 $2,750,000 Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Unidentified $0 $0 $0 $0 $0 $0 $2,750,000 $2,750,000 Total $0 $0 $0 $0 $0 $0 $2,750,000 $2,750,000 Table of ContentsDublin Sports Grounds - Phase 5 Renovation 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 145 865 Eastern Dublin Transpor tation Impact Fee Overview Project Number S-02 Description This project provides for the design and construction of 15 projects being partially funded by the Eastern Dublin Transportation Impact Fee (EDTIF) program. The City Council established the EDTIF program on January 9, 1995 and adopted the most recent update on December 21, 2021. This project does not include completed EDTIF projects, current projects that are individual CIP projects, or current projects to be constructed by developers. EDTIF projects within the ve-year capital improvement program are: ST0116 Tassajara Road Realignment & Widening; ST0119 Tassajara Road Improvements - North Dublin Ranch Drive to Quarry Lane School; and ST0216 Dublin Boulevard Extension. Capital Cost FY2025 Budget $0 Total Budget (all years) $0 Future $61.8M Project Total $61.8M Funding Sources FY2025 Budget $0 Total Budget (all years) $0 Future $61.8M Project Total $61.8M Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Estimated Costs $0 $0 $0 $0 $0 $0 $61,750,000 $61,750,000 Total $0 $0 $0 $0 $0 $0 $61,750,000 $61,750,000 Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Unidentified $0 $0 $0 $0 $0 $0 $61,750,000 $61,750,000 Total $0 $0 $0 $0 $0 $0 $61,750,000 $61,750,000 Table of ContentsEastern Dublin Transportation Impact Fee 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 146 866 Emerald Glen Recreation and Aquatic Complex - Phase 2 Overview Project Number P-02 Description This project provides for the design and construction of the nal phase of the Emerald Glen Recreation and Aquatic Complex (known as The Wave). Amenities may include a community room and gymnasium space. This project may be modied as the City has entered into an agreement for a joint use gymnasium at the Dublin Crossing school site. Until such time, it will remain as a future project. Capital Cost FY2025 Budget $0 Total Budget (all years) $0 Future $17.6M Project Total $17.6M Funding Sources FY2025 Budget $0 Total Budget (all years) $0 Future $17.6M Project Total $17.6M Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Estimated Costs $0 $0 $0 $0 $0 $0 $17,600,000 $17,600,000 Total $0 $0 $0 $0 $0 $0 $17,600,000 $17,600,000 Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Unidentified $0 $0 $0 $0 $0 $0 $17,600,000 $17,600,000 Total $0 $0 $0 $0 $0 $0 $17,600,000 $17,600,000 Table of ContentsEmerald Glen Recreation and Aquatic Complex - Phase 2 2024-2029 Five-Year Capital Improvement Program Update | DublinPage 147 867 Western Dublin Transportation Impact Fee Overview Project Number S-03 Description This project provides for the design and construction of eight projects being partially funded by the Western Dublin Transportation Impact Fee (WDTIF) program. The City Council adopted an update to the WDTIF on September 6, 2016. The WDTIF program includes a total of nine projects, however the following three projects are within the ve-year capital improvement program: ST0815 - Amador Plaza Road Bicycle and Pedestrian Improvements, and ST0423 - Golden Gate Drive Intersection Improvements - Dublin Boulevard and St. Patrick Way. Capital Cost FY2025 Budget $0 Total Budget (all years) $0 Future $8.75M Project Total $8.75M Funding Sources FY2025 Budget $0 Total Budget (all years) $0 Future $8.75M Project Total $8.75M Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Estimated Costs $0 $0 $0 $0 $0 $0 $8,750,000 $8,750,000 Total $0 $0 $0 $0 $0 $0 $8,750,000 $8,750,000 Detailed Breakdown Category Historical FY2025 Requested FY2026 Requested FY2027 Requested FY2028 Requested FY2029 Requested Future Total Unidentified $0 $0 $0 $0 $0 $0 $8,750,000 $8,750,000 Total $0 $0 $0 $0 $0 $0 $8,750,000 $8,750,000 Table of ContentsWestern Dublin Transportation Impact Fee 2024-2029 Five-Year Capital Improvement Program Update | Dublin Page 148 868 Five-Year Capital Improvement Program 2024-2029 Update June 17, 2025 869 Capital Improvement Program •A five-year planning document used by the City to identify and establish budgets for capital improvement projects. •CIP is adopted every two-years. •CIP project funding sources include: General Fund, Impact Fees, Special Revenues, Assessment Districts, and Grants. •April 15 –Preliminary CIP update presented to City Council •June 3 –Review of projects funded by the General Fund 870 2024-2029 CIP Expenditure Summary CATEGORY 2024-25 2025-26 2026-27 2027-28 2028-29 Five-Year General Improvements $10,075,459 $5,702,000 $1,500,000 $200,000 Public Art $780,000 $300,000 $0 $0 Parks $2,516,985 $6,050,941 $1,100,000 $5,150,000 Streets $24,240,347 $20,287,000 $15,942,000 $5,292,000 TOTAL $37,612,791 $32,339,941 $18,542,000 $10,642,000 General 16%Public Art 1% Parks 15% Streets 68% 871 General Improvement Projects PROJECT NUMBER & DESCRIPTION 2024-25 2025-26 BUDGET 2026-27 2027-28 2028-29 FIVE-YEAR GI0421 Audio Visual System Upgrade $771,000 $1,198,000 GI0121 Citywide Energy Improvements $1,500,000 $2,500,000 GI0001 Civic Center Elevator Modernization $900,000 GI0125 Civic Center Exterior Glazing, Sealing & Painting $4,250,000 $4,750,000 GI0122 Civic Center Rehabilitation $205,000 $205,000 GI0225 Condition Assessment of Water Features $50,000 $50,000 GI0120 Dublin Arts Center $1,000,000 GI0219 Electric Vehicle (EV) Charging Stations $197,459 $197,459 GI0325 Facilities Parking Lot Resurfacing $500,000 $1,000,000 GI0521 Library Tenant Improvements $2,000,000 $2,000,000 GI0221 Resiliency and Disaster Preparedness Improvements $277,000 $1,652,000 GI0004 Shannon Community Center Play Yard $200,000 $200,000 GI0006 The Wave Pool Replastering $500,000 $1,500,000 $2,000,000 GI0425 Waste Enclosures Upgrades $325,000 $325,000 TOTAL $10,075,459 $500,000 $1,500,000 $200,000 $17,977,459 872 Public Art Projects PROJECT NUMBER & DESCRIPTION 2024-25 2025-26 BUDGET 2026-27 2027-28 2028-29 FIVE-YEAR PA0121 Camp Parks Sign $280,000 $280,000 PA0123 Downtown Dublin $300,000 $250,000 $850,000 PA0125 Outdoor Murals $200,000 $200,000 TOTAL $780,000 $250,000 $0 $0 $1,330,000 873 Parks Projects PROJECT NUMBER & DESCRIPTION 2024-25 2025-26 BUDGET 2026-27 2027-28 2028-29 FIVE-YEAR PK0221 Downtown Dublin Town Square Park $4,680 $4,680 PK0002 Dublin Sports Grounds Rehabilitation $150,000 $600,000 $2,900,000 $3,650,000 PK0003 Fallon Sports Park - Artificial Turf Field Replacement $2,250,000 $2,250,000 PK0225 Fallon Sports Park Baseball Field G Upgrades $150,000 $400,000 PK0322 Forest Park $740,000 $740,000 PK0422 Iron Horse Nature Park and Open Space $1,497,305 $2,778,654 $6,766,900 PK0224 Kolb Park Renovation $1,975,000 PK0321 Restrooms Replacement $475,000 PK0004 Sports Courts Resurfacing $500,000 $1,100,000 PK0125 Sunday School Barn Flooring $125,000 $385,000 TOTAL $2,516,985 $2,928,654 $1,100,000 $5,150,000 $17,746,580 874 Streets Projects PROJECT NUMBER & DESCRIPTION 2024-25 2025-26 BUDGET 2026-27 2027-28 2028-29 FIVE-YEAR ST0117 Annual Street Resurfacing $4,603,324 $4,500,000 $4,500,000 $4,500,000 $22,603,324 ST0517 Citywide Bicycle and Pedestrian Improvements $2,474,673 $750,000 $750,000 $750,000 $7,330,673 ST0713 Citywide Signal Communications Upgrade $825,040 $2,679,040 ST0221 Downtown Dublin Street Grid Network $8,990 $8,990 ST0216 Dublin Blvd. Extension - Fallon Road to N. Canyons Parkway $11,450,000 $11,450,000 ST0417 Dublin Ranch Streetlight Improvements $42,000 $42,000 $42,000 $42,000 $210,000 ST0423 Golden Gate Dr. Inter. Imp. - Dublin Blvd & St. Patrick Way $816,320 $3,500,000 $4,316,320 ST0121 Green Stormwater Infrastructure $420,000 $450,000 $870,000 ST0118 Iron Horse Trail Bridge at Dublin Boulevard $50,000 $50,000 ST0119 Tassajara Rd. Imp. - N. Dublin Ranch Dr. to Quarry Lane School $1,500,000 $1,500,000 ST0116 Tassajara Rd. Realig. & Widening - Fallon Rd. to N. City Limit $1,000,000 $1,000,000 ST0223 Traffic Signal Re-Lamping $135,000 ST0323 Village Parkway Reconstruction $1,050,000 $3,300,000 $10,650,000 $26,150,000 TOTAL $24,240,347 $12,542,000 $15,942,000 $5,292,000 $78,303,347 875 Funding Source Breakdown General Fund 28.3% Special Revenues 36.3%Public Art Fund 1.2% Traffic Impact Fees 0.7% Public Facility Fees 3.5% Internal Service Funds 17.3% Other 8.0% Unidentified 4.6% 876 Funding Source Totals 2024-25 2025-26 BUDGET 2026-27 2027-28 2028-29 FIVE-YEAR TOTAL General Fund $18,221,900 $5,200,000 $1,850,000 $1,850,000 $32,702,723 Special Revenues $7,550,100 $4,842,000 $4,942,000 $3,442,000 $41,923,919 Public Art Fund $300,000 $250,000 $1,330,000 Traffic Impact Fees $816,320 Public Facility Fees $2,490,941 $4,054,446 Internal Service Funds $3,777,000 $650,000 $2,600,000 $5,350,000 $19,998,000 Other $9,150,000 $9,253,324 Unidentified $5,278,654 $5,278,654 TOTAL FINANCING $32,339,941 $16,220,654 $18,542,000 $10,642,000 $115,357,386 877 Future Projects •Corporation Yard Equipment Wash Pad * •Electric Vehicle (EV) Charging Stations (Future Phase) •Waste Enclosure Upgrades (Future Phase) •Downtown Dublin Town Square Park (Future Phase) •Sports Courts Resurfacing (Future Phase) •Dublin Sports Grounds – Phase 5 Renovation * •Emerald Glen Recreation and Aquatic Complex - Phase 2 * •Downtown Dublin Street Grid Network (Future Phase) •Dublin Boulevard Extension (Unfunded Portion of Current Project) •City Entrance Signs * •Eastern & Western Dublin Transportation Impact Fee Projects 878 Updates to Preliminary CIP Since April •Audio Visual System Upgrade (GI0421) •$250K Increase •Dublin Arts Center (GI0120) •$1M Increase •Resiliency and Disaster Preparedness Improvements (GI0221) •Award Tonight w/ $660,000 increase •Marquee Signs (GI0124) •Removed from CIP •Shade Structures at Various Facilities and Parks (GINEW01) •Removed from CIP •Fallon Sports Park Baseball Field G Upgrades (PK0225) •$250K Increase 879 Updates to Preliminary CIP Since April •Kolb Park Renovation (PK0224) •$475K Reduction (Moved restroom replacement to PK0321) •Reevaluating project scope •Restroom Replacement (PK0321) •$475K Increase (Added Kolb Park Restroom) •City Entrance Monument Signs (ST0319) •Removed from CIP (Added Kimball Ave. sign to Village Parkway Project (ST0323) & Remaining 4 Signs to Future City Entrance Signs (S-01)) •Citywide Storm Drain Improvements (ST0124) •Removed from CIP (Incorporated into Public Works Operating Budget) •San Ramon Road Landscape Renovation (ST0218) •Removed from CIP (Incorporated into Public Works Operating Budget) 880 CIP Book and Online Transparency Tool 881 Staff Recommendation Adopt the Resolution Adopting the Five-Year Capital Improvement Program 2024-2029 Update. 882