HomeMy WebLinkAbout8.1 2022-2027 Capital Improvement Program – Project Status ReportII DUBLIN CALIFORNIA STAFF REPORT CITY COUNCIL Agenda Item 8.1 DATE: January 9, 2024 TO: Honorable Mayor and City Councilmembers FROM: Linda Smith, City Manager SU B.ECT : 2022-2027 Capital Improvement Program - Project Status Report Prepared by: Michael Boitnott, Capital Improvement Program Manager EXECUTIVE SUMMARY: The City Council will receive a report on the status of current Capital Improvement Program projects. STAFF RECOMMENDATION: Receive the report. FINANCIAL IMPACT: None. DESCRIPTION: The Capital Improvement Program (CIP) is a five-year planning instrument used to identify capital projects and to establish a budget for those projects. Every year, the City Council adopts an update to the CIP, and Staff includes the project budgets as part of the citywide two-year budget. The current 2022-2027 CIP (Attachment 1) includes projects in the categories of General Improvements (buildings, technology upgrades, etc.), Public Art, Parks, and Streets. In the coming months, in conjunction with the City's budget process, the City Council will be considering a new five-year CIP. Staff will include a discussion on CIP priorities at the City Council's Strategic Planning Session in early 2024. Additions and changes will then be incorporated into the 2024- 2029 Capital Improvement Program to be considered by the City Council later this fiscal year. This report provides the status of CIP projects with funding appropriated through the current fiscal year. Projects without funding until Fiscal Year 2024-25 or beyond are not discussed in this report. Page 1 of 15 1 General Improvements Audio -Visual System Upgrade (GI0421) This project provides for the planning, design, and construction of the audio-visual system upgrades in the Ambrose Hall and adjoining conference room at the Shannon Community Center, the Alamilla Springs Ballroom at the Senior Center, and the Program Room at the Dublin Library. The upgrades will include replacement of equipment to improve the service quality for rentals, meetings, and corporate events. Status:The plans and specifications for the project are currently being prepared. Next Milestone: Spring 2024 - Construction Bid Opening. Construction is expected to begin in summer 2024. Citywide Energy Improvements (GI0121) This project provides for the planning (Investment Grade Audit), design, and construction of various energy upgrades, efficiency improvements, lighting upgrades, energy generation, solar photovoltaic (PV) systems, and energy storage projects at facilities, parks, street rights -of -way, and other City -owned property. The project invests approximately $23 million in capital improvements that will result in more than $28 million in utility savings over the next 25 years. Status:The following construction is complete: lighting upgrades to various buildings, parks, sports fields and courts, and Dublin Ranch streetlights; HVAC controls upgrades at various facilities; solar panel installation at the Corp Yard, Dublin Sports Grounds (DSG), Fallon Sports Park, Fire Stations 17 and 18, and the Library; installation of new emergency back-up generators at Fire Station 16, the Library, and Shannon Community Center; and traffic signal hydrogen fuel cell and battery backup systems. Next Milestone: Installation and commissioning of microgrid at The Wave and Senior Center; solar panel and electric vehicle (EV) charging systems at DSG and the Public Safety Complex. Civic Center Rehabilitation (GI0122) This project provides for the planning, design, and construction of various rehabilitation and renovation projects at the Civic Center. The projects may include renovation of all restrooms, showers, kitchenettes, and the employee break room; modifications to conference rooms; lighting and ceiling replacement; site improvements to the parking lot area and surrounding walkways of the Civic Center; plaza and landscaping improvements; building security evaluation and upgrades; repainting; and Americans with Disabilities Act (ADA) and Code upgrades. Status: The renovation of three spaces into six on the second floor of City Hall is currently in construction. Conceptual plans for rehabilitation of the City Hall and Dublin Arts Center (DAC) interior courtyard are currently being prepared. Design has started for reconfiguration and reconstruction of the back (formerly Police Services) parking lot in support of the new solar panels and battery back-up system to be constructed with the Citywide Energy Improvements project after the DAC is complete. Next Milestone: Conceptual design for the renovation/rehabilitation of the courtyard will be presented to the City Council for consideration in early 2024. Final design for the parking lot reconfiguration will be completed in spring 2024. Page 2 of 15 2 Dublin Arts Center (DAC) (Cultural Arts Center GI0120) This project provides for the design and improvements of the approximately 13,000-square-foot DAC on the first floor of the Civic Center, which was formerly occupied by Dublin Police Services. The DAC will include: an Art Gallery, Black Box Theater space; multi -purpose art and music classrooms; a dance studio; and restrooms; as well as renovation of the second floor for the relocation of the Parks and Community Services Department offices. Status:The project is currently in construction. Next Milestone: Substantial completion is currently anticipated for summer 2024. Dublin Standard Plans & Details Update (GI0123) This project will update the City's Standard Plans, Details, and Specifications (Standards) utilized by the Public Works Department for design and construction of public improvements within the City's rights -of -way and properties. These Standards are necessary for consistency to provide guidance to designers, and to specify the current requirements for public infrastructure to be constructed and maintained by the City. Status: Review of the first draft of the revised and new standard details was completed in November 2023. Work on the standard specifications will begin in early 2024. Next Milestone: A second draft of the revised and new standard details is anticipated in January 2024. Electric Vehicle (EV) Charging Stations (GI02191 This project provides for the design and construction of electric vehicle (EV) charging spaces at The Wave at Emerald Glen Park and the underground infrastructure for future expansion. In future years, the project could provide for design and construction of EV charging spaces at other City facilities. Status: Eight EV charges at The Wave went into operation in September 2023. Next Milestone: Future phases are anticipated beyond 2026. Exterior Painting at Various City Facilities (GI0223) This project provides for the design and construction to paint the exterior and make minor repairs at various City facilities. Buildings should be painted approximately every 10 years to maintain the structures' appearance and to prevent damage caused by moisture infiltration. This project will include work at the following locations: Heritage Museum, Saint Raymond's Church, Kolb House, Senior Center, Fire Stations 16, 17, and 18, The Wave, and the Library. Status:The plans and specifications are currently being prepared for the project. Next Milestone: Spring 2024 - Construction Bid Opening. Construction is expected to begin in summer 2024. Page 3 of 15 3 Financial System Replacement (GI0319) This project provides for the replacement of the City's Enterprise Resource Planning (ERP) system and other related technological projects that support the City Council's initiative to "Become a 24/7 City Hall to Enhance Resident and Business Engagement." These include the OpenGov budget and financial transparency software and upgrades to the City's Laserfiche document management software. Status:The Finance, Human Resources and Payroll modules have been implemented. Next- Milestone: The Land Management module is anticipated to be implemented in 2024. IT Infrastructure Improvement (GI01171 This project allows for the replacement and upgrade of aging network hardware as well as the implementation of centralized Information Technology management tools that will increase efficiencies in City operations. Status: Replacement of situational cameras and monitoring software at The Wave, Senior Center, Heritage and Kolb House, and part of Civic Center have been completed. Shannon Community Center replacement is currently in the planning phase. Next Milestone: The integration of new cameras at DAC and upgrade to city Wi-Fi hardware, is anticipated to be implemented in 2024, after the DAC is substantially completed and the new data center is operational. Library Tenant Improvement (GI0521) This project provides for the design and construction of tenant improvements to the Dublin Library, including completion of 5,150 square feet of currently unoccupied space within the library building. Improvements may include removal of interior walls and the installation and modification of shelving and fixtures; carpet replacement; and repainting. Status:The conceptual design and estimates are currently being prepared. Next Milestone:The conceptual design is anticipated to be presented to the City Council for consideration in February 2024. Marquee Signs (GI0124) This project will provide for the design and construction to replace the digital signage display components at the Shannon Community Center and the Senior Center, as well as the addition of a double -sided LED marquee sign at Civic Center. Status: Site assessments are complete and conceptual design has begun. Next- Milestone: The conceptual design is anticipated to be presented to the City Council for consideration in 2024. Municipal Fiber (GI03231 This project provides for the planning, design, and construction to improve and extend the existing City Information Technology fiber optic network cabling and infrastructure by laying the foundation for future high speed networking capability and improve existing City facilities' Page 4 of 15 4 networking speed and reliability by interconnecting City facilities from Civic Center to Heritage Park and Museums, Shannon Community Center, Senior Center, and the Corp Yard. This project will improve Citywide Wi-Fi access, performance, security, also assist in improving Traffic Operations with faster fiber optic networks that support smart and adaptive traffic software. Status: Revisions are being made to the Municipal Fiber Master Plan Request for Proposals to potentially add broadband Internet connectivity for more public -facing infrastructure capabilities. Next Milestone: Issue the RFP in spring 2024. Resiliency and Disaster Preparedness (GI02211 This project provides for the planning, design, environmental permitting, if necessary, and construction to make repairs at the following locations: • Dougherty Hills Open Space, Crossridge Road Trailhead - slide repair • Dublin Boulevard, west of Silvergate Road - slide repair • Mape Memorial Park - Pathway Relocation • Shannon Community Center/San Ramon Road - ditch and culvert improvements • Various citywide storm drainage facility locations and repairs such as trash racks, culverts, ditches, bank stabilization, etc. Status: Staff has requested federal funding through FEMA and state funding through California Office of Emergency Services (CalOES) for these areas. Site visits with both agencies were conducted in August 2023. Preliminary engineering and design have begun. Next Milestone: Construction for the Mape Memorial Park - Pathway Relocation repairs will begin in early 2024. Roof Replacement at Various City Facilities (GI0423) This project provides for the design and construction of the roof replacement at the following City facilities: Heritage Museum, Saint Raymond's Church, Senior Center, and Fire Station 16. Status: This project has not started. Next Milestone: Design is anticipated to begin in 2024. Situational Awareness Camera Program (GI0523) This project will provide for 40 situational awareness cameras at 10 locations to cover known gaps within the City. These cameras will strategically be located along major corridors and arterials to maximize observation of Dublin's many entrances and exit points into and out of town. These cameras will be valuable technological resources that assists in criminal investigations and the apprehension of law violators within the City. Status: In spring 2023, the City worked with congressional representatives to request Community Project Funding of $198,000 for Situational Awareness Cameras for Dublin Police Services. The City proposes using this funding to purchase and install 60 cameras at 13 sites at or near schools and community parks. The proposal has secured the support of Congressman DeSaulnier, and the request will now work its way through the congressional appropriations process. If approved, the City expects to receive the funds in late 2024 or early 2025. Page 5 of 15 5 Next Milestone: Proceeding with design and implementation is dependent on receiving the additional funds. Public Art Camp Parks Sign (PA0121) This project provides for the restoration and relocation of the historic Camp Parks entrance sign from its current location at 201 Dougherty Road to the new entrance at Camp Parks Boulevard and Dougherty Road. The rehabilitation will be in accordance with standards and guidelines of the U.S. Department of the Interior National Park Service. Status: Awaiting Approval of Permit Plans and Specifications from the U.S. Army. Next Milestone: Early 2024 - Construction Bid Opening. Construction is expected to begin in mid- 2024. Downtown Dublin (PA0123) This project provides for public art commissions in Downtown Dublin, including the development of a guide for public art in that area. Status: The planning phase is currently underway with a comprehensive review of existing Downtown Dublin planning documents and the Public Art Master Plan, and consideration of an art project at the northwest corner of Village Parkway and Dublin Boulevard (Village Art Project). Next Milestone: Early 2024 - Issue a Call -for -Artists for the Village Art Project. Spring 2024 - Continue planning for future Downtown Dublin Public Art Projects. Heritage Park (PA0222) This project includes a monument piece at the corner of Donlon Way and Dublin Boulevard, as well as a series of six mini -sculptures (Artistic Park Features) located throughout the park. Status: Monument Art at the corner of Donlon Way and Dublin Boulevard was dedicated on October 7, 2023. Next Milestone: Installation of Artistic Park Features is scheduled for completion by the end of the fiscal year. Parks Alamo Creek Park - Fence Replacement (PK0122) This project provides for the design and construction of replacement fencing at Alamo Creek Park and replacement and repair of fencing within the Dougherty Road Landscape and Lighting District No. 1986-1. Most of the existing tubular steel fencing has reached the end of its service life and needs to be replaced or repaired. Status: Design is anticipated to be completed in 2024. Next Milestone: Fall 2024 - Construction Bid Opening. Construction is expected to begin in late 2024. Page 6of15 6 Don Biddle Community Park (PK01151 This project provides for the design and construction of a 30-acre community park in the Boulevard Development within the Dublin Crossing Specific Plan area. The park is located between Dublin Boulevard, Scarlett Drive, Horizon Parkway, and Columbus Street and will be built by the Boulevard Developer. Status:The park was opened in September 2022 and is anticipated to be completed in 2024. Next Milestone: Completion of project at conform points along Iron Horse Regional Trail, Scarlett Drive, and Dublin Boulevard is anticipated in mid -to -late 2024. Park completion is coordinated with developer -built street improvements and construction of the Iron Horse Trail Bridge over Dublin Boulevard. Downtown Dublin Town Square Park (PK0221) This project provides for the planning of a new Town Square in accordance with the main principles of the Downtown Dublin Preferred Vision. The Town Square is a one -acre park and plaza that will serve as Downtown Dublin's gathering place, which may include a market promenade, outdoor dining, and event space. Status: With the most recent approval of the Downtown Dublin Specific Plan amendments, the project applicant is expected to apply for Planning permits to construct the Downtown Dublin Preferred Vision in late Spring to early Summer 2024. NextMilestone:Work with the property owner/developer to begin the planning and design during the development application review process. Fallon Sports Park - Phase 3 (PK01191 Phase 3 provides for the design and construction of the remaining 14 acres of Fallon Sports Park, which includes a cricket field, two ballfields, sand volleyball courts, multi -sport batting cages, playground, landscaping, and picnic and seating areas. Status:The park was opened in October 2022. Cricket field fencing and netting was completed in July 2023. Final construction will be complete in early 2024. Next Milestone: Acceptance of the improvements in spring 2024. Iron Horse Nature Park and Open Space (PK04221 This project provides for the planning, design, and construction of 12.13 acres of a nature park and open space adjacent to the Iron Horse Regional Trail, from the Dublin/San Ramon City limit to the confluence of Alamo and South San Ramon Creeks, that may be developed in partnership with Zone 7 Water Agency. The park will be designed in accordance with the Iron Horse Nature Park and Open Space Master Plan. Status: Construction of the first phase of the improvements has been awarded and field work will begin in spring 2024. Start of construction is scheduled to comply with resource agency permitting for work within the stream and wetland areas. Next Milestone: Phase 1 construction is anticipated to be completed by the end of 2024. Page 7 of 15 7 lordan Ranch Neighborhood Square (PK0322) This project provides for the planning, design, and construction of a 2.0-acre neighborhood square in the Jordan Ranch Development. The square will be designed in accordance with the Neighborhood Square Standards contained in the Parks and Recreation Master Plan. Status:Design is anticipated to be completed in early 2024. Next Milestone: Spring 2024 - Construction Bid Opening. Construction is expected to begin in summer 2024. Kolb Park Renovation (PK0224) This project will provide for the planning, design, and construction to renovate the 4.86-acre Kolb Park. The improvements will be consistent with the Parks and Recreation Master Plan and may include the replacement of the restroom building, play equipment, site furnishings, picnic areas, drinking fountains, tot -lot fencing, parcourse equipment stations, signage, refresh the shade structure, pavers and pathways, and landscaping. Status:This project has not started. Next Milestone: Planning and design to begin in 2024. The conceptual design is anticipated to be presented to the City Council for consideration in 2025. Parks Playground Replacement (PK0124) This project provides for the planning, design, and construction