HomeMy WebLinkAboutReso 087-24 Item 5.3 Accepting Fallon Sports Park - Phase 3, CIP No. PK0119.pdf Docusign Envelope ID:2640FC10-F9D7-414D-A491-3A73EC197331
RESOLUTION NO. 87 - 24
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
ACCEPTING FALLON SPORTS PARK - PHASE 3, CIP NO. PK0119
WHEREAS, on February 16, 2021, the City of Dublin entered into a Construction Contract
with Suarez and Munoz Construction, Inc. for the Fallon Sports Park- Phase 3, with improvements
that included a cricket field, lighted five-bay batting cage, four volleyball courts, play area and two
little league fields; and
WHEREAS, said improvements have been completed in accordance with plans and
specifications, and any approved modifications thereof, to the satisfaction of the City Engineer of
the City of Dublin.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby accept the Fallon Sports Park - Phase 3, CIP No. PK0119 and authorize Staff to file a
Notice of Completion with Alameda County.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
authorize the City Manager or designee, to release the retention, if after 35 days of filing the Notice
of Completion there are no subcontractor claims.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
authorize the City Manager, or designee, to release the maintenance bond at the end of the
warranty period.
PASSED, APPROVED AND ADOPTED this 20th day of August 2024, by the following
vote:
AYES: Councilmembers Hu, Josey, Qaadri, Thalblum and Mayor McCorriston
NOES:
ABSENT:
ABSTAIN:
Signed by:
Mayor
ATTEST:
Docusigned by:
City ler
Reso. No. 87-24, Item 5.3, Adopted 08/20/2024 Page 1 of 1