of the replacement of playground equipment at various parks. Based on the results of annual inspections and regular maintenance records, all City parks will be evaluated for the need to replace play equipment at the end of its useful life. The first replacements will be at Emerald Glen Park and Ted Fairfield Park. Status:This project has not started. Next Milestone: Planning and design to begin in 2024. The conceptual design is anticipated to be presented to the City Council for consideration in 2025. Persimmon Drive Pedestrian Path Rehabilitation (PK0123) This project will provide for removal and replacement of approximately 1,250 linear feet of asphalt pathway along Persimmon Drive between Gleason Drive and Central Parkway. The asphalt concrete surface has experienced distress due to soil expansion, the encroachment of tree roots, and some slope creep along the adjacent Tassajara Creek bank. Status:Design will be completed in 2024 and is being included with the Annual Street Resurfacing Project. Next Milestone: Spring 2024 - Construction Bid Opening. Construction is expected to begin in summer 2024. Restrooms Replacement (PK0321) This project provides for the planning, design, and construction to replace the existing restrooms at Alamo Creek Park and Mape Memorial Park. To bring them up to current accessibility standards Page 8of15 8 and codes, the restrooms will be demolished and replaced with pre-engineered restroom buildings. Status:Design is currently underway. Next Milestone: Summer 2024 - Construction Bid Opening. Construction is expected to begin in late 2024. Wallis Ranch Community Park (PK0421) This project provides for the planning, design, and construction of Wallis Ranch Community Park, which consists of three separate parcels totaling 8.85 acres. The park amenities include play areas, picnic facilities, turf area, lighted tennis courts, pickle ball courts, basketball facilities, natural area, restrooms, pathways, lighting, dog park, irrigation, and landscaping. Status: Construction began in October 2023. Next Milestone: Construction is anticipated to be substantially complete in late 2024 with a park opening in 2025. Streets Amador Plaza Road Bicycle and Pedestrian Improvements (ST08151 This project provides for the design, construction, and acquisition of the right-of-way for an exclusive southbound right turn lane on Amador Plaza Road at Dublin Boulevard. Status:Design is currently at 90%. Next Milestone: Completion is dependent on timing of the adjacent development. Annual Street Resurfacing (ST01171 This project provides for the design and construction of a variety of pavement resurfacing treatments, from slurry seal to major rehabilitation and reconstruction of streets and resurfacing of bridge decks. This year's project will include a slurry seal, cape seal, and an overlay project. A cape seal is a multi -layered and phased pavement preservation treatment where during the first phase, aggregate is spread over an existing road that has been coated with an asphalt binder. In the next phase, a slurry seal is applied to provide a smooth surface. The general area of the cape seal will be on Dublin Boulevard between Hansen Drive and the western terminus. Slurry seal is planned for the Dublin Ranch and Terracina neighborhoods. An asphalt overlay is planned for John Monego Court and Dublin Boulevard, from Hacienda Drive to Myrtle/Toyota Drive. Status: The 2023 slurry seal project is in the construction closeout phase and the 2024 resurfacing projects are currently in design. Next Milestone: The 2023 slurry seal will be accepted in the next month. The 2024 projects are anticipated for mid-2024 construction bid openings. Construction is expected to begin by summer 2024. Page 9of15 9 City Entrance Monument Signs (ST0319) This project provides for the design and construction to install a gateway sign in the Downtown, and City entrance monument signs at the Village Parkway median at Kimball Avenue, the San Ramon Road median at Alcosta Boulevard, Schaefer Ranch Road at Dublin Boulevard, and Tassajara Road north of Fallon Road. Status:The Downtown gateway sign is complete. Design of the monument signs for Village Parkway and Tassajara Road are being integrated into the Village Parkway Reconstruction Project and Tassajara Road Realignment and Widening Project. Next Milestone: The Village Parkway and Tassajara Road monument signs will be designed in 2024. Citywide Bicycle and Pedestrian Improvements (ST0517) This project includes planning, design, and construction of improvements to various pedestrian and bicycle facilities throughout the City, including pedestrian/bicycle bridges. Status: Design of Safe Routes to School Improvements, consisting of curb ramp upgrades, crosswalk improvements, traffic signal modifications, and rectangular rapid flashing beacons (RRFB)at Amador Valley Boulevard and Burton Street, Central Parkway and Aspen Street, Central Parkway and Hibernia Drive, and Antone Way and Grafton Street, are at 65%. The plans include a new mid -block crosswalk on Regional Street in Downtown. Next Milestone: Spring 2024 - Construction Bid Opening. Construction is expected to begin summer 2024. Citywide Signal Communications Upgrade (ST0713) This project provides for the continued upgrades of the traffic signal communications system and includes the replacement of signal controllers, conflict monitors, and battery backup units, as well as managing ongoing signal operations of coordinated corridors. The project will also provide for the installation of new conduits, removing the existing copper communication cables and installing new fiber optic cables throughout the City. Status: Phase 1 construction, which installed conduit on Dublin Boulevard from San Ramon Road to the Civic Center, is complete. Design for Phase 2, which includes pulling fiber optic communications cables through the Phase 1 conduit and connecting them in the newly renovated server area of the DAC, will begin when the DAC is substantially complete. Next Milestone: Phase 2 design will begin in mid-2024. Citywide Storm Drain Improvements (ST01241 This project will provide for the planning, design, maintenance, and construction of various improvements to citywide storm drainage facilities that are not located within public street rights - of -way, such as v-ditches and culverts on City -owned properties or public easements, such as the large G-3 box culvert running parallel to I-580. Status:The project has not started. Next Milestone: The first phase of the project will include a storm drainage master plan and/or Page 10 of 15 10 condition assessment report which is anticipated to start in 2024. Downtown Dublin Street Grid Network (ST02211 This project provides for the planning of a new Street Grid Network in accordance with the main principles of the Downtown Dublin Preferred Vision. The Street Grid Network will introduce new streets that will break down the large block format into smaller, walkable blocks between 350 to 450 feet per side. Status: Currently Staff is working on the North project with Hines to coordinate the planned public streets. Next Milestone:A traffic analysis to determine Downtown Dublin improvements based on the recent amendment to the Downtown Dublin Specific Plan land use is anticipated in early 2024. Dublin Boulevard Extension - Fallon Road to North Canyons Parkway (ST0216) This project provides for the environmental review, preliminary engineering, design, and construction of the 1.5-mile extension of Dublin Boulevard from Fallon Road to North Canyons Parkway in Livermore. The extension is planned to have four to six travel lanes, bike lanes, a Class 1 bike/multi-use path, sidewalk, curb and gutter, traffic signals, street lighting, landscaped medians, bus stops, and utilities. Status: Alameda County Transportation Commission and their consultant team started the final design process. City Staff continues to work on right-of-way and mitigation land acquisitions. Next Milestone: 95% design plans are anticipated to be completed in summer 2024. Dublin Boulevard Pavement Rehabilitation (ST0120) This project provides for pavement rehabilitation of Dublin Boulevard between Scarlett Drive and Hacienda Drive. Rehabilitation included removal and replacement of existing failed pavement, resurfacing with new asphalt concrete, and installation of new pavement striping. The project also included installation of new curb ramps or upgrade of existing curb ramps to comply with ADA standards. Status: The project was accepted as complete by the City Council in December 2023. Next Milestone: The close-out package will be submitted to Caltrans Local Assistance for reimbursement of One Bay Area Grant (OBAG) federal funds. Dublin Ranch Streetlight Improvements (ST0417) This project provides for the repainting and LED conversion of decorative streetlight poles in the Dublin Ranch streetlight assessment district. Converting existing Dublin Ranch streetlights to energy efficient LEDs was completed as part of the Citywide Energy Improvements (GI0121) project. Status: Conversion of 1,625 streetlights into energy -efficient LEDs is complete. Next Milestone: Planning and design for the pole -painting portion of the project is anticipated to start in 2025. Page 11 of 15 11 Golden Gate Drive Intersection Improvements at Dublin Blvd. and St. Patrick Wav (ST04231 This project provides for the planning, design, and construction of improvements at the intersections of Dublin Boulevard at Golden Gate Drive and St. Patrick Way at Golden Gate Drive. The project may also include pavement markings, necessary utility, pavement, curb, gutter, ADA curb ramps, sidewalk modifications or adjustments, and required green stormwater infrastructure. Status:The feasibility study, conceptual planning, and 35% plans were completed in December 2023. Staff has applied for a $3M Safe Routes to BART grant for this project. Next Milestone:The 65% design is anticipated to be completed in mid-2024. Green Stormwater Infrastructure (ST01211 This project provides for the planning, design, and construction of various citywide projects that will improve water quality and provide other environmental benefits in accordance with the Green Stormwater Infrastructure (GSI) Plan. Projects include stormwater full trash capture device installation throughout the City, and construction of GSI along the Iron Horse Regional Trail corridor, south of Amador Valley Boulevard, GSI planning, and planning for the installation of trash capture devices. Status:The design of the portion of the project along the Iron Horse Regional Trail, south of Amador Valley Boulevard, is nearly complete and permit applications have been submitted to the various agencies and utilities impacted. Next Milestone: Early 2024 - Construction Bid Opening. Construction is expected to begin by mid- 2024. Intelligent Transportation System Upgrade - Connected/Autonomous Vehicle and Safety Improvements (ST0519) This project provides for improvements to the City's transportation system using emerging technologies, such as support for connected and autonomous vehicles, and is a collaborative effort between the City of Dublin, Livermore Amador Valley Transportation Authority (LAVTA), and the Metropolitan Transportation Commission (MTC). Status: Phase 1, which included LAVTA testing a shared autonomous vehicle (SAV) south of Dublin Boulevard near the Dublin/Pleasanton BART Station, is complete. Phase 2 was to expand SAV service north of Dublin Boulevard. LAVTA began the Phase 2 design process and completed the Update of User Needs analysis, System Engineering Management Plan, Concept of Operations document, and the System Engineering requirements. Unfortunately, LAVTA was unable to find a SAV vendor to meet Phase 2 project requirements and goals. LAVTA, MTC, and Alameda CTC have agreed to discontinue the project. Next Milestone: Project close-out activities in early 2024. Iron Horse Trail Bridge at Dublin Boulevard (ST0118) This project provides for the planning, design, and construction of the Iron Horse Trail bridge for bicycles and pedestrians to cross over Dublin Boulevard. The project will construct a 230-foot Page 12 of 15 12 clear span truss arch bridge, approach ramps, and an entry point at the corner of Dublin Boulevard, Scarlett Drive, and Don Biddle Community Park. Status: Construction is underway. The bridge was lifted into place in October 2023 and the concrete bridge deck was placed in December 2023. NextMilestone:With construction of the approach ramps, electrical installation, and coordination with adjacent park improvements, the project is anticipated to be complete in mid-2024. San Ramon Road Landscape Renovation (ST02181 This project provides for planning, design, and construction to renovate the landscaping along San Ramon Road between Silvergate Drive and Alcosta Boulevard. Proposed renovation includes the removal of failing plants, soil amendment, and installation of new plants, with an emphasis on Bay Friendly and water -conserving plant species. Status: This project has not started. Next Milestone: Design is anticipated to begin in 2024. San Ramon Road Trail Lighting (ST0514) This project provides for the design and construction of improvements to the trail light fixtures between Silvergate Drive and Alcosta Boulevard. Status:The trail lighting LED conversion is complete. Next Milestone:The remaining pole painting will be completed in conjunction with the Dublin Ranch Street Light Pole Improvements Project (ST0417). St. Patrick Way Extension (ST02221 This project provides for the design and construction of the final segment of St. Patrick Way from west of Golden Gate Drive to Regional Street. Status:The roadway is near completion and is providing access to the residents of the Avalon Bay development. Next Milestone:St. Patrick Way will be complete and open to the public by the end of 2024. Tassaiara Road Improvements - North Dublin Ranch Drive to Ouarry Lane School (ST01191 This project provides for design and construction to complete the street improvements on Tassajara Road, from North Dublin Ranch Drive to Quarry Lane School, to a four -lane arterial standard with bike lanes, sidewalks, landscaped median, stormwater treatment areas, and other associated street improvements. Status: The design in nearing completion and Staff is currently negotiating the acquisition of right- of-way. Next Milestone: PG&E is currently working to relocate power infrastructure in conflict with the widening improvements. PG&E anticipates relocation to start in 2024. Page 13 of 15 13 Tassaiara Road Realignment and Widening - Fallon Road to North City Limit (ST0116) The project provides for the planning and preliminary engineering to define a new roadway alignment, design cross-section, right-of-way, and environmental clearance for realigned Tassajara Road from Fallon Road to the northern city limit, which will be coordinated with Contra Costa County. The improvements will include a four -lane road with bike lanes, sidewalks, landscaped median, stormwater treatment areas, and other associated street improvements. Status: Contra Costa County Public Works is the project lead and is currently working on the detailed design of the project. Next Milestone:The 65% design plans are anticipated to be complete in mid-2024. Traffic Signal and Roadway Safety Improvements (ST0123) This project will provide for feasibility, design, and construction and modification of traffic signals and roadway safety improvements at locations prioritized and recommended by Local Roadway Safety Plan (LRSP). Improvements include upgrading the signal equipment such as traffic signal poles/mast arms, vehicle and pedestrian signal heads, signal controllers, cabinet upgrades, streetlighting/safety lighting improvements, signal phasing and timing changes, signing, and striping improvements, and other alternatives. Status: LRSP-recommended retroreflective borders on traffic signal head back plates is being combined with the Traffic Signal Re-Lamping project (ST0223). Next Milestone: See Traffic Signal Re-Lamping (ST0223). Traffic Signal Re-Lamping (ST02231 This project provides for the replacement of the traffic signal and pedestrian signal LED lamps at approximately 78 signalized intersections. Status: This project has not started. Next Milestone: Design will begin in 2024. Construction is expected to begin in late 2024. Village Parkway Reconstruction (ST0323) This project provides for the planning, design, and construction of the replacement of the existing streetscape elements on Village Parkway between Amador Valley Boulevard and the northern city limit (approximately 6,000 linear feet). The project will transform the segment of Village Parkway between Amador Valley Boulevard and Kimball Avenue to a pedestrian and bicycle friendly roadway, which will incorporate complete streets elements such as median islands, bulb -outs, decorative or high visibility crosswalks, and street furniture. Page 14 of 15 14 Status: The preliminary design is nearly complete, and the environmental evaluation of the project continues. Coordination with stakeholders, such as Dublin High School and LAVTA, continues. Staff continues to look for grants and other project funding opportunities. Additional funding from the State Transportation Improvement Program (STIP) is anticipated to be awarded in spring 2024 by the California Transportation Commission. Next Milestone: Design will begin in early 2024. STRATEGIC PLAN INITIATIVE: None. NOTICING REQUIREMENTS/PUBLIC OUTREACH: The City Council Agenda was posted. ATTACHMENTS: 1) Five -Year Capital Improvement Program 2022-2027 Update Page 15 of 15 15 Attachment I City of Dublin CALIFORNIA FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM 2022-2027 UPDATE City of Dublin CALIFORNIA Dublin bitting All-AMNICa city 2011 Proposed Five -Year Capital Improvement Program 2022-2027 Update May 2023 Melissa Hernandez, Mayor Michael McCorriston, Vice Mayor Jean Josey, Council Member Sherry Hu, Council Member Kashef Qaadri, Council Member Submitted by: Linda Smith, City Manager Colleen Tribby, Assistant City Manager 17 CONTENTS CONTENTS SUMMARY SCHEDULES HIGHLIGHTS SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM — GENERAL IMPROVEMENTS 3 SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM — PUBLIC ART 4 SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM — PARKS 5 SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM — STREETS 6 GENERAL IMPROVEMENTS 8 SUMMARY OF PROJECTS PROJECTED TO BE COMPLETED IN FISCAL YEAR 2022-2023 8 LOCATION MAP 9 AUDIO VISUAL SYSTEM UPGRADE 10 CITYWIDE ENERGY IMPROVEMENTS 11 CIVIC CENTER ELEVATOR MODERNIZATION 12 CIVIC CENTER EXTERIOR SEALING & PAINTING 13 CULTURAL ARTS CENTER 15 DUBLIN STANDARD PLANS & DETAILS UPDATE 16 ELECTRIC VEHICLE (EV) CHARGING STATIONS 17 EXTERIOR PAINTING AT VARIOUS CITY FACILITIES 18 FINANCIAL SYSTEM REPLACEMENT 19 IT INFRASTRUCTURE IMPROVEMENT 20 LIBRARY TENANT IMPROVEMENTS 21 MARQUEE SIGNS 22 MUNICIPAL FIBER 23 Contents City of Dublin Capital Improvement Program 2022-2027 Update i 18 RESILIENCY AND DISASTER PREPAREDNESS IMPROVEMENTS 24 ROOF REPLACEMENT AT VARIOUS CITY FACILITIES 25 SITUATIONAL AWARENESS CAMERA PROGRAM 26 PUBLIC ART 27 SUMMARY OF PROJECTS PROJECTED TO BE COMPLETED IN FISCAL YEAR 2022-2023 27 LOCATION MAP 28 CAMP PARKS SIGN 29 DOWNTOWN DUBLIN 30 HERITAGE PARK 31 PARKS 32 SUMMARY OF PROJECTS PROJECTED TO BE COMPLETED IN FISCAL YEAR 2022-2023 32 LOCATION MAP 33 ALAMO CREEK PARK AND ASSESSMENT DISTRICT— FENCE REPLACEMENT 34 DON BIDDLE COMMUNITY PARK 35 DOWNTOWN DUBLIN TOWN SQUARE PARK 36 DUBLIN SPORTS GROUNDS REHABILITATION 37 FALLON SPORTS PARK — PHASE 3 38 IRON HORSE NATURE PARK AND OPEN SPACE 39 JORDAN RANCH NEIGHBORHOOD SQUARE 41 KOLB PARK RENOVATION 42 PARKS PLAYGROUND REPLACEMENT 43 PERSIMMON DRIVE PEDESTRIAN PATH REHABILITATION 44 RESTROOMS REPLACEMENT 45 SUNDAY SCHOOL BARN IMPROVEMENTS 46 WALLIS RANCH COMMUNITY PARK 47 STREETS 48 Contents City of Dublin Capital Improvement Program 2022-2027 Update ii 19 SUMMARY OF PROJECTS PROJECTED TO BE COMPLETED IN FISCAL YEAR 2022-2023 48 LOCATION MAP 49 AMADOR PLAZA ROAD BICYCLE AND PEDESTRIAN IMPROVEMENTS 50 ANNUAL STREET RESURFACING 51 CITY ENTRANCE MONUMENT SIGNS 53 CITYWIDE BICYCLE AND PEDESTRIAN IMPROVEMENTS 54 CITYWIDE SIGNAL COMMUNICATIONS UPGRADE 56 CITYWIDE STORM DRAIN IMPROVEMENTS 58 DOWNTOWN DUBLIN STREET GRID NETWORK 59 DUBLIN BOULEVARD EXTENSION — FALLON ROAD TO NORTH CANYONS PARKWAY 60 DUBLIN BOULEVARD PAVEMENT REHABILITATION 62 DUBLIN RANCH STREETLIGHT IMPROVEMENTS 63 GOLDEN GATE DRIVE INTERSECTION IMPROVEMENTS - DUBLIN BLVD AND ST. PATRICK WAY 64 GREEN STORMWATER INFRASTRUCTURE 65 INTELLIGENT TRANSPORTATION SYSTEM UPGRADE - CONNECTED/AUTONOMOUS VEHICLE AND SAFETY IMPROVEMENTS 67 IRON HORSE TRAIL BRIDGE AT DUBLIN BOULEVARD 69 SAN RAMON ROAD LANDSCAPE RENOVATION 71 SAN RAMON ROAD TRAIL LIGHTING 72 ST. PATRICK WAY EXTENSION 73 TASSAJARA ROAD IMPROVEMENTS - NORTH DUBLIN RANCH DRIVE TO QUARRY LANE SCHOOL 74 TASSAJARA ROAD REALIGNMENT AND WIDENING - FALLON ROAD TO NORTH CITY LIMIT 76 TRAFFIC SIGNAL AND ROADWAY SAFETY IMPROVEMENTS 78 TRAFFIC SIGNAL RE-LAMPING 79 VILLAGE PARKWAY RECONSTRUCTION 80 FUTURE PROJECTS 81 LOCATION MAP 82 Contents City of Dublin Capital Improvement Program 2022-2027 Update ii 20 CROAK NEIGHBORHOOD PARK EAST 83 CROAK NEIGHBORHOOD PARK WEST 83 DUBLIN SPORTS GROUNDS — PHASE 5 RENOVATION 84 EMERALD GLEN RECREATION AND AQUATIC COMPLEX - PHASE 2 84 CITY ENTRANCE SIGNS 85 EASTERN DUBLIN TRANSPORTATION IMPACT FEE 85 WESTERN DUBLIN TRANSPORTATION IMPACT FEE 86 Contents City of Dublin Capital Improvement Program 2022-2027 Update iv 21 SUMMARY SCHEDULES HIGHLIGHTS The following schedules provide an overview of the financial information contained in the Proposed Five -Year Capital Improvement Program 2022- 2027 Update. The first summary schedule highlights expenditures by program area for all projects and identifies the financing category used for the projects. The following financial schedules provide information by major program area (General Improvements, Public Art, Parks, and Streets) as well as separate schedules listing unfunded or Future Projects. Additional details about each project are in the corresponding program area. SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM — ALL FUNDS 2022-2027 CAPITAL IMPROVEMENT PROGRAM CATEGORY PRIOR YEARS 2022-2023 2023-2024 FUTURE 2024-2025 2025-2026 2026-2027 YEARS TOTAL General Improvements Public Art Parks Streets $54,666,069 $908,126 $66,369,178 $18,623,452 TOTAL COSTS $140,566,825 Summary Schedules $32,504,973 $1,445,860 $37,591,938 $70,743,887 $2,696,840 $500,000 $3,894,115 $30,214,580 $1,705,000 $300,000 $9,462,780 $5,225,459 $142,286,658 $37,305,535 $16,693,239 $300,000 $860,000 $13,888,961 $292,410 $250,000 $8,331,461 $105,422,306 $91,865,292 $3,703,986 $4,500,000 $122,678,011 $252,450,106 $15,048,961 $8,581,461 $110,214,716 $470,697,395 City of Dublin Capital Improvement Program 2022-2027 Update Page 1 22 SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM — FINANCINC SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM — ALL FUNDS 2022-2027 CAPITAL IMPROVEMENT PROGRAM FINANCING PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTAL General Fund Special Revenue Special Revenue Funds- Assmt. Dist. Public Art Fund Traffic Impact Fees Public Facility Fees Internal Service Funds Energy Improve. Lease Bond Dublin Crossing Fund Other Developer Built Unidentified $26,767,824 $16,536,632 $348,307 $908,126 $2,100,687 $53,370,408 $7,602,952 $11,731,890 $18,199,999 $34,771,304 $21,645,824 $1,132,210 $1,445,860 $24,284,258 $25,823,826 $3,457,952 $8,890,725 $800,000 $3,435,000 $16,599,699 $17,929,893 $3,406,689 $42,000 $500,000 $613,880 $2,279,875 $170,000 $12,363,198 $3,898,670 $8,740,000 $157,500 $3,253,149 $3,208,961 $2,873,961 $42,000 $300,000 $816,320 $4,514,600 $1,650,000 $2,218,500 $300,000 $250,000 $600,000 $292,410 $4,500,000 $2,200,000 $5,300,000 $105,422,306 $92,557,601 $50,925,216 $1,564,517 $3,703,986 $27,815,145 $93,488,709 $13,480,904 $20,622,615 $18,999,999 $15,798,198 $16,599,699 $115,140,806 TOTAL FINANCING $140,566,825 $142,286,658 $37,305,535 $16,693,239 $15,048,961 $8,581,461 $110,214,716 $470,697,395 Summary Schedules City of Dublin Capital Improvement Program 2022-2027 Update Page 2 23 SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM - GENERAL IMPROVEMENTS 2022-2027 CAPITAL IMPROVEMENT PROGRAM RO ECT BER & DESCRIPTION PRIOR 2023-2024 FUTURE YEARS 2022-2023 BUDGET 2024-2025 2025-2026 2026-2027 YEARS TOT GI0421 G10121 GI0119 GI0001 GI0002 GI0122 GI0120 GI0123 GI0219 GI0223 GI0319 GI0117 GI0521 GI0509 GI0124 GI0116 GI0323 GI0221 GI0423 GI0523 Audio Visual System Upgrade Citywide Energy Improvements Civic Center HVAC and Roof Replacement Civic Center Elevator Modernization Civic Center Exterior Sealing & Painting Civic Center Rehabilitation Cultural Arts Center Dublin Standard Plans & Details Update Electric Vehicle (EV) Charging Stations Exterior Painting at Various City Facilities Financial System Replacement IT Infrastructure Improvement Library Tenant Improvements Maintenance Yard Facility Improvements Marquee Signs Public Safety Complex - Police Services Build. Municipal Fiber Resiliency and Disaster Preparedness Imp. Roof Replacement at Various City Facilities Situational Awareness Camera Pro am TOTAL COSTS $1,117 $157,923 $12,124,804 $10,801,586 $5,063,380 $111,620 $35,998 $1,307,892 $1,129,707 $13,267,328 $142,500 $17,907 $212,093 $665,000 $1,323,202 $1,176,799 $989,323 $254,277 $1,835,665 $9,925,644 $55,089 $24,052,798 $87,201 $140,000 $2,189 $1,100,000 $605,000 $585,000 $314,000 $30,000 $687,840 $120,000 $1,000,000 $495,000 100 $900,000 $600,000 $205,000 $54,666,069 $32,504,973 $2,696,840 $1,705,000 $292,410 $473,040 $22,956,390 $5,175,000 $900,000 $600,000 $2,236,730 $14,397,035 $142,500 $522,410 $785,000 $2,500,001 $1,243,600 $2,835,665 $9,980,733 $495,000 $24,139,999 $140,000 $1,102,189 $655,000 $585,000 $292,410 $91,865,292 FINANCING 1001 General Fund 1101 General Fund Designation 2207 Transportation for Clean Air 2705 Street Light District East Dublin 1999-1 4100 Public Facility Fees 4401 Dublin Crossing Development Fee 6205 Internal Service Fund - Facilities Replacement 6305 Internal Service Fund - Equipment 6605 IT Fund 7102 Enert4 Im.rove. Lease Bond $732,369 $4,738,781 $15,269,305 $8,612,749 $18,000 $332,053 $474,302 $1,129,707 $6,505,158 $17,999,999 $5,587,366 $2,903,638 $655,000 $1,228,380 $361,620 $11,731,890 $8,890,725 $1,809,000 $687,840 $30,000 $170,000 $205,000 $1,500,000 $292,410 $7,572,560 $24,774,894 $18,000 $836,355 $7,634,865 $17,999,999 $10,161,004 $655,000 $1,590,000 $20,622,615 TOTAL FINANCING $54,666,069 $32,504,973 $2,696,840 $1,705,000 $292,410 $91,865,292 Summary Schedules City of Dublin Capital Improvement Program 2022-2027 Update Page 3 24 SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM - PUBLIC ART 2022-2027 CAPITAL IMPROVEMENT PROGRAM PRO ECT -UMBER & DESCRIPTION PRIOR 2023-2024 FUTURE YEAR 2022-2023 BUDGET 2024-2025 2025-2026 2026-2027 YEARS TOTAL PA0121 PA0217 PA0123 PA0222 PA0218 PA0419 PA0418 Camp Parks Sign Don Biddle Community Park Downtown Dublin Heritage Park Public Art - Butterfly Knoll Park Public Art - Dublin Sports Grounds Public Art - Sean Diamond Park $17,134 $414,635 $483,316 $266,114 $150,000 $68,150 $526,550 $13,456 $4,104 $350,264 $6,263 $44,487 $9,513 $500,000 $300,000 $300,000 $250,000 $500,450 $680,749 $1,500,000 $594,700 $17,560 $356,527 $54,000 TOTAL COSTS $908,126 $1,445,860 $500,000 $300,000 $300,000 $250,000 $3,703,986 FINANCING 2801 Public Art Fund $908,126 $1,445,860 $500,000 $300,000 $300,000 $250,000 $3,703,986 TOTAL FINANCING $908,126 $1,445,860 $500,000 $300,000 $300,000 $250,000 $3,703,986 Summary Schedules City of Dublin Capital Improvement Program 2022-2027 Update Page 4 25 SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM - PARKS 2022-2027 CAPITAL IMPROVEMENT PROGRAM PRO ECT UMBER & DESCRIPTIO PRIOR YEARS 2023-2024 FUTURE 2022-2023 BUDGET 2024-2025 2025-2026 2026-2027 YEARS TOTAL PK0122 Alamo Creek Park and Assessment District - Fence R PK0115 Don Biddle Community Park PK0221 Downtown Dublin Town Square Park PK0215 Dublin Heritage Park Cemetery Improvements PK0002 Dublin Sports Grounds Rehabilitation PK0105 Emerald Glen Recreation & Aquatic Complex - Phase PK0119 Fallon Sports Park - Phase 3 PK0518 Imagine Playground at Dublin Sports Grounds PK0422 Iron Horse Nature Park and Open Space PK0322 Jordan Ranch Neighborhood Square PK0224 Kolb Park Renovation PK0124 Parks Playground Replacement PK0123 Persimmon Drive Pedestrian Path Rehabilitation PK0321 Restrooms Replacement PK0001 Sunday School Barn Improvements PK0421 Wallis Ranch Communit Park $12,932 $837,068 $6,222,890 $18,601,115 $102,205 $1,582,252 $21,748 $44,912,827 $7,928,102 $5,050,580 $182,411 $17,928 $218,123 $2,669,898 $48,820 $3,426,889 $1,752,244 $195,000 $280 $999,720 $458,976 $8,719,108 $4,680 $1,301,100 $1,028,775 $450,000 $1,109,560 $4,680 $150,000 $600,000 $6,733,100 $2,450,000 $125,000 $260,000 $4,500,000 $850,000 $24,824,005 $4,611,565 $1,604,000 $750,000 $45,130,950 $10,598,000 $5,099,400 $11,643,500 $2,798,947 $2,900,000 $1,109,560 $195,000 $1,000,000 $385,000 $9,178,084 TOTAL COSTS $66,369,178 $37,591,938 $3,894,115 $9,462,780 $860,000 $4,500,000 $122,678,011 FINANCING 1001 General Fund 1101 General Fund Designation 2207 Transportation for Clean Air 2212 Vehicle Registration Fee (ACTC) 2302 Measure D 2403 State Park Grant 2703 Landscape District Dougherty 1986-1 2704 Landscape District Santa Rita 1997-1 4100 Public Facility Fees 6205 Internal Service Fund - Facilities Replacement 6605 IT Fund 9998 Unidentified 9999 Develo.er Built $3,513 $1,597,512 $9,648,459 $788,941 $8,000 $14,894 $35,106 $51,180 $1,358,000 $2,294,000 $9,699 $390,301 $195,000 $55,240,701 $19,318,668 $42,732 $107,268 $12,857,142 $1,614,240 $2,279,875 $2,579,680 $260,000 $4,514,600 $150,000 $600,000 $2,218,500 $6,054,945 $10,437,400 $8,000 $50,000 $51,180 $3,652,000 $400,000 $195,000 $4,500,000 $85,853,844 $750,000 $150,000 $2,218,500 $12,857,142 TOTAL FINANCING $66,369,178 $37,591,938 $3,894,115 $9,462,780 $860,000 $4,500,000 $122,678,011 Summary Schedules City of Dublin Capital Improvement Program 2022-2027 Update Page 5 26 SUMMARY 2022-2027 CAPITAL IMPROVEMENT PROGRAM - STREETS 2022-2027 CAPITAL IMPROVEMENT PROGRAM PRO ECT NUMBER & DESCRIPTION PRIOR 2023-2024 FUTURE YEARS 2022-2023 BUDGET 2024-2025 2025-2026 2026-2027 YEARS TOTAL ST0815 Amador Plaza Road Bicycle and Pedestrian Imp. $553,151 $860,498 ST0117 Annual Street Resurfacing $9,432,823 $3,797,834 ST0319 City Entrance Monument Signs $485,000 ST0517 Citywide Bicycle and Pedestrian Improvements $2,363,921 $1,638,223 ST0713 Citywide Signal Communications Upgrade $1,385,067 $2,799,579 ST0124 Citywide Storm Drain Improvements ST0221 Downtown Dublin Street Grid Network $13,147 $196,893 Dublin Boulevard Extension - Fallon Road to North ST0216 Canyons Parkway $1,215,309 $16,101,578 ST0120 Dublin Boulevard Pavement Rehabilitation $737,000 ST0417 Dublin Ranch Street Light Improvements $6,555 $72,607 Golden Gate Drive Intersection Improvements at ST0423 Dublin Boulevard and St. Patrick Way $21,440 ST0121 Green Stormwater Infrastructure $301 $2,153,074 Intelligent Transportation System Upgrade - ST0519 Connected/Autonomous Vehicle and Safety $85,757 $714,125 ST0118 Iron Horse Trail Bridge at Dublin Boulevard $2,496,956 $11,507,483 ST0122 Local Roadway Safety Plan $43,301 $94,679 ST0218 San Ramon Road Landscape Renovation $405 $238,660 ST0514 San Ramon Road Trail Lighting $165,465 $7,996 ST0222 St. Patrick Way Extension $3,742,556 Tassajara Road Improvements - North Dublin Ranch ST0119 Drive to Quarry Lane School $491,643 $12,508,357 Tassajara Road Realignment and Widening - Fallon ST0116 Road to North City Limit $369,651 $12,407,765 ST0123 Traffic Signal and Roadway Safety Improvements $60,000 ST0223 Traffic Signal Re-Lamping $298,540 ST0323 Villa•e Parkwa Reconstruction $300,000 $2,299,881 $653,228 $235,040 $30,000 $8,990 $24,652,333 $12,000 $113,880 $1,135,688 $500,000 $110,000 $213,540 $250,000 $2,299,881 $2,573,961 $2,573,961 $733,228 $275,040 $30,000 $157,500 $8,990 $42,000 $816,320 $135,000 $1,050,000 $11,150,000 $5,600,000 $21,200,000 $1,413,649 $22,978,341 $485,000 $5,388,600 $4,694,726 $217,500 $21,428,020 $84,222,306 $126,191,526 $737,000 $133,162 $951,640 $3,289,063 $799,882 $14,004,439 $137,980 $239,065 $173,461 $3,742,556 $13,500,000 $12,777,416 $170,000 $647,080 $18,350,000 TOTAL COSTS $18,623,452 $70,743,887 $30,214,580 $5,225,459 $13,888,961 $8,331,461 $105,422,306 $252,450,106 Summary Schedules City of Dublin Capital Improvement Program 2022-2027 Update Page 6 27 2022-2027 CAPITAL IMPROVEMENT PROGRAM FINANCING PRIOR 2023-2024 FUTURE YEARS 2022-2023 BUDGET 2024-2025 2025-2026 2026-2027 YEARS TOTAL 1001 General Fund 1101 General Fund Designation 2201 State Gas Tax 2202 Federal Transportation Grant 2203 Transportation Development Act 2204 Measure B Sales Tax - Local Streets Fund (ACTC) Measure B Sales Tax - Bike & Pedestrian Fund 2205 (ACTC) 2206 State Transportation Improvement 2207 Transportation for Clean Air 2212 Vehicle Registration Fee (ACTC) 2214 Measure BB Sales Tax - Local Streets Fund (ACTC) Measure BB Sales Tax - Bike & Pedestrian Fund 2215 (ACTC) 2216 Measure B Grants 2217 Measure BB Grants 2218 Measure RR 2220 Road Maint. & Rehab Account (RMRA) 2304 Local Recycling Programs 2705 Street Light District East Dublin 1999-1 4300 Eastern Dublin Transportation Impact Fee 4303 Traffic Impact Fee - Category 3 4304 Western Dublin Transportation Impact Fee 4305 Traffic Impact Fee - Dougherty Valley 4306 Tri-Valley Transportation Development Fee 4309 Mitigation Contributions 4401 Dublin Crossing Development Fee 6305 Internal Service Fund - Equipment 9997 Other 9998 Unidentified 9999 Developer Built TOTAL FINANCING $1,034,023 $1,217,542 $80,154 $17,815,780 $3,480,408 $3,903,173 $661,000 $192,683 $17,317 $2,251,913 $955,706 $497,494 $345,406 $43,301 $28,699 $739,714 $262,705 $763,976 $961,010 $2,717,620 $1,425,980 $524,330 $493,814 $82,500 $1,551,666 $5,146,840 $121,242 $1,378,758 $1,990,072 $3,705,949 $155,640 $4,360 $6,555 $72,607 $1,001,516 $11,826,742 $27,211 $382,052 $580,429 $1,053,660 $5,464,338 $491,531 $5,511,486 $45,980 $200,000 $800,000 $89,474 $85,426 $3,435,000 $3,742,556 $7,311,372 $6,507,441 $659,460 $165,040 $1,110,000 $348,228 $1,123,961 $12,000 $500,000 $113,880 $12,363,198 $113,990 $30,000 $157,500 $1,000,000 $8,450,000 $775,920 $1,110,000 $900,000 $35,040 $930,000 $950,000 $850,000 $9,864,427 $33,853,375 $10,828,961 $661,000 $210,000 $3,207,619 $842,900 $72,000 $1,002,419 $1,925,066 $7,983,600 $348,228 $25,000 $1,739,600 $82,500 $6,698,506 $1,500,000 $1,163,961 $1,123,961 $1,123,961 $10,231,865 $160,000 $42,000 $133,162 $13,328,258 $409,263 $2,564,289 $5,464,338 $6,003,017 $45,980 $1,000,000 $174,900 $15,798,198 $2,200,000 $5,300,000 $105,422,306 $112,922,306 $3,742,556 $816,320 $18,623,452 $70,743,887 $30,214,580 $5,225,459 $13,888,961 $8,331,461 $105,422,306 $252,450,106 Summary Schedules City of Dublin Capital Improvement Program 2022-2027 Update Page 7 28 GENERAL IMPROVEMENTS SUMMARY OF PROJECTS PROJECTED TO BE COMPLETED IN FISCAL YEAR 2022-2023 Project Number Project Description Estimated Total Project Cost General Improvements GI0119 Civic Center HVAC and Roof Replacement GI0509 Maintenance Yard Facility Improvements GI0116 Public Safety Complex — Police Services Building $5,175,000 1 $9,980,733 1 $24,139,999 1 City of Dublin Capital Improvement Program 2022-2027 Update Page 8 29 LOCATION MAP GENERAL IMPROVEMENTS GIP Number CEP Name GI0421 GI0121 GI0001 GI0002 GI0114 G]OL 22 Audio Visual System Upgrade Citywide Energy Lnprovernents (Various Locations) Civic Center Elcaator Flodernietim Civic Center Exterior Sealing & Panting dvIc Center HVAC and Roof Replacement dvlr ',enter RebahlllI rrn General Improvements CIP Number CIF' Nome UI0120 610122 610219 610223 G)0314 %;i1117 Cultural Arts Center Dubin Standard Plans Details Update Electric Vehicle (EV) Charging Stations Exterior Painting at Various City Facilities Financial System Reriacmlent R Infrasmrrnrre Im9mvenxrt {Vannes I tat GIP Number LIP Name GIl521 Library Tenant Improvements C10124 Marquee Agns GI0323 Municipal Fiber GIl221 Rsilien y and Disaster Rreparetirims ]mproverner>ls (Various' mzalki s) G1U923 Roof Replacement at Various City Facllltles Slrualronal awareness Camera Pmnram'Various t crams) City of Dublin Capital Improvement Program 2022-2027 Update j Page 9 30 Number — GI042 I 7 AUDIO VISUAL SYSTEM UPGRADE IIProgram — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the planning, design, and construction of the audio visual -system upgrades in the Ambrose Hall and adjoining conference room at the Shannon Community Center, the Alamilla Springs Ballroom at the Senior Center, and the Program Room at the Dublin Library. The upgrades will include replacement of equipment to improve the service quality for rentals, meetings, and corporate events. The upgrade will also bring the audio-visual systems up to current industry standards. A request for proposals was completed in summer 2022 for the design and construction is anticipated for summer 2023. ANNUAL OPERATING IMPACT: To be determined. MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9600 — E.ui.ment TOTAL $1,117 $12,019 $10,088 $14,904 $49,912 $131,000 $254,000 $1,117 $157,923 $314,000 $23,224 $64,816 $385,000 $473,040 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 10 31 Number— GI0121 IMCITYWIDE ENERGY IMPROVEMENTS! Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the planning (Investment Grade Audit), design, and construction of various energy upgrades, efficiency improvements, lighting upgrades, energy generation, solar photovoltaic (PV) systems, and energy storage projects at facilities, parks, street rights -of -way, and other City -owned property. The project includes lighting and controls upgrades at Mape Memorial Park, Alamo Creek Park, Ted Fairfield Park, Bray Commons Park, Dolan Park, Emerald Glen Park, Fallon Sports Park, Heritage Park, and Shannon Park, as well as interior and exterior building lighting and controls upgrades at the Library, Corp Yard, Heritage Park and Museums facilities, Shannon Community Center, Fire Stations 16, 17, and 18, and at The Wave. The conversion of approximately 1,626 streetlights in the East Ranch Street Light Assessment District (1999-1) to LED is also included. There will be various mechanical, HVAC and controls upgrades at the following facilities: Library, Senior Center, Heritage Park and Museums, The Wave, Fire Stations 16, 17, and 18. Renewable, resiliency, and disaster preparedness improvements to prepare for future PG&E Public Safety Power Shutoff events and other emergency events will be provided with back-up generators at the Library, Shannon Community Center, Fire Stations 16, 17, and 18, while battery back-up or hydrogen fuel cell resiliency will be provided at 22 major street intersections throughout the city. Solar PV and EV charging will be provided at Dublin Sports Grounds and Public Safety Complex. Solar PV with battery energy storage systems will be provided at the Civic Center, The Wave, Corp Yard, and Senior Center. Solar PV will be provided at the Library, Fallon Sports Park, Fire Stations 17 and 18. The new solar PV and replacement HVAC systems on the Library roof require a portion of the roof to be replaced, and to support the additional solar PV canopies at the Civic Center, a portion of the parking lot will be reconfigured. ANNUAL OPERATING IMPACT: Savings in energy costs MANAGING DEPARTMENT: Public Works r 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $11,129 $49,586 $12,063,943 $146 $88,871 $97,334 $10,615,027 $30,000 $354 $100,000 $146,920 $22,708,970 $500 TOTAL $12,124,804 $10,801,586 $30,000 $22,956,390 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund 2705 — Street Light Dist East Dublin 1999-1 $60,861 $1,436,559 $332,053 $474,302 $30,000 $1,497,420 $836,355 7102 — Eners Im.rov. Lease Bond TOTAL $11,731,890 $8,890,725 $12,124,804 $10,801,586 $30,000 $20,622,615 $22,956,390 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 11 32 Number — GI000 I CIVIC CENTER ELEVATOR MODERNIZATION Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project will provide for the design and construction to upgrade the three existing elevators located within Civic Center. Most elevators are built to provide about 30 to 40 years of service. The modernization process will include upgrading the critical parts of the elevators in order for them to accommodate new technology, have better performance, less energy consumption, and improved safety. This upgrade will also include the replacement of the interior panels and controls within the elevator cars. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 FUTURE 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9600 — E ment $24,960 $100,040 $750,000 $25,000 $900,000 $24,960 $100,040 $750,000 $25,000 $900,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 FUTURE 2026-2027 YEARS TOTALS 6205 — Internal Service Funds - Facilities $900,000 $900,000 TOTAL $900,000 $900,000 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 12 33 Number — GI0002 CIVIC CENTER EXTERIOR SEALING & PAINTING Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project will provide for design and construction for the sealing of the exterior natural stone veneer, concrete masonry block, and replacement of the caulked joints in the architectural metal panels and stonework at Civic Center. The project will also paint the accent trim colors inside City Hall and the exterior surfaces of the building that are not stone or architectural panels. Buildings should be sealed approximately every 10 years and caulking replaced every 30 years to maintain the exterior's appearance and to prevent damage caused by moisture infiltration. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 FUTURE 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements $24,960 $75,040 $500,000 $24,960 $75,040 $500,000 TOTAL $600 000 $600 000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 FUTURE 2026-2027 YEARS TOTALS 6205 — Internal Service Funds - Facilities $600,000 $600,000 TOTAL $600 000 $600 000 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 13 34 Number — GI0122 CIVIC CENTER REHABILITATION Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the planning, design, and construction of various rehabilitation and renovation projects at the Civic Center. Projects may include: renovation of all restrooms, showers, kitchenettes, and the employee break room; modifications to conference rooms; lighting and ceiling replacement; site improvements to the parking lot area and surrounding walkways of the Civic Center; plaza and landscaping improvements; building security evaluation and upgrades; repainting; and Americans with Disabilities Act (ADA) and Code upgrades. Interior repainting in select areas were completed during construction of the Civic Center HVAC and Roof Replacement project, and minor parking lot and walkway improvements are anticipated to be designed and constructed in conjunction with the Cultural Arts Center project. This project also includes the partitioning of three spaces into six on the second floor of Civic Center. Planning for other projects is anticipated to begin in Fiscal Year 2023-24. This project is funded by General Fund Reserves. Other potential funding sources for the building security upgrades may include Federal and State public safety grants. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 FUTURE 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $5,594 $49,586 $30,404 $373,306 $875,000 $10,000 $24,960 $107,880 $550,000 $5,000 $100,000 $100,000 $5,000 $80,140 $611,590 $1,525,000 $20,000 TOTAL $35,998 $1,307,892 $687,840 $205,000 $2,236,730 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 FUTURE 2026-2027 YEARS TOTALS 1101 — General Fund Desi. ation $35,998 $1,307,892 $35,998 $1,307,892 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 14 35 Number — GIO 120 i ICULTURAL ARTS CENTER 1 Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the design and improvements of an approximately 13,000-square-foot Cultural Arts Center on the first floor of the Civic Center, which was formerly occupied by Dublin Police Services. The Parks & Recreation Master Plan identifies a Cultural Arts Center that would serve as a multi -use facility that affords cultural, educational, and social opportunities for the community. The Cultural Arts Center will include: an Art gallery, Black Box theater space; multi -purpose art and music classrooms; a dance studio; and restrooms. The project also provides for the replacement of the heating, ventilation, and air conditioning (HVAC) systems, HVAC controls, roof replacement, major upgrades to the main telecommunication room, and the relocation of the Parks and Community Services Department offices to the second floor of the Cultural Arts Center. Construction began in November 2022 and is anticipated to be completed in mid-2024. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $63,418 $1,060,875 $13 $5,402 $136,527 $1,774,125 $10,543,987 $12,688 $199,945 $2,835,000 $10,544,000 $18,090 9600 — E.ui.ment TOTAL $ 800,000 $1,129,707 $13,267,328 $800,000 $14,397,035 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1101 — General Fund Designation 4100 — Public Facility Fees 6205 — Internal Service Fund — Facilities $6,964,197 $1,129,707 $4,759,493 $1,543,638 $6,964,197 $5,889,200 $1,543,638 TOTAL $1,129,707 $13,267,328 $14,397,035 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 15 36 Number— GI0123 DUBLIN STANDARD PLANS & DETAILS UPDATE Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project will update the City's Standard Plans, Details and Specifications (Standards) utilized by the Public Works Department for design and construction of public improvements within the City's right-of-way and properties. These Standards are necessary for consistency to provide guidance to designers, and to specify the current requirements for public infrastructure to be constructed and maintained by the City. The Standards require periodic update and revision to be aligned with current industry practice, changes in materials and construction methods, as well as to be compliant with local, State, and federal goals and requirements, such as the Storm Water Municipal Regional Permit and accessibility requirements of the ADA. Planning began in early 2023 and the update is anticipated to take 12 to 18 months to complete. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9500 — Miscellaneous $15,392 $124,608 $2,500 $15,392 124,608 $2,500 TOTAL $142,500 $142,500 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 1001 — General Fund $142,500 $142,500 TOTAL $142,500 $142,500 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 16 37 Number - GI0219 ELECTRIC VEHICLE (EV) CHARGING STATIONS Program - GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the design and construction of at least two electric vehicle (EV) charging spaces at The Wave at Emerald Glen Park and the underground infrastructure for future expansion. In future years, the project could provide for design and construction of EV charging spaces at other City facilities. Staff will apply for grant funding for the charging units; agencies typically fund conduits, wiring, and electrical panel upgrades as local/match contribution to grant funding. This project is funded with General Fund reserve designation for Innovation/New Opportunities. Installation of EV charging units at The Wave will be completed by summer 2023. ANNUAL OPERATING IMPACT: $1,500 MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 - Salaries & Benefits 9200 - Contract Services 9400 - Improvements 9200 - Miscellaneous $10,000 $2,620 $7,481 $20,906 $14,135 $426 $426 $15,000 $75,000 $202,410 $27,620 $103,386 $216,545 $853 9600 - E.ui.ment TOTAL $17,907 $174,005 $212,093 $292,410 $174,005 $522,410 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 1101 - General Fund Designation 1001 - General Fund 1001 - Transportation for Clean Air $17,907 $194,093 $18,000 $292,410 $212,000 $292,410 $18,000 TOTAL $17,907 $212,093 $292,410 $522,410 ANNUAL OPERATING IMPACT $1,500 $1,500 $1,500 $1,500 General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 17 38 Number — GI0223 EXTERIOR PAINTING AT VARIOUS CITY FACILITIES Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the design and construction to paint the exterior and make minor repairs at various City facilities. Buildings should be painted approximately every 10 years to maintain the structures' appearance and to prevent damage caused by moisture infiltration. This project will include work at the following locations: Heritage Museum, Saint Raymond's Church, Kolb House, Senior Center, Fire Stations 16, 17, and 18, The Wave, and the Library. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services $29,952 $85,048 $65,000 $29,952 $150,048 9400 — Im.rovements TOTAL $550,000 $55,000 $665,000 $120,000 $605,000 $785,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 6205 — Internal Service Funds - Facilities $665,000 $120,000 $785,000 TOTAL $665,000 $120,000 $785,000 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 18 39 Number— GI0319 FINANCIAL SYSTEM REPLACEMENT Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the replacement of the City's Enterprise Resource Planning (ERP) system and other related technological projects that support the City Council's initiative to "Become a 24/7 City Hall to Enhance Resident and Business Engagement." These include the OpenGov budget and financial transparency software and upgrades to the City's Laserfiche document management software. The City's ERP system serves as the primary software platform for Finance, Human Resources, Public Works, Community Development, and all other core transactions. The current system was implemented in Fiscal Year 2008-09 and has reached the end of its 10-year lifespan. This multi -year ERP replacement project began with the engagement of consultant services to assist with the issuance of Request For Proposals and evaluation of software selections. The selection of software vendor was approved in December 2020, the implementation started in Spring 2021, Finance Module went live on July 1, 2022, and the complete transition is expected for Fiscal Year 2023-24. ANNUAL OPERATING IMPACT: $238,326 at complete transition. MANAGING DEPARTMENT: Administrative Services 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9200 — Contract Services 9500 — Miscellaneous 9600 — Equi.ment $343,966 $655,534 $14 $486 $979,222 $520,779 TOTAL $1,323,202 $1,176,799 $999,500 $500 $1,500,001 $2,500,001 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund 6305 — Internal Service Fund - Equipment $668,202 $1,176,799 $655,000 $1,845,001 $655,000 TOTAL $1,323,202 $1,176.799 $2,500,001 ANNUAL OPERATING IMPACT $238,326 $245,476 $252,840 $265,482 General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 19 40 Number — GIO 117 • IT INFRASTRUCTURE IMPROVEMENT Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project allows for the replacement and upgrade of aging network hardware as well as the implementation of centralized Information Technology management tools that will increase efficiencies in City operations. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Information Services 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $198,610 $123,644 $678 $104,276 $150,000 $302,886 $273,644 $678 9600 — Equi.ment TOTAL $666,391 $989,323 $254,277 $666,391 $1,243,600 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1101 — General Fund Designation 6605 — IT Fund $89,323 $900,000 $4,227 $250,000 $93,600 $1,150,000 TOTAL $989,323 $254,277 $1,243,600 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 20 41 Number — GI0521 LIBRARY TENANT IMPROVEMENTS Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the design and construction of tenant improvements to the Dublin Library, including completion of 5,150 square feet of currently unoccupied space within the library building. The 37,000 square -foot library building was completed in Fiscal Year 2002-03, however only 30,000 square feet was occupied. In Fiscal Year 2016-17, a tenant improvement project was completed which opened an additional 1,850 square feet of space adjacent to the children's area. This project will open the remaining 5,150 square feet of building area for library and community use Improvements may include removal of interior walls and the installation and modification of shelving and fixtures; carpet replacement; and repainting. Planning and preliminary design is anticipated to begin in Fiscal Year 2023-24. ANNUAL OPERATING IMPACT: $8,000 MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $62,510 $292,885 $200,000 $1,460,270 $800,000 $20,000 $62,510 $492,885 $2,260,270 $20,000 TOTAL $1,835,665 $1,000,000 $2,835,665 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 4100 — Public Facility Fees 6205 — Internal Service Fund -Facilities 1001 — General Fund $1,745,665 $90,000 $1,000,000 $1,745,665 $90,000 $1,000,000 TOTAL $1,835,665 $1,000,000 $2,835,665 ANNUAL OPERATING IMPACT $8,000 $8,000 $8,000 General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 21 42 Number — GI0124 i MARQUEE SIGNS Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project will provide for the design and construction to replace the digital signage display components at the Shannon Community Center and the Senior Center, as well as the addition of a double -sided LED marquee sign at Civic Center. Digital signage typically has a service life of approximately 10 years. The project will also standardize the digital signage operating system to allow the signage to be controlled from multiple facilities. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Information Services & Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements $20,072 $74,928 $375,000 $20,072 $74,928 $375,000 9500 — E.ui.ment TOTAL $25,000 495,000 $25,000 $495,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 1001— General Fund $495,000 $495,000 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 22 43 Number — GI0323 MUNICIPAL FIBER Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION This project provides for the planning, design, and construction to improve and extend the existing City Information Technology fiber optic network cabling and infrastructure by laying the foundation for future high speed networking capability and improve existing City facilities' networking speed and reliability by interconnecting City facilities from Civic Center to Heritage Park and Museums, Shannon Community Center, Senior Center, and the Corp Yard. An approximate 13- mile loop is anticipated to connect these facilities. This project will also assist in improving Traffic Operations with faster fiber optic networks that support smart and adaptive traffic software. Additionally, Dublin Police Services' ability and effectiveness in crime prevention will be enhanced with faster connections to the situational awareness cameras, license plate readers, and major intersection video streaming. Lastly, this project will improve Citywide Wi-Fi access, performance, and security. The first phase will be to solicit consultant services to develop a five-year fiber optic master plan and feasibility study, which will include an assessment of the existing City network infrastructure and the required build out. The preliminary planning began in 2022 with identifying the locations citywide of existing infrastructure. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Information Services & Public Works 1 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services $20,800 $119,200 $140,000 $20,800 $119,200 $140,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund $140,000 $140,000 TOTAL $140,000 $140,000 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 23 44 Number — GI022 1 RESILIENCY AND DISASTER PREPAREDNESS IMPROVEMENTS Program — GENERAL IMPROVEMENTS PROJECT DESCRIPTION Beginning in the end of December 2022 through the first few weeks of 2023, Dublin and most of California experienced damage due to a series of rain fall events that were declared a major disaster in Alameda County by the President on January 17, 2023. The City experienced damage at various sites, including street rights -of -way, parks and open space, and facilities and buildings. This project will be utilized to provide for the planning, design, environmental permitting, if necessary, and construction to make the repairs at various sites impacted. The following locations and types of repairs have been identified: Dougherty Hills Open Space, Crossridge Road Trailhead — slide repair Dublin Boulevard, west of Silvergate Road — slide repair Mape Memorial Park — Pathway Realignment Shannon Community Center/San Ramon Road — ditch and culvert improvements Various citywide storm drainage facilities repairs, such as trash racks, culverts, ditches, bank stabilization, etc. The City will apply for grant funding through FEMA and CalOES. The clean-up effort has been on -going since the storm events and the planning for the permanent repair is anticipated to begin in Fiscal Year 2023-24. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-20 FUTURE 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements $2,189 $52,000 $223,000 $825,000 $54,189 $223,000 $825,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1001— General Fund $2,189 $1,100,000 $2,189 $1,100,000 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 24 45 Number — GI0423 ROOF REPLACEMENT AT VARIOUS CITY FACILITIES Program — GENERAL IMPROVEMENTS ■ PROJECT DESCRIPTION This project provides for the design and construction of the roof replacement or partial roof replacement at various City facilities. Typically, a roof has a 20-30 year service life depending on the roof type. This project will include work at the following locations: Heritage Museum, Saint Raymond's Church, Senior Center, and Fire Station 16. The project will begin design in 2023 with construction anticipated to begin in spring/summer of 2024. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services $29,952 $75,048 $29,952 $75,048 9400 — Im.rovements TOTAL $500,000 $50,000 $605,000 $50,000 $550,000 $655,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 6205 — Internal Service Funds - Facilities $605,000 $50,000 $605,000 $50,000 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 25 46 Number — GI0523 SITUATIONAL AWARENESS CAMERA PROGRAM Program — GENERAL IMPROVEMENTS ■ PROJECT DESCRIPTION This project will provide for 40 situational awareness cameras at 10 locations to cover known gaps within the major corridors and arteries to maximize observation of Dublin's many entrances and exit points into and out resources that assists in criminal investigations and the apprehension of law violators within the City. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Police Services City. These cameras will strategically be located along of town. These cameras will be valuable technological 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Im.rovements TOTAL $7,072 $44,928 $533,000 $585,000 $7,072 $44,928 $533,000 $585,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 1001 — General Fund $585,000 $585,000 ANNUAL OPERATING IMPACT General Improvements City of Dublin Capital Improvement Program 2022-2027 Update Page 26 47 PUBLIC ART SUMMARY OF PROJECTS PROJECTED TO BE COMPLETED IN FISCAL YEAR 2022-2023 Project Number Project Description Estimated Total Project Cost PA0217 PA0218 PA0419 PA0418 Public Art Don Biddle Community Public Art — Butterfly Knoll Park Public Art - Dublin Sports Grounds Public Art - Sean Diamond Park City of Dublin Capital Improvement Program 2022-2027 Update $680,749 1 $17,560 1 $356,527 1 $54,000 1 Page 27 48 LOCATION MAP PUBLIC ART CIP Number CIP Name CIP Number CIP Name PA0121 Public Art - Camp Parks Sign PA0222 Public Art - Heritage Park PA0123 Public Art - Downtown Dublin Public Art City of Dublin Capital Improvement Program 2022-2027 Update Page 28 49 Number— PA0I2I CAMP PARKS SIGN IProgram — PUBLIC ART PROJECT DESCRIPTION This project includes the restoration and relocation of the historic Camp Parks entrance sign from its current location at approximately 201 Dougherty Road to the new entrance at Camp Parks Boulevard and Dougherty Road. The original sign was constructed by artist/architect Bruce Goff in the 1940s and is eligible for the National Register. Rehabilitation will be in accordance with standards and guidelines per the U.S. Department of the Interior National Park Service. The design process began in winter 2022 and the rehabilitation work is anticipated to be complete in Summer 2024. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Parks & Community Services 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $1,502 $23,948 $15,632 $149,368 $300,000 $10,000 $25,450 $165,000 $300,000 $10,000 TOTAL $17,134 $483,316 $500,450 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 2801 — Public Art Fund $17,134 $483,316 $500,450 TOTAL $17,134 $483,316 $500,450 ANNUAL OPERATING IMPACT Public Art City of Dublin Capital Improvement Program 2022-2027 Update Page 29 50 Number — PA0123 DOWNTOWN DUBLIN Program — PUBLIC ART PROJECT DESCRIPTION This project provides for public art commissions in Downtown Dublin. The planning phase is anticipated to begin in Fiscal Year 2022-23 with a comprehensive review of existing Downtown Dublin planning documents and the Public Art Master Plan. The planning phase will include the development of a guide for public art in the Downtown. Additionally, known locations for public art, including a monumental sculpture at the northwest corner of Dublin Boulevard and Village Parkway will be initiated. This project will be funded by the Public Art Fund. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Parks & Community Services 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $24,960 $75,040 $300,000 $300,000 $300,000 $250,000 $50,000 $200,000 $24,960 $75,040 $1,150,000 $250,000 TOTAL $150,000 $500,000 $300,000 $300,000 $250,000 $1,500,000 FUNDING SOURCE PRIOR YEARS •'1 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 2801 — Public Art Fund $150,000 $500,00 $300,000 $300,000 $250,000 $1,500,000 TOTAL $150,000 $500,000 $300,000 $300,000 $250,000 $1,500,000 ANNUAL OPERATING IMPACT Public Art City of Dublin Capital Improvement Program 2022-2027 Update Page 30 51 Number — PA0222 HERITAGE PARK Program — PUBLIC ART PROJECT DESCRIPTION This project will be located at Dublin Heritage Park and Museums. The project budget is based on the Public Art in -lieu contribution required by the Schaefer Ranch Development Agreement. This project includes a monument piece at the corner of Donlon Way and Dublin Blvd as well as a series of six mini -sculptures located throughout the park. These artworks, approved by City Council in February 2022, will represent Dublin's rich heritage, culture, and diversity. Project planning began in Fiscal Year 2021-22 with project completion anticipated in Summer 2024. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Parks & Community Services 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-202 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $9,700 $100,000 $62,500 $387,500 $29,350 $5,650 $9,700 $100,000 $450,000 $35,000 TOTAL $68 150 $526 550 $594 700 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 2801 — Public Art Fund $68,150 $526,550 TOTAL $68,150 $526,550 ANNUAL OPERATING IMPACT Public Art City of Dublin Capital Improvement Program 2022-2027 Update Page 31 52 PARKS SUMMARY OF PROJECTS PROJECTED TO BE COMPLETED IN FISCAL YEAR 2022-2023 Project Number Project Description Estimated Total Project Cost PK0215 PK0105 PK0518 Dublin Heritage Park Cemetery Improvements Emerald Glen Recreation & Aquatic Complex - Phase 1 Imagine Playground at Dublin Sports Grounds $1,604,000 $45,130,950 $5,099,400 Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 32 53 LOCATION MAP CIP !lumbar CIPHami PK0122 Alamo Creek Park and Assessment District - Fence Replac n ae PK0115 Don Biddle Community Park PK0221 Downtown Dublin Tan n Square Park. PK0662 Dublin Sports Grounds Rehabilitation PK0119 Faltui Staon :5 Park - Phase CIP Numbat PK6422 PK6622 PIC6224 PK6124 Pt:4123 CEP mains PARKS Iron Horse Nature Park and Open space ]adan Ranch Neighborhood Square Kolb Park Renovation Parks Playground Replecenn nt Persimmar Pr, Asphalt Path Rehabilitation CIP Number PK0321 PK0661 PK0421 CIP Nam Restrooms Replacement Sunday School Barn Improvements Wallis Ranch Commuiity Park Parks Ore City of Dublin Capital Improvement Program 2022-2027 Update Page 33 54 Number — PK0122 ALAMO CREEK PARK AND ASSESSMENT DISTRICT — FENCE REPLACEMENT Program — PARKS PROJECT DESCRIPTION This project provides for the design and construction of replacement fencing at Alamo Creek Park and for replacement and repair of fencing within the Dougherty Road Landscape and Lighting District No. 1986-1. Most of the existing tubular steel fencing has reached the end of its service life and needs to be replaced or repaired. The project will include replacement of the tubular steel fencing within Alamo Creek Park. In addition to the park fencing, the existing decorative concrete masonry walls within the park, which include integrated tubular steel fence elements, will be evaluated, repaired as needed, and repainted. The project will also include evaluation and select replacement or repair of the tubular steel fencing that is maintained by the Dougherty Road Landscape and Lighting District No. 1986-1. The subject fencing is located along Fall Creek Road, Wildwood Road, and Willow Creek Drive. Funding for this portion of the project is provided from funding reserves that were collected from District No. 1986-1. Design is complete and construction is anticipated summer 2023. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $2,911 $38,689 $10,021 $43,730 $747,500 $7,149 $41,600 $53,751 $747,500 $7,149 TOTAL $12,932 $837,068 $850,000 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund 2703 — Landscape District — Dougherty 1986-1 $3,233 $446,767 $9,699 $390,301 $450,000 $400,000 TOTAL $12,932 $837,068 $850,000 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 34 55 Number — PKO 115 DON BIDDLE COMMUNITY PARK Program — PARKS PROJECT DESCRIPTION This project provides for the design and construction of a 30-acre community park in the Boulevard Development within the Dublin Crossing Specific Plan. The park is located between Dublin Boulevard, Scarlett Drive, Horizon Parkway, and Columbus Street and will be built by the Boulevard Developer. The conceptual plan was approved by the City Council on January 9, 2018. The plan includes tennis courts, basketball courts, a picnic and barbeque area, a great lawn (multi -use lawn area), playgrounds, parent paddock, community garden, and other amenities. On October 2, 2018, City Council provided direction to use $600,000 of Community Benefit Funds for the inclusion of a specimen tree and upgraded playground equipment in the park design. Construction was substantially completed in late summer 2022 and a park opening ceremony was held on September 24, 2022. The project is anticipated to be completed in late spring of 2023. In accordance with the Dublin Crossing Development Agreement, the Developer is responsible for project costs up to $12,857,142. The City is responsible for reimbursing the Developer for project costs that exceed that amount. City funding will come from Public Facility Fee Funds. ANNUAL OPERATING IMPACT: $660,000 (at completion) MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous TOTAL $137,172 $382,731 $613,661 $2,318,500 $3,766,591 $15,562,129 $1,705,466 $337,755 $6,222,890 $18,601,115 $519,903 $2,932,161 $19,328,720 $2,043,221 $24,824,005 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 FUTURE 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1101 — General Fund Designation 4100 — Public Facilities Fees 9999 — Developer Built $1,424,807 $4,798,083 $675,193 $5,068,780 $12,857,142 $2,100,000 $9,866,863 $12,857,142 TOTAL $6,222,890 $18,601,115 $24,824,005 ANNUAL OPERATING IMPACT $660,000 $660,000 $660,000 $660,000 Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 35 56 Number — PK0221 DOWNTOWN DUBLIN TOWN SQUARE PARK Program — PARKS PROJECT DESCRIPTION This project provides for the planning of a new Town Square, in accordance with the main principles of the Downtown Dublin Preferred Vision, which was approved by the City Council on November 5, 2019. The Town Square is a one -acre park and plaza that will serve as Downtown Dublin's gathering place, which may include a market promenade, outdoor dining, and event space, and will be located one block north of Dublin Boulevard in the Dublin Place shopping center along the proposed extension of Golden Gate Drive. The planning phase is anticipated to begin in 2023. Possible funding sources are development impact fees, community facilities district or other assessment district. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9300 — Land/Right of Way 9400 — Improvements $27,205 $4,680 $4,680 $75,000 $110,000 $550,000 $2,400,000 $1,440,000 $146,565 $625,000 $2,400,000 $1,440,000 TOTAL $102,205 $4,680 $4,680 $4,500,000 $4,611,565 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund 4100 — Public Facili Fees $102,205 $4,680 $4,680 $4,500,000 $111,565 $4,500,000 TOTAL $102,205 $4,680 $4,680 $4,500,000 $4,611,565 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 36 57 Number — PK0002 DUBLIN SPORTS GROUNDS REHABILITATION di Program — PARKS PROJECT DESCRIPTION This project will provide for the design and construction to renovate Baseball Fields 2 and 3 at the Dublin Sports Grounds. The improvements will include dugout covers/shelter, fence repairs, reconfiguration of Field 3 dugouts and bullpen openings out onto the field, and the replacement of the score booth at Field 2. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS FUTURE 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Im.rovements TOTAL $24,960 $24,960 $125,040 $150,000 $575,040 $600,000 $49,920 $125,040 $575,040 $750,000 FUNDING SOURCE PRIOR YEARS FUTURE 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 6205 — Internal Service Fund — Facilities $150,000 $600,000 TOTAL $150,000 $600,000 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 37 58 Number — PKO 119 FALLON SPORTS PARK — PHASE 3 Program — PARKS PROJECT DESCRIPTION Fallon Sports Park is a 60-acre community park bordered by Fallon Road, Central Parkway, Lockhart Street and Gleason Drive. Phases 1 and 2 of the park have been completed and Phase 3 represents the final phase of park development. The Phase 3 project provides for the design and construction of the remaining 14 acres of Fallon Sports Park, referred to as the Upper Terrace. On December 17, 2019, City Council approved the concept design that includes a cricket field, two ballfields, sand volleyball courts and multi -sport batting cages. On September 2022 the City Council authorized the use of construction contingency to install perimeter fencing/netting at the cricket field. Construction was substantially completed in late summer 2022 and a park opening ceremony was on October 22, 2022. The project is anticipated to be completed in spring/summer 2023. ANNUAL OPERATING IMPACT: $500,000 MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $148,685 $901,000 $6,853,679 $24,738 $21,333 $1,093,112 $1,380,091 $175,362 $170,018 $1,994,112 $8,233,770 $200,100 TOTAL $7,928,102 $2,669,898 $10,598,000 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1101 — General Fund Designation 4100 — Public Facility Fees TOTAL $100,000 $7,928,102 $2,569,898 $7,928,102 $100,000 $10,498,000 $2,669,898 $10,598,000 ANNUAL OPERATING IMPACT $500,000 $500,000 $500,000 $500,000 Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 38 59 Number — PK0422 IRON HORSE NATURE PARK AND OPEN SPACE Program — PARKS PROJECT DESCRIPTION This project provides for the planning, design, and construction of 12.13 acres of a nature park and open space adjacent to the Iron Horse Trail, from the Dublin/San Ramon city limit to the confluence of Alamo and South San Ramon Creeks, that may be developed in partnership with Zone 7 Water Agency. The park size could increase to over 20 acres of usable parkland when combined with adjacent Zone 7 Water Agency property. The park will be designed in accordance with the Iron Horse Nature Park and Open Space Master Plan, which was approved by City Council on October 1, 2013. The City has already acquired the 12.13 acres and the balance of the parkland would be accessible through an easement and operational agreement with Zone 7 Water Agency. The City will continue to pursue the acquisition of the Alameda County portion of the Iron Horse Trail corridor to add to the City's portion of the parkland. Planning and design for Phase 1 began in Fiscal Year 2021-22 and construction of the first phase is anticipated to begin in summer 2023. The phase I improvements will provide a trail connection to Stagecoach Park and the installation of a shade structure over a picnic area. In addition to the Public Facility Fee, possible funding sources are additional statewide grants or federal grants for projects that provide non -motorized infrastructure and enhancements that promote new or alternate access to parks, waterways, outdoor recreational pursuits, and forested or other natural environments to encourage health -related active transportation and opportunities for residents and trail users to reconnect with nature, such as Active Transportation Program grants or Proposition 68. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $1,096 $173,704 $181,315 $848,685 $2,294,000 $110,500 $52,000 $610,000 $384,100 $255,000 $52,000 $196,505 $6,229,595 $255,000 $278,800 $1,836,505 $8,907,695 $620,500 TOTAL $182,411 $3,426,889 $1,301,100 $6,733,100 $11,643,500 Parks sV City of Dublin Capital Improvement Program 2022-2027 Update Page 39 60 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 4100 — Public Facilities Fee 2403 — State Park Grant 9998 — Unidentified 1001 — General Fund $182,411 $1,132,889 $1,251,100 $4,514,600 $2,294,000 $50,000 $2,218,500 $7,081,000 $2,294,000 $2,218,500 $50,000 TOTAL $182,411 $3,426,889 $1,301,100 $6,733,100 $11,643,500 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 40 61 Number — PK0322 JORDAN RANCH NEIGHBORHOOD SQUARE Program — PARKS PROJECT DESCRIPTION This project provides for the planning, design, and construction of a 2.0-acre neighborhood square in the Jordan Ranch Development. The neighborhood square will be designed in accordance with the Neighborhood Square Standards contained in the Parks and Recreation Master Plan. The planning phase begin in Fiscal Year 2021-22 and the conceptual plan was approved by City Council on December 6, 2022. The detailed design of the park will continue through Fiscal Year 2022- 23 with construction anticipated to begin in Fiscal Year 2023-24. ANNUAL OPERATING IMPACT: $57,000 MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 FUTURE 026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $6,244 $100,934 $10,400 $11,684 $447,756 $27,50 $920,874 $990,875 $282,680 $117,578 $486,940 $1,911,749 $282,680 TOTAL $17,928 $1,752,244 $1,028,775 $2,798,947 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 4100 — Public Facility Fees $17,928 $1,752,244 $1,028,775 $2,798,974 TOTAL $17,928 $1,752,244 $1,028,775 $2,798,947 ANNUAL OPERATING IMPACT $57,000 $57,000 Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 41 62 Number — PK0224 KOLB PARK RENOVATION L Program — PARKS PROJECT DESCRIPTION This project will provide for the planning, design, and construction to renovate the 4.86-acre Kolb Park. The improvements will be consistent with the Parks and Recreation Master Plan and may include the replacement of the restroom building, play equipment, site furnishings, picnic areas, drinking fountains, tot lot fencing, parcourse equipment stations, signage, refresh the shade structure, relevel the existing paver and DG pathways, and refresh the landscaping. Staff will look for opportunities to incorporate Green Stormwater Infrastructure within the park as a part of the renovation. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $24,960 $425,040 $24,960 $75,040 $2,300,000 $50,000 $49,920 $500,080 $2,300,000 $50,000 TOTAL $450,000 $2,450,000 $2,900,000 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund $450,000 $2,450,000 $2,900,000 TOTAL $450,000 $2,450,000 $2,900,000 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 42 63 Number — PK0124 i PARKS PLAYGROUND REPLACEMENT Program — PTU PROJECT DESCRIPTION This project provides for the planning, design, and construction of the replacement of playground equipment at various parks. Based on the results of annual inspections and regular maintenance records, all City parks will be evaluated for the need to replace play equipment at the end of their useful life. The first phase will be at Emerald Glen Park (Near Splash Pad Ages 5-12) and Ted Fairfield Park (Ages 2-5 and 5-12). ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 FUTURE 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $118,560 $120,000 $850,000 $21,000 $118,560 $120,000 $850,000 $21,000 TOTAL $1,109,560 $1,109,560 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund $1,109,560 $1,109,560 TOTAL $1,109,560 $1,109,560 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 43 64 Number— PK0123 PERSIMMON DRIVE PEDESTRIAN PATH REHABILITATION Program — PARKS PROJECT DESCRIPTION This project will provide for removal and replacement of approximately 1,250 linear feet of asphalt pathway along Persimmon Drive between Gleason Drive and Central Parkway. The asphalt concrete surface has experienced distress due to soil expansion, the encroachment of tree roots, and some slope creep along the adjacent Tassajara Creek bank. Design began in spring 2023 in conjunction with the Annual Street Resurfacing Project. Construction is anticipated summer/fall 2023. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services $15,080 $29,920 $15,080 $29,920 9400 — Im.rovements TOTAL $150,000 $195,000 $150,000 $195,000 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 2704 — Landscape District Santa Rita 1997-1 $195,000 $195,000 TOTAL $195,000 $195,000 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 44 65 Number — PK0321 RESTROOMS REPLACEMENT I 7 Program — PARKS PROJECT DESCRIPTION This project provides for the planning, design, and construction to replace the existing restrooms at Alamo Creek Park, Mape Memorial Park, and Kolb Park. To bring the restrooms up to current accessibility standards and codes, the existing restroom buildings will be demolished and replaced with pre-engineered restroom buildings. The planning and design phases are anticipated to begin in 2023. The restroom replacement at Kolb Park will be completed with the Kolb Park Renovation Project, PK0224. ANNUAL OPERATING IMPACT: No increase MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $280 $33,100 $59,000 $900,000 $7,620 $33,380 $59,000 $900,000 $7,620 TOTAL $280 $999,720 $1,000,000 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund $280 $999,720 $1,000,000 TOTAL $280 $999,720 $1,000,000 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 45 66 Number — PK000I SUNDAY SCHOOL BARN IMPROVEMENTS 1 i Program — PARKS PROJECT DESCRIPTION This project provides for the design and construction to renovate the existing wood floor inside the Sunday School Barn at Heritage Park. The original wood floors are not adequate for the types and frequency of use that the building is experiencing. The project is intended to preserve the look and historic fabric of the original wood that is believed to be from the late 1800's while ensuring the structural integrity and finish of the floor are adequate for the current and planned uses of the barn. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $24,960 $100,040 $24,960 25,040 $200,000 $10,000 $49,920 $125,080 $200,000 $10,000 TOTAL $125 000 $260 000 $385 000 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund $125,000 $260,000 $385,000 TOTAL $125,000 $260,000 $385,000 ANNUAL OPERATING IMPACT Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 46 67 Number — PK042 I WALLIS RANCH COMMUNITY PARK L Program — PARKS PROJECT DESCRIPTION The Wallis Ranch Community Park consists of three separate parcels totaling 8.85 acres in the Wallis Ranch Development. The project will provide for the design and construction of a community park and will be designed to the Community Park Standards contained in the Parks and Recreation Master Plan. Park amenities include: play area, picnic facilities, turf area, lighted tennis, pickle ball, and basketball facilities, natural area, restrooms, pathways, lighting, dog park, and irrigation and landscaping. Design began in spring 2021. Construction is anticipated to begin in summer 2023. ANNUAL OPERATING IMPACT: $215,000 MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 FUTURE 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $38,308 $170,362 $415,906 $707,664 $6,858,639 $982,443 $4,762 $208,670 $1,123,570 $6,858,639 $987,205 TOTAL $458,976 $8,719,108 $9,178,084 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 4100 — Public Facilities Fee $458,976 $8,719,108 $9,178,084 TOTAL $458,976 $8,719,108 $9,178,084 ANNUAL OPERATING IMPACT $215,000 $215,000 $215,000 Parks City of Dublin Capital Improvement Program 2022-2027 Update Page 47 68 STREETS SUMMARY OF PROJECTS PROJECTED TO BE COMPLETED IN FISCAL YEAR 2022-2023 Project Number Estimated Total Project Description Project Cost ST0122 Local Roadway Safety Plan $137,980 Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 48 69 LOCATION MAP STREETS CIF Nimbi. Mach- Pace Rued PkTcae and Pahsban 1nGrvaenahtr Arno& Sheen PnudeeirgiVedwls brerti.0 O ly Gomm lunument Sons Gtywide Pkpde end hdetrii.. Inwm.en.e.vs(Vern. Vaoetnm) Citywide Sgxl fomunicatanr.Upward, (Minim motions) t tywde Sporn Oman G Mvrn. cub a asI arbor,] bvwmmen ❑.din Street God Network 6uofn Poul•.ehd son- Falhn Rued To North Conons Park:ray O u,ln Einfieven1Paren,,t Mahan Mann Duo In Ranch Stent L. ht Impm.xments (Venous hcatrons) Go deg Sate O. Irxrsec. In, pv.e. at °Alin Rl t. and St. Patna Wky ram-. Szo m. ct 1111:851rGla Streets QP IWm *, [.ZP11am• TORS. Nb:,14nnt Trenwoataben Srxe^•Cbgahas- ChnneaeoVAeteh.anop .nanda ad Sefisp Inwnema•ae Niro. kmaims) 9i0118 Ice. Horse 'hi Bridge At Whin Boulevard ST0122 Lazo. tadwea °Bateau Pim STOMA San Ramon Rood ka..denape llasxetwn SW5kl can Raman Rana Trill bohfinp Si0112 9. Pabukrim Eatenarn Si0119 Twagam Faced Improvements -Monti ddn Ranch Dave To quarry tone &hod ST811b Tmsep ra Rted Realimment And tnderina-Felon Rued To Nsth Crty taint Si411] Traffic Sgnd nd Roadney Saf eT impvxnherb(Tomos locabms) Si0211 'Traffic Sgrap! Art.ammnoiVenohe Ira km) STOW Wive Porknerl Reaorwtrumn City of Dublin Capital Improvement Program 2022-2027 Update Page 49 70 Number — ST0815 AMADOR PLAZA ROAD BICYCLE AND PEDESTRIAN IMPROVEMENTS Program — STREETS PROJECT DESCRIPTION This project provides for the design and construction of pedestrian, bicycle, and vehicular improvements along Amador Plaza Road between Dublin Boulevard and Amador Valley Boulevard. The project is also consistent with the Western Dublin Transportation Impact Fee program. The project has two phases. On December 6, 2016, the City Council accepted the first phase of improvements, which included the installation of two mid -block crosswalks with pedestrian warning lights and construction of a raised concrete median at the southern Safeway/Dublin Place driveway. The second phase will include construction of an exclusive southbound right turn lane on Amador Plaza Road at Dublin Boulevard. Phase 2 design began in mid-2018 and construction will occur following acquisition of the right-of-way for these improvements, which are dependent upon the timing of an adjacent development project at the former Coco's site. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS FUTURE 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9300 — Land/Right of Way 9400 — Improvements 9500 — Miscellaneous $11,344 $190,849 $350,242 $716 $8,072 $37,522 $126,000 $685,620 $3,284 TOTAL $553,151 $860,498 $19,416 $228,371 $126,000 $1,035,862 $4,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 4304 — Western Dublin Transportation Impact Fee $553,151 $860,498 $1,413,649 TOTAL $553,151 $860,498 $1,413,649 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 50 71 Number — STO 117 ANNUAL STREET RESURFACING Program — STREETS PROJECT DESCRIPTION This project provides for the design and construction of a variety of pavement resurfacing treatments, from slurry seal to major rehabilitation and reconstruction of streets and resurfacing of bridge decks. The project also includes installation of new or upgrades of existing ADA curb ramps on roads that are reconstructed or receive an asphalt concrete overlay. Streets are selected for improvements based on the City's Pavement Management System to optimize the pavement condition in relation to available budget. The City owns and maintains approximately 148 centerline miles of streets. The Metropolitan Transportation Commission groups Pavement Condition Index (PCI) ratings into the following categories: 80-100 Very Good -Excellent; 70-79 Good, 60-69 Fair, 50-59 At Risk, 25-49 Poor, and 0-24 Failed. The City of Dublin is rated very good with a three-year moving average PCI of 82. This annual Resurfacing Program is primarily funded by Alameda County Transportation Commission Measure B/BB funds, SB-1, and Gas Tax. This program protects the substantial investment the City has in the public street system. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM 1 ESTIMATED COSTS PRIOR YEARS FUTURE 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous TOTAL Streets $142,884 $48,991 $35,360 $35,360 $35,360 $35,360 $1,484,397 $684,947 $340,000 $340,000 $360,000 $360,000 $7,796,520 $3,023,727 $1,917,401 $1,917,401 $2,170,601 $2,170,601 $9,022 $40,169 $7,120 $7,120 $8,000 $8,000 $9,432,823 $3,797,834 $333,315 $3,569,344 $18,996,251 $79,431 $2,299,881 $2,299,881 $2,573,961 $2,573,961 $22,978,341 City of Dublin Capital Improvement Program 2022-2027 Update Page 51 72 FUNDING SOURCE PRIOR YEARS 2022-2023 FUTURE 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1001— General Fund 2201— State Gas Tax 2204 — Measure B Sales Tax — Local Streets Fund (ACTC) 2205 — Measure B Sales Tax — Bike & Pedestrian Fund (ACTC) 2214 — Measure BB Sales Tax — Local Streets Fund (ACTC) 2215 — Measure BB Sales Tax — Bike & Pedestrian Fund (ACTC) 2216 — Measure B Grants 2220 — Road Maint. & Rehab. Account (RMRA) 2304 — Local Recycling Programs 4309 — Miti.ation Contributions $467,999 $3,456,188 $1,232,833 $600,920 $1,484,999 $300,000 $300,000 $1,806,020 $450,000 $575,000 $450,000 $650,000 $650,000 $304,500 $82,500 $1,374,977 $155,640 $9,432,823 $1,764,661 $4,360 $45,980 $3,797,834 $1,123,961 $2,299,881 $725,920 $800,000 $1,123,961 $2,299,881 $1,123,961 $800,000 $1,123,961 $2,573,961 $2,573,961 $467,999 $7,615,861 $1,784,999 $300,000 $4,581,020 $304,500 $82,500 $7,635,482 $160,000 $45,980 $22,978,341 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 52 73 Number — ST0319 CITY ENTRANCE MONUMENT SIGNS i Program — STREETS PROJECT DESCRIPTION This project provides for the design and construction to install City entrance monument signs and a Downtown gateway sign at the following locations: Village Parkway median at Kimball Avenue (monument), San Ramon Road median at Alcosta Boulevard (monument), Schaefer Ranch Road at Dublin Boulevard (monument), and Tassajara Road north of Fallon Road (monument); and the southeast corner of Dublin Boulevard and San Ramon Road (Downtown gateway). The new signs will conform to the City of Dublin Streetscape Master Plan and the monument signs will match the existing granite monument signs currently installed within the City. Installation of the Downtown gateway signage was completed in spring 2022 and the monument signage is anticipated to start in Fiscal Year 2023-24. Funding for the Downtown gateway sign comes from the General Fund Downtown Public Improvements Reserve. The Streetscape Master Plan also calls for entrance monument signs at Fallon Road at Dublin Boulevard and at Dublin Boulevard at the eastern city limits. Currently there are no medians at these locations on which to install the signs. These two entrance monument signs may be installed on the Dublin Boulevard Extension — Fallon Road to North Canyons Parkway project (ST0216) or when adjacent property develops and installs associated street improvements. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $45,175 $80,000 $350,000 $9,825 $485,000 $45,175 $80,000 $350,000 $9,825 $485,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund 1101 — General Fund Desi. ation $285,000 200,000 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 53 74 Number — ST0517 CITYWIDE BICYCLE AND PEDESTRIAN IMPROVEMENTS Program — STREETS PROJECT DESCRIPTION This project includes planning, design, and construction of improvements to various pedestrian and bicycle facilities throughout the City, including pedestrian/bicycle bridges and annual sidewalk repair. This project includes design and construction of improvements recommended in the Bicycle and Pedestrian Plan, as well as the Safe Routes to School improvements and the Downtown pedestrian crossing improvements on Regional Street. The project includes an update to the ADA Transition Plan. The plan update will include a review of City buildings, parks, and rights -of -way. The ADA Transition Plan update will be funded by General Fund. It is anticipated that the ADA Transition Plan update will be completed in 2023. An update of the Bicycle and Pedestrian Plan was adopted by City Council on January 10, 2023. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $66,995 $64,185 $659,402 $398,948 $1,636,757 $1,145,899 $768 $29,190 $30,160 $222,350 $390,988 $9,730 $30,160 $302,350 $390,988 $9,730 $191,500 $1,583,050 $3,564,632 $49,418 TOTAL $2,363,921 $1,638,223 $653,228 $733,228 $5,388,600 Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 54 75 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1001— General Fund $387,008 $365,992 $105,000 $105,000 2203 — Transportation Development Act $192,683 $17,317 2204 — Measure B Sales Tax - Local Streets Fund (ACTC) $509,900 $100 2205 — Measure B Sales Tax - Bike & Pedestrian Fund (ACTC) $142,900 2214 — Measure BB Sales Tax - Local Streets Fund (ACTC) $911,600 $280,000 $280,000 $280,000 2215 — Measure BB Sales Tax - Bike & Pedestrian Fund (ACTC) $219,830 $113,814 $268,228 $348,228 $726,000 2212 — Vehicle Registration Fee 2217 - Measure BB Grants $135,000 $963,000 $210,000 $510,000 $142,900 $1,751,600 $950,100 $726,000 $135,000 TOTAL $2,363,921 $1,638,223 $653,228 $733,228 $5,388,600 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 55 76 Number — ST0713 Illm CITYWIDE SIGNAL COMMUNICATIONS UPGRADE Program — STREETS PROJECT DESCRIPTION This project provides for the continued upgrades of the traffic signal communications system and includes the replacement of signal controllers, conflict monitors, and battery backup units, as well as managing ongoing signal operations of coordinated corridors. In Fiscal Years 2019-20 and 2020-21, the project further expanded the traffic communication network, connecting traffic signals on Dublin Boulevard, San Ramon Road, Fallon Road and Tassajara Road. The project will provide for the installation of new conduits, removing the existing copper communication cables and installing new fiber optic cables on Dublin Boulevard. The project will also expand the adaptive traffic signal system along key corridors and will connect existing and new public safety infrastructure, such as situational awareness cameras and automated license plate recognition cameras, to the high-speed fiber optic communications system. A project is currently in construction to install a conduit pathway between Civic Center and San Ramon Road to accommodate the future fiber optic upgrade to city infrastructure. The project updated the City of Dublin Travel Demand Forecasting Model to provide traffic flow projections on the arterial and collector roadways as well as analyzed future land use development proposals and transportation network changes in the City. In April 2021, the project resulted in City Council adopting a resolution establishing the California Environmental Quality Act (CEQA) transportation thresholds of significance for Vehicle Miles Traveled (VMT). This project is partially funded with General Fund reserve designation for One Time Initiative - Capital. Potential other funding for this project may include Federal and State grants. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous 9600 — E.ui.ment $38,637 $92,990 $8,320 $8,320 $612,021 $466,060 $135,000 $135,000 $729,509 $2,235,409 $91,720 $131,720 $4,900 $5,120 TOTAL $1,385,067 $2,799,579 $235,040 $275,040 Streets City of Dublin Capital Improvement Program 2022-2027 Update $148,267 $1,348,081 $3,188,358 $4,900 $5,120 $4,694,726 Page 56 77 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1101 - General Fund Designation $79,853 $1,420,147 2201- State Gas Tax $104,000 2204 - Measure B Sales Tax - Local Streets Fund (ACTC) $194,493 $54,147 2207 - TFCA/Transportation for Clean Air $54,426 $91,574 2212 - Vehicle Registration Fee (ACTC) $704,451 $53,335 $35,040 $35,040 2214 - Measure BB Sales Tax - Local Streets Fund (ACTC) 2220 - Road Maint. & Rehab. Account (RMRA) 4301 - Eastern Dublin Transportation Impact Fee 4304 - Western Dublin Transportation Impact Fee 6305 - Internal Service Fund Equipment $200,000 $200,000 $200,000 $36,844 $617,476 $40,000 $198,248 $1,752 $27,278 $171,722 $89,474 $85,426 $1,500,000 $104,000 $248,640 $146,000 $827,866 $600,000 $694,320 $200,000 $199,000 $174,900 TOTAL $1 385 067 $2 799 579 $235 040 $275 040 $4 694 726 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 57 78 Number — STO 124 I CITYWIDE STORM DRAIN IMPROVEMENTS Program — STREETS PROJECT DESCRIPTION This project will provide for the planning, design, maintenance, and construction of various improvements to citywide storm drainage facilities that are not located within public street rights -of -way, such as v-ditches and culverts on City -owned properties or public easements, such as the large G-3 box culvert running parallel to I-580. The first phase of the project will include a storm drainage master plan and/or condition assessment report with recommendations for maintenance or improvements. Future phases will include design and maintenance and/or construction implementing the recommendations from the Master Plan. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9500 — Miscellaneous $4,992 $25,008 $4,992 $4,992 $25,008 $150,000 $2,508 $14,976 $200,016 $2,508 TOTAL $30,000 $30,000 $157,500 $217,500 FUNDING SOURCE PRIOR YEARS 2022-2023 2025-2026 2026-2027 FUTURE YEARS TOTALS 1001 — General Fund TOTAL $30,000 $30,000 $157,500 $217,500 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 58 79 Number — ST0221 ELDOWNTOWN DUBLIN STREET GRID NETWORK Program — STREETS PROJECT DESCRIPTION This project provides for the planning of a new Street Grid Network, in accordance with the main principles of the Downtown Dublin Preferred Vision, which was approved by the City Council on November 5, 2019. The Street Grid Network will introduce new streets that will break down the large block format into smaller, walkable -sized blocks between 350 to 450 feet per side. The proposed extension of Golden Gate Drive north from Dublin Boulevard up to Amador Valley Boulevard will become a new main street with the classic Downtown street grid network within street rights -of -way varying between 60 and 90 feet wide. Street infrastructure may include storm drainage, sewer, water, recycled water, communications, gas, and electric utilities, as well as landscaping and irrigation. The planning phase began in 2020 with the update of the existing City Travel Demand Forecasting Model to provide traffic flow projections on the new roadways, analyze future land use development proposals, and transportation network changes in the Downtown. Staff is currently working on the Retail District Parking Study. Street rights -of -way are anticipated to be dedicated by developers. Possible funding sources are development impact fees, community facilities district or other assessment district. ANNUAL OPERATING IMPACT: To be determined. MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements $4,152 $55,888 $8,990 $8,990 $8,995 $141,005 $200,000 $1,000,000 $20,000,000 $278,020 $1,150,000 $20,000,000 TOTAL $13,147 $196,893 $8,990 $8,990 $21,200,000 $21,428,020 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1001 — General Fund 9998 — Unidentified $13,147 $196,893 $8,990 $8,990 $228,020 $21,200,000 $21,200,000 TOTAL $13,147 $196,893 $8,990 $8,990 $21,200,000 $21,428,020 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 59 80 Number — ST0216 i DUBLIN BOULEVARD EXTENSION — FALLON ROAD TO NORTH CANYONS PARKWAY Program — STREETS PROJECT DESCRIPTION This project provides for the environmental review, preliminary engineering, design and construction of the 1.5 mile extension of Dublin Boulevard from Fallon Road to North Canyons Parkway in Livermore. The extension is planned to have four to six travel lanes, bike lanes, a Class 1 bike/multi-use path, sidewalk, curb and gutter, traffic signals, street lighting, landscaped medians, bus stops, and utilities. The preliminary engineering and Environmental Impact Report (EIR) cost allocation between the City of Dublin and City of Livermore is governed by a Memorandum of Understanding approved by the City Council on April 19, 2016. The project EIR and precise roadway alignment were completed in 2020. The NEPA Environmental Assessment was completed in early 2021 with a Finding of No Significant Impact. Alameda CTC has assumed the role of implementing agency for the final design phase of the project working in cooperation with the cities of Dublin and Livermore. The preliminary engineering level cost estimate for this project is currently at $153.6 million, which includes all project mitigation costs and indirect impacts mitigation and is anticipated to be divided among the City of Dublin and the City of Livermore based on street length in each jurisdiction. It is expected that the City of Dublin share will be approximately $126.1 million, and the City of Livermore share will be $27.5 million. The unincorporated Alameda County's costs will be shared between the City of Dublin and City of Livermore with the final cost allocation to each jurisdiction to be defined by a Cooperative Agreement. The $11.2 million identified as "Other" is from Tri-Valley Transportation Development Fee. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works ESTIMATED COSTS 9100 — Salaries & Benefits 9200 — Contract Services 9300 — Land/Right of Way 9400 — Improvements 9500 — Miscellaneous TOTAL Streets «' 2022-2027 CAPITAL IMPROVEMENT PROGRAM PRIOR YEARS 2022-2023 2023-2024 $69,827 $255,683 $99,944 $1,141,532 $15,852,380 $3,950 $23,515 $1,215,309 $16,101,578 $24,552,389 $24,652,333 2024-2025 FUTURE 2025-2026 2026-2027 YEARS City of Dublin Capital Improvement Program 2022-2027 Update TOTALS $200,000 $595,454 $9,549,891 $26,543,803 $24,552,389 $74,472,415 $74,472,415 $27,465 $84,222,306 $126,191,526 Page 60 81 PRIOR FUNDING SOURCE YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1001— General Fund 1101 — General Fund Designation 2217 — Measure BB Grants 2220 - Road Maint. & Rehab. Account (RMRA) 4301 — Eastern Dublin Transportation Impact Fee 4302 — Eastern Dublin Transportation Impact Fee 9997 — Other 9998 — Unidentified TOTAL $123,000 $7,167,382 $13,742,559 $6,257,441 $439,824 $172,703 $67,302 $602,782 $431,133 $1,737,585 $11,227,510 $1,215,309 $16,101,578 $24,652,333 $84,222,306 $84,222,306 $7,290,382 $20,000,000 $439,824 $240,004 $1,033,914 $1,737,585 $11,227,510 $84,222,306 $126,191,526 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 61 82 Number — STO 120 DUBLIN BOULEVARD PAVEMENT REHABILITATION Program — STREETS PROJECT DESCRIPTION This project provides for pavement rehabilitation of Dublin Boulevard between Scarlett Drive and Hacienda Drive. Rehabilitation included removal and replacement of existing failed pavement, resurfacing with new asphalt concrete, and installation of new pavement striping. The project also included installation of new curb ramps or upgrade of existing curb ramps to comply with Americans with Disabilities Act (ADA) standards. On April 4, 2017, the City Council authorized the filing of an application to the Metropolitan Transportation Commission (MTC) for federal funding through the One Bay Area Grant Local Streets and Roads (OBAG-LSR) program. In November 2017, MTC approved OBAG-LSR funding of $661,000 for the project. The OBAG-LSR funding requires 11.47% local funding, which is provided by Measure B Local Streets and Roads funds. This project represents the OBAG-LSR funded portions on the improvements along Dublin Boulevard. The balance of the improvements will be constructed in conjunction with that year's Annual Street Resurfacing Project, CIP No. ST0117. This project will protect the substantial investment the City has in the public street system. The project is anticipated to be completed in spring 2023. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9400 — Improvements $737,000 $737,000 TOTAL $737,000 $737,000 FUNDING SOURCE PRIOR YEARS 2022-2023 FUTURE 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 2202 — Federal Transportation Grant 2204 — Measure B Sales Tax - Local Streets Fund (ACTC) TOTAL $661,000 $76,000 $737,000 $661,000 $76,000 $737,000 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 62 83 Number — ST0417 DUBLIN RANCH STREETLIGHT IMPROVEMENTS 1 Program — STREETS PROJECT DESCRIPTION This project provides for the design and repainting of decorative streetlight poles. Repainting of the streetlight poles protects its integrity and improves aesthetics in the surrounding neighborhood. This project is funded by revenue collected through District assessments. The conversion of approximately 1,626 existing streetlights into energy efficient LED in the Dublin Ranch Street Light Assessment District (1999-1) is now included within the Citywide Energy Improvements Project, CIP No. GI0121. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9500 — Miscellaneous $6,555 $6,980 $61,987 $3,640 $6,760 $4,820 $420 $6,760 $34,820 $420 $27,055 $101,627 $4,480 TOTAL $6,555 $72,607 $12,000 $42,000 $133,162 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 2705 — Streetlight District East Dublin 1991-1 $6,555 $72,607 $12,000 $42,000 $133,162 TOTAL $6,555 $72,607 $12,000 $42,000 $133,162 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 63 84 Number — ST0423 GOLDEN GATE DRIVE INTERSECTION IMPROVEMENTS - DUBLIN BLVD AND ST. PATRICK WAY Program — STREETS PROJECT DESCRIPTION This project provides for the design and construction of improvements at the intersections of Dublin Boulevard at Golden Gate Drive and St. Patrick Way at Golden Gate Drive. This is a Western Dublin Transportation Impact Fee Program project designed to relieve congestion, reduce greenhouse gases, and is an Active Transportation Solution. The project is identified in the Downtown Dublin Specific Plan and the Bicycle and Pedestrian Plan. The improvements may include a new traffic signal at the intersection of St. Patrick Way and Golden Gate Drive; traffic signal modifications at the intersection of Dublin Boulevard at Golden Gate Drive; conversion of signal interconnection from copper to fiber optic; signage, striping and markings; necessary utility, pavement, curb, gutter, ADA curb ramps, and sidewalk modifications or adjustments. Design is anticipated to begin in Fiscal Year 2023-24. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements $11,440 $22,880 $8,320 $10,000 $91,000 $99,000 $709,000 $42,640 $200,000 $709,000 TOTAL $21 440 $113 880 $816 320 $951 640 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 4304 — Western Dublin Transportation Impact Fee $21,440 $113,880 $816,320 $951,640 TOTAL $21,440 $113,880 $816,320 $951,640 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 64 85 Number — STO 12I i GREEN STORMWATER INFRASTRUCTURE 1 Program — STREETS PROJECT DESCRIPTION This project provides for the planning, design, and construction of various citywide projects that will improve water quality and provide other environmental benefits in accordance with the Green Stormwater Infrastructure (GSI) Plan, which was approved by the City Council on June 18, 2019. The GSI Plan and associated implementing projects, as well as trash load reduction requirements, are mandated by the Municipal Regional Stormwater Permit (MRP). Projects include: stormwater full trash capture device installation throughout the City, and construction of GSI along the Iron Horse Trail corridor, south of Amador Valley Boulevard. GSI planning and planning for the installation of trash capture devices began in Fiscal Year 2021-22. The installation of the trash capture devices is anticipated in Fiscal Year 2023-24. Construction of GSI along the Iron Horse Trail corridor, south of Amador Valley Boulevard, is anticipated in 2024. This project is funded by a General Fund Reserve set aside for this purpose. The City and Alameda CTC entered into a Cooperative Agreement on February 7, 2023 to partner on the design and environmental permitting phase for a bio-retention and hydromodification management facility along the Iron Horse Trail corridor, south of Amador Valley Boulevard, that satisfies a portion of the City's GSI requirement and Alameda CTC's project, SR84 Expressway Widening and SR84/I-680 Interchange Improvements. Alameda CTC's share of the costs is 75% of the total, which will be reimbursed to the City after expenditure. Both agencies will enter into a subsequent agreement for the construction phase. The "Other" funding is from Alameda County Transportation Commission. ANNUAL OPERATING IMPACT: To be determined. Alameda CTC will enter into a long-term maintenance agreement with the City for the GSI along the Iron Horse Trail corridor, south of Amador Valley Boulevard, to account for the on -going maintenance costs of the portion of the facility that satisfies their project. MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $301 $96,039 $611,365 $235,688 $1,433,670 $900,000 $12,000 $96,340 $847,053 $2,333,670 $12,000 TOTAL $301 $2,153,074 $1,135,688 $3,289,063 Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 65 86 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 1101 — General Fund Designation 9997 — Other $301 $2,153,074 $1,135,688 $2,153,375 $1,135,688 TOTAL $301 $2,153,074 $1,135,688 $3,289,063 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 66 87 Number — ST05 19 INTELLIGENT TRANSPORTATION SYSTEM UPGRADE - CONNECTED/AUTONOMOUS VEHICLE AND SAFETY IMPROVEMENTS Program — STREETS PROJECT DESCRIPTION This project provides for improvements to the City's transportation system using emerging technologies, such as support for connected and autonomous vehicles, and is a collaborative effort between the City of Dublin, Livermore Amador Valley Transportation Authority (LAVTA), and the Metropolitan Transportation Commission (MTC). System improvements will be completed both by the City. The funding source for the MTC/LAVTA led work is shown as "Other" because project costs will be funded directly by MTC. Transportation system improvements will include Connected Vehicle Software that will integrate with the City's central traffic management system to broadcast real- time traffic signal information to transit vehicles and other motorists; Shared Autonomous Vehicle (SAV) Communications that will provide for the integration of SAV with the City's traffic signal controllers. The project will also evaluate vulnerable road user protection systems at three to four signalized intersections on Dublin Boulevard in the vicinity of the Dublin/Pleasanton BART station to see if it can effectively detect pedestrians and bicyclists in or near the intersections. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements $25,142 $41,265 $19,351 $10,518 $21,103 $682,503 $35,660 $62,368 $701,854 TOTAL $85 757 $714 125 $799 882 Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 67 88 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 2201 — State Gas Tax 2212 — Vehicle Registration Fee (ACTC) 2217 — Measure BB Grants 9997 — Other $11,895 $213,105 $59,525 $51,675 $14,338 $64,344 $385,000 TOTAL $85,757 $714,125 $225,000 $111,200 $78,682 $385,000 $799,882 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 68 89 Number — STO 118 IRON HORSE TRAIL BRIDGE AT DUBLIN BOULEVARD ■ Program — STREETS PROJECT DESCRIPTION This project provides for the planning, design, and construction of the Iron Horse Trail bridge for bicycles and pedestrians over Dublin Boulevard. The project will construct a 230-foot clear span truss arch bridge consistent with the Iron Horse Trail Feasibility Study and preliminary bridge design, approved by the City Council on November 7, 2017. The bridge will provide safer and easier trail access, including access to and from the Dublin -Pleasanton BART station. The Alameda County Transportation Commission (ACTC) approved an allocation of $1,294,000 of Measure BB discretionary funds in Fiscal Year 2017-18 for the bridge design and environmental clearance. On June 17, 2019, ACTC approved additional funding in the amount of $4,751,000 of Measure BB and $856,419 of Transportation for Clean Air funds for the construction phase of the project. The project will also receive funding of $1,000,000 for construction from a Developer contribution from the Boulevard Project. Fall of 2020, BART approved $1,500,000 of Measure RR Safe Routes to BART Grant for the construction phase of the project. Construction of the project was awarded by the City Council on March 1, 2022 and is anticipated to be completed in fall 2023. The $600,000 identified as "Other" is from the Tri-Valley Transportation Development Fee. ANNUAL OPERATING IMPACT: $100,000 MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous TOTAL Streets $124,389 $1,352,570 $1,014,640 $5,358 $31,071 $1,066,970 $10,402,339 $7,102 $2,496,956 $11,507,483 $155,460 $2,419,540 $11,416,979 $12,460 $14,004,439 City of Dublin Capital Improvement Program 2022-2027 Update Page 69 90 FUNDING SOURCE PRIOR YEARS 2022-2023 FUTURE 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 2201— State Gas Tax 2204 — Measure B Sales Tax — Local Streets Fund (ACTC) 2205 — Measure B Sales Tax — Bike & Pedestrian Fund (ACTC) 2207 — TFCA/Transportation for Clean Air 2214 — Measure BB Sales Tax — Local Streets Fund (ACTC) 2215 — Measure BB Sales Tax — Bike & Pedestrian Fund (ACTC) 2217 — Measure BB Grants 2218 — Measure RR Safe Routes to BART 2220 — Road Maint. & Rehab. Account (RMRA) 4301 — Eastern Dublin Transportation Impact Fee 4401 — Dublin Crossing Fund 9997 — Other $12,325 $832,715 $62,521 $525,459 $54,594 $345,406 $685,288 $171,131 $400,000 $300,000 $1,097,504 $4,947,496 $121,242 $1,378,758 $263,482 $706,518 $500,000 $200,000 $800,000 $600,000 $845,040 $587,980 $400,000 $856,419 $400,000 $300,000 $6,045,000 $1,500,000 $970,000 $500,000 $1,000,000 $600,000 TOTAL $2,496,956 $11,507,483 $14,004,439 ANNUAL OPERATING IMPACT $100,000 $100,000 $100,000 $100,000 Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 70 91 Number — ST0218 SAN RAMON ROAD LANDSCAPE RENOVATION Program — STREETS PROJECT DESCRIPTION This project provides for design and construction to renovate the landscaping along San Ramon Road between Silvergate Drive and Alcosta Boulevard. Proposed renovation includes the removal of failing plants, soil amendment, and installation of new plants, with an emphasis on Bay Friendly and water conserving plant species. Much of the existing landscaping in this area was installed between 1993 and 1995, and some of the planting has reached the end of its life expectancy. The project has been delayed due to prior years' droughts and due to other adjacent projects, such as installation of a recycled water irrigation main by Dublin San Ramon Services District. The project design could commence in 2023 and construction is anticipated the following summer. However, this project may be delayed if severe drought restrictions are imposed to achieve water conservation limits. Potential funding for Bay Friendly landscaping may be available from Measure D. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $405 $12,459 $19,000 $206,201 $1,000 $12,864 $19,000 $206,201 $1,000 TOTAL $405 $238,660 $239,065 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 1001 — General Fund $405 $238,660 $239,065 TOTAL $405 $238,660 $239,065 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 71 92 Number — ST0514 i SAN RAMON ROAD TRAIL LIGHTING ■ Program — STREETS PROJECT DESCRIPTION This project provides for the design and construction of improvements to the trail light fixtures between Silvergate Drive and Alcosta Boulevard. In prior years, the project included installation of tree root barriers and repair of portions of the asphalt concrete trail. Other CIP Projects (ST0514 - Storm Drain Bypass San Ramon Road, ST0117 - Annual Street Resurfacing, and ST0517 - Citywide Bicycle and Pedestrian Improvements) replaced the existing asphalt trail surface. The trail lighting improvement portion of the project was completed in early 2022. The remaining pole painting portion of the project will be completed in conjunction with the Dublin Ranch Street Light Improvements, CIP No. ST0417. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $20,098 $1,280 $25,026 $6,116 $119,891 $450 $600 $21,378 $31,142 $119,891 $1,050 TOTAL $165,465 $7,996 $173,461 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 1001 — General Fund $165,465 $7,996 $173,461 TOTAL $165,465 $7,996 $173,461 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 72 93 Number — ST0222 ST. PATRICK WAY EXTENSION Program — STREETS PROJECT DESCRIPTION This project provides for the design and construction of the final segment of St. Patrick Way from west of Golden Gate Drive to Regional Street. This is a Western Dublin Transportation Impact Fee Program project which will relieve congestion, reduce greenhouse gases, and is an Active Transportation Solution. The project is identified in the General Plan, Downtown Dublin Specific Plan, and the Bicycle and Pedestrian Plan. Prior segments of St. Patrick Way were constructed by Caltrans in 1998 and Connelly Station in 2014. The developer of the St. Patrick Way, Avalon Bay project entered into an agreement with the City on June 18, 2018, which required dedication of right-of-way and construction of improvements to complete the St. Patrick Way Extension. The developer is responsible for all project costs to acquire right-of-way, design, and construction in exchange for credit toward Western Dublin Transportation Impact Fees. Construction began in 2021 and is anticipated to be completed at the end of 2024. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9400 — Improvements $3,742,556 $3,742,556 TOTAL $3 742 556 $3 742 556 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9999 — Develo.er Built ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 73 94 Number — STO 119 i TASSAJARA ROAD IMPROVEMENTS - NORTH DUBLIN RANCH DRIVE TO QUARRY LANE SCHOOL I Program — STREETS PROJECT DESCRIPTION This project provides for design and construction to complete the street improvements on Tassajara Road, from North Dublin Ranch Drive to Quarry Lane School. The scope of this project was previously included as part of Fiscal Years 2016-19 Capital Improvement Program project, ST0116 - Tassajara Road Realignment & Widening, which included the design and construction of Tassajara Road from North Dublin Ranch Drive to Dublin's northern limit. In Fiscal Year 2018-19, the scope of ST0116 was revised to only include the segment of Tassajara Road north of Fallon Road. The project will improve Tassajara Road to a four -lane arterial standard, with bike lanes, sidewalks, landscaped median, stormwater treatment areas, and other associated street improvements. Portions of the existing roadway have been improved by adjacent development projects and this project will complete the street improvements implementing the General Plan and the Complete Streets Policy. This roadway segment is a project within the Eastern Dublin Transportation Impact Fee program. Preliminary engineering and environmental documentation were completed as part of ST0116. Design of the project began in early 2020. Construction is anticipated to start in Fiscal Year 2023-24; however, it is dependent upon utility relocation, right-of-way acquisition, and permitting by regulatory agencies. The $1,450,000 identified as "Other" is from Tri-Valley Transportation Development Fee. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9300 — Land/Right of Way 9400 — Improvements 9500 — Miscellaneous $26,570 $109,470 $414,250 $1,755,410 $50,596 $385,704 $9,840,000 $500,000 $227 $417,773 $136,040 $2,169,660 $436,300 $10,340,000 $418,000 TOTAL $491,643 $12,508,357 $500,000 $13,500,000 Streets it City of Dublin Capital Improvement Program 2022-2027 Update Page 74 95 FUNDING SOURCE PRIOR YEARS 2022-2023 FUTURE 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 2201— State Gas Tax 4301 — Eastern Dublin Transportation Impact Fee 4305 — Traffic Impact Fee — Dougherty Valley 4306 — Tri-Valley Transportation Development Fee 9997 — Other $1,201,980 $112 $3,347,908 $500,000 $1,500,000 $491,351 $5,008,469 $1,450,000 $1,201,980 $3,848,020 $1,500,000 $5,500,000 $1,450,000 TOTAL $491,643 $12,508,357 $500,000 $13,500,000 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 75 96 Number — STO 116 TASSAJARA ROAD REALIGNMENT AND WIDENING - FALLON ROAD TO NORTH CITY LIMIT Program — STREETS PROJECT DESCRIPTION The project provides for the planning and preliminary engineering to define a new roadway alignment, design cross-section, right-of-way, and environmental clearance for Tassajara Road between North Dublin Ranch Drive and the City and Contra Costa County limits. The project also provides for the design and construction of a realigned Tassajara Road from Fallon Road to the northern city limit, which will be coordinated with Contra Costa County. Planning and preliminary engineering cost will be split in accordance with the Memorandum of Understanding, which was approved on September 16, 2014. Costs for the design and construction will be agreed upon and split proportionally with the work within each jurisdiction. The City and Contra Costa County executed a JEPA on September 23, 2020 for Contra Costa County to lead the project design, which started in January 2021. The design and construction of the southerly Tassajara Road segment is included in another Capital Improvement Program project, Tassajara Road Improvements - North Dublin Ranch Drive to Quarry Lane School (ST0119). This project will widen Tassajara Road to a four -lane arterial standard with bike lanes, sidewalks, landscaped median, stormwater treatment areas, and other associated street improvements. Segments of the existing roadway have been improved by adjacent development projects. This project will complete the street improvements and realign the remaining segments of the existing roadway to improve safety and achieve better circulation while adhering to the Complete Streets Policy. The roadway segment is a project within both the Tri-Valley Transportation Council Strategic Expenditure Plan (Project B-8) and the Eastern Dublin Transportation Impact Fee Program. The $1,000,000 in "Other" funding is from Tri-Valley Transportation Development Fee. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works ESTIMATED COSTS 9100 — Salaries & Benefits 9200 — Contract Services 9300 — Land/Right of Way 9400 — Improvements 9500 — Miscellaneous PRIOR YEARS 2022-2027 CAPITAL IMPROVEMENT PROGRAM 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 $79,244 $226,234 $284,736 $1,639,414 $1,980,000 $8,072,476 $489,641 $5,672 FUTURE YEARS TOTALS $305,478 $1,924,149 $1,980,000 $8,072,476 $495,313 TOTAL $369,651 $12,407,765 $12,777,416 Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 76 97 FUNDING SOURCE PRIOR YEARS 2022-2023 FUTURE 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 2201 — State Gas Tax 2220 — Road Maint. & Rehab. Account (RMRA) 4301 — Eastern Dublin Transportation Impact Fee $200,000 $142,066 $549,993 $200,374 $5,808,365 4303 — Traffic Impact Fee — Category 3 $27,211 $382,052 4305 — Traffic Impact Fee — Dougherty Valley $3,964,338 4306 — Tri-Valley Transportation Development Fee $503,017 9997 — Other $1,000,000 $200,000 $692,059 $6,008,739 $409,263 $3,964,338 $503,017 $1,000,000 TOTAL $369,651 $12,407,765 $12,777,416 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 77 98 Number — STO 123 TRAFFIC SIGNAL AND ROADWAY SAFETY IMPROVEMENTS ■ Program — STREETS PROJECT DESCRIPTION This project will provide for feasibility, design, and construction and modification of traffic signals and roadway safety improvements at locations prioritized and recommended by Local Roadway Safety Plan (LRSP), which was approved in January 2023. Improvements include upgrading the signal equipment such as traffic signal poles/mast arms, vehicle and pedestrian signal heads, signal controllers, cabinet upgrades, streetlighting/safety lighting improvements, signal phasing and timing changes, signing and striping improvements, and other alternatives identified in the LRSP toolbox and under systemic and site recommendations. The project will also provide for evaluating the design and installation of protected intersection elements. Planning is anticipated to begin in Fiscal Year 2023-24. ANNUAL OPERATING IMPACT: To be determined MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services $10,400 $10,400 $49,600 $99,600 TOTAL $60,000 $110,000 $20,800 $149,200 $170,000 FUNDING SOURCE PRIOR YEARS 2022-2023 2023-2024 2024-2025 FUTURE 2025-2026 2026-2027 YEARS TOTALS 2214 — Measure B Sales Tax — Local Streets Fund (ACTC) 2215 — Measure BB Sales Tax — Bike & Pedestrian (ACTC) $30,000 $55,000 $30,000 $55,000 $85,000 $85,000 TOTAL $60,000 $110,000 $170,000 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 78 99 Number — ST0223 TRAFFIC SIGNAL RE-LAMPING 1 Program — STREET PROJECT DESCRIPTION This project provides for the replacement of the traffic signal and pedestrian signal LED lamps at approximately 78 signalized intersections. The City currently has 98 traffic signals, many of which were installed in 2008, and the LED lamps are reaching the end of their useful life, which is typically eight to ten years. The City has replaced 20 signalized intersection lamps through on -going maintenance efforts. New LED lamps will ensure proper visibility of vehicle and pedestrian signal heads, which is critical for maintaining safe traffic flow. Design is anticipated to begin in Fiscal Year 2023-24. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements $4,160 $35,000 $259,380 $4,160 $35,000 $174,380 $4,160 $130,840 $12,480 $70,000 $564,600 TOTAL $298 540 $213 540 $135 000 $647 080 FUNDING SOURCE PRIOR YEARS 2022-2023 FUTURE 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 2201— State Gas Tax 2212 — Vehicle Registration Fee (ACTC) 2214 — Measure BB Sales Tax — Local Streets Fund (ACTC) 2215 — Measure BB Sales Tax — Bike & Ped Fund (ACTC) $118,540 $58,540 $130,000 $130,000 $50,000 $25,000 $60,000 $50,000 $25,000 $237,080 $260,000 $50,000 $100,000 TOTAL $298,540 $213,540 $135,000 $647,080 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 79 100 Number — ST0323 VILLAGE PARKWAY RECONSTRUCTION mi Program — STREET PROJECT DESCRIPTION This project provides for the planning, design, and construction of the replacement of the existing streetscape elements on Village Parkway between Amador Valley Boulevard and the northern city limit (approximately 6,000 linear feet). The project will transform the segment of Village Parkway between Amador Valley Boulevard and Kimball Avenue to a pedestrian and bicycle friendly roadway, which will incorporate complete streets elements such as median islands, bulbouts, decorative or high visibility crosswalks, and street furniture. The work may include the reconstruction of the median island; reconstruction of the roadway base immediately adjacent to the median island; reconstruction necessary for sidewalks improvements, ADA upgrades to curb ramps, curb, and gutter, necessary utility work; landscaping; stormwater improvements; and new pavement for the roadway. The first item of work, which began in Fall 2022, consists of preliminary level planning and environmental assessment and the evaluation of potential outside funding sources to provide for the current funding shortfall. ANNUAL OPERATING IMPACT: To be determined. MANAGING DEPARTMENT: Public Works 2020-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 9100 — Salaries & Benefits 9200 — Contract Services 9400 — Improvements 9500 — Miscellaneous $45,032 $254,968 $49,920 $250,000 $1,000,080 $64,480 $89,440 $1,000,000 $510,560 $10,000,000 $ 5,000,000 $85,520 $248,872 $3,015,608 $15,000,000 $85,520 TOTAL $300,000 $250,000 $1,050,000 $11,150,000 $5,600,000 $18,350,000 FUNDING SOURCE PRIOR FUTURE YEARS 2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 YEARS TOTALS 1101 — General Fund Designation 2201 — State Gas Tax 2214 — Measure BB Sales Tax — Local Streets Fund 9998 — Unidentified $300,000 $250,000 $1,000,000 $8,450,000 $50,000 $250,000 $100,000 $250,000 $200,000 $2,200,000 $5,300,000 TOTAL $300,000 $250,000 $1,050,000 $11,150,000 $5,600,000 $10,000,000 $400,000 $450,000 $7,500,000 $18,350,000 ANNUAL OPERATING IMPACT Streets City of Dublin Capital Improvement Program 2022-2027 Update Page 80 101 Future Projects FUTURE PROJECTS City of Dublin Capital Improvement Program 2022-2027 Update Page 81 102 LOCATION MAP FUTURE PROJECTS CIP Number CIP Name P-01 Dublin Sports Grounds - Phase 5 Renovation P-02 Croak Neighborhood Park West P-03 Croak Neighborhood Park East P-04 Emerald Glen Recreation and Aquatic Complex Phase 2 1 CIP Number CIP Name 5-01 City Entrance Sign Modifications S-02 Eastern Dublin Transportation Impact Fee (Various locations) S-03 Western Dublin Transportation Impact Fee (Various locations) Future Projects City of Dublin Capital Improvement Program 2022-2027 Update Page 82 103 Number — P-03 CROAK NEIGHBORHOOD PARK EAST Program — FUTURE PROJECTS PROJECT DESCRIPTION This project provides for the design and construction of a 5.5-acre neighborhood park to serve new development. The park will be designed in accordance with the Neighborhood Park Standards contained in the Parks and Recreation Master Plan. Based on development projections, it is anticipated that design and construction will occur beyond the CIP time frame and will occur at or after development of the project area. ESTIMATED COSTS: $4,390,000 MANAGING DEPARTMENT: Public Works Number — P-02 CROAK NEIGHBORHOOD PARK WEST 1 Program — FUTURE PROJECTS PROJECT DESCRIPTION This project provides for the design and construction of a 5.0-acre neighborhood park to serve new development. The park will be designed in accordance with the Neighborhood Park Standards contained in the Parks and Recreation Master Plan. Based on development projections, it is anticipated that design and construction will occur beyond the current CIP time frame and will occur at or after development of the project area. ESTIMATED COSTS: $3,995,000 MANAGING DEPARTMENT: Public Works Future Projects City of Dublin Capital Improvement Program 2022-2027 Update Page 83 104 Number — P-0 I DUBLIN SPORTS GROUNDS — PHASE 5 RENOVATION Program — FUTURE PROJECTS PROTECT DESCRIPTION This project provides for the design and construction to renovate a portion of the Dublin Sports Grounds. The Phase 5 project encompasses approximately 180,000 square feet, west of Soccer Field #3, and includes installation of a sand channel drainage system, irrigation upgrades and new turf. ESTIMATED COSTS: $2,400,000 MANAGING DEPARTMENT: Public Works Number — P-04 EMERALD GLEN RECREATION AND AQUATIC COMPLEX - PHASE 2 Program — FUTURE PROJECTS PROJECT DESCRIPTION This project provides for the design and construction of the final phase of the Emerald Glen Recreation and Aquatic Complex (known as The Wave). Amenities may include a community room and gymnasium space. This project may be modified as the City has entered into an agreement for a joint use gymnasium at the Dublin Crossing school site. Until such time, it will remain as a future project. ESTIMATED COSTS: $17,600,000 MANAGING DEPARTMENT: Public Works Future Projects City of Dublin Capital Improvement Program 2022-2027 Update Page 84 105 Number — S-0 I CITY ENTRANCE SIGNS Program — FUTURE PROJECTS PROJECT DESCRIPTION This project provides for the design and construction to install City entrance signs at the following two locations: Fallon Road at Dublin Boulevard and at Dublin Boulevard at the eastern city limit. Currently there are no medians at these locations on which to install the signs. The new signs will conform to the City of Dublin Streetscape Master Plan and will match the existing granite monument signs currently installed within the City. ESTIMATED COSTS: $200,000 MANAGING DEPARTMENT: Public Works Number — S-02 EASTERN DUBLIN TRANSPORTATION IMPACT FEE Program — FUTURE PROJECTS PROJECT DESCRIPTION This project provides for the design and construction of 15 projects being partially funded by the Eastern Dublin Transportation Impact Fee (EDTIF) program. The City Council established the EDTIF program on January 9, 1995 and adopted the most recent update on December 21, 2021. This project does not include completed EDTIF projects, current projects that are individual CIP projects, or current projects to be constructed by developers. EDTIF projects within the five-year capital improvement program are: ST0116 Tassajara Road Realignment & Widening; ST0119 Tassajara Road Improvements - North Dublin Ranch Drive to Quarry Lane School; and ST0216 Dublin Boulevard Extension. ESTIMATED COSTS: $61,750,000 MANAGING DEPARTMENT: Public Works Future Projects City of Dublin Capital Improvement Program 2022-2027 Update Page 85 106 Number — S-03 WESTERN DUBLIN TRANSPORTATION IMPACT FEE Program — FUTURE PROJECTS PROJECT DESCRIPTION This project provides for the design and construction of eight projects being partially funded by the Western Dublin Transportation Impact Fee (WDTIF) program. The City Council adopted an update to the WDTIF on September 6, 2016. The WDTIF program includes a total of nine projects, however the following three projects are within the five-year capital improvement program: ST0815 - Amador Plaza Road Bicycle and Pedestrian Improvements, ST0222 - St. Patrick Way Extension, and ST0423 - Golden Gate Drive Intersection Improvements - Dublin Blvd and St. Patrick Way. ESTIMATED COSTS: $8,750,000 MANAGING DEPARTMENT: Public Works Future Projects City of Dublin Capital Improvement Program 2022-2027 Update Page 86 107 2022-2027 Capital Improvement Program - Project Status Report January 9, 2024 Vt DUBLIN CALIFORNIA 108 2022-2027 Capital Improvement Program CATEGORY 2022-23 2023-24 2024-25 2025-26 2026-27 Five -Year General Improvements Public Art Parks Streets 1 uOTAL $32,504,973 $1,445,860 $37,591,938 $70,743,887 $2,696,840 $ 500,000 $3,894,115 $30,214,580 $1,705,000 $ 300,000 $9,462,780 $5,225,459 $o $300,000 S860,000 $13, 888,961 $0 $250,000 $0 $8,331,461 $36,906,813 $2,795,860 $51,808,833 $128,404,348 $142,286,658 $37,305,535 $16,693,239 $15,048,961 $8,581,461 $219,915,854 General 17% Streets 58% Public Art 1% Parks 24% WM DUBLIN CALIFORNIA Genera Improvements PROJECT NAME 2022-23 2023-24 2024-25 2025-26 2026-27 Five -Year Audio Visual System Upgrade Citywide Energy Improvements Civic Center HVAC and Roof Replacement Civic Center Elevator Modernization Civic Center Exterior Sealing & Painting Civic Center Rehabilitation Cultural Arts Center Dublin Standard Plans and Details Update Electric Vehicle (EV) Charging Stations Exterior Painting at Various City Facilities Financial System Replacement IT Infrastructure Improvements Library Tenant Improvements Maintenance Yard Facility Improvements Marquee Signs Municipal Fiber Public Safety Complex - Police Services Building Resiliency and Disaster Preparedness Impr. Roof Replacement at Various City Facilities Situational Awareness Camera Program $ 157,923 $ 314,000 $ 10,801,586 $ 30,000 $ 111,620 $ 900,000 $ 600,000 $ 1,307,892 $ 687,840 $ 205,000 $ 13,267,328 $ 142,500 $ 212,093 $ 665,000 S 120,000 $ 1,176,799 $ 254,277 $ 1,835,665 $ 1,000,000 $ 55,089 $ 495,000 $ 140,000 $ 87,201 $ 1,100,000 $ 605,000 $ 50,000 $ 585,000 $ 471,923 $ 10,831,586 $ 111,620 $ 900,000 $ 600,000 $ 2,200,732 $ 13,267,328 $ 142,500 $ 212,093 $ 785,000 $ 1,176,799 $ 254,277 $ 2,835,665 $ 55,089 $ 495,000 $ 140,000 $ 87,201 $ 1,100,000 $ 655,000 $ 585,000 TOTAL $32,504,973 $2,696,840 $1,705,000 $0 $0 $36,906,613 DUBLIN CALIFORNIA 110 Genera Improvements • Projects Not Started • Projects In Design • Projects In Construction • Projects In Closeout/Warranty • Total 0 9 5 4 18 R DUBLIN CALIFORNIA 111 Dub in Arts Center CALIFORNIA Citywide Energy Im 3rovements CALIFORNIA PROJECT NAME Camp Parks Sign Dorn Biddle Community Park Downtown Dublin Heritage Park Butterfly Knoll Park Dublin Sports Grounds Sean Diamond Park Public Art 2022-23 2023-24 2024-25 2025-26 2026-27 Five -Year $ 483,316 $ 266,114 $ 150,000 $ 526,550 $ 4,104 $ 6,263 $ 9,513 $ 500,000 $ 483,316 $ 266,114 S 300,000 S 300,000 S 250,000 $ 1,500, 000 $ 526,550 $ 4,104 $ 6,263 $ 9,513 TOTAL $1,445,860 $500,000 $300,000 $300,000 $250,000 $2,795,860 DUBLIN CALIFORNIA Pub icArt • Projects Not Started • Projects In Design • Projects In Construction • Projects In Closeout/Warranty • Total 0 2 4 7 R DUBLIN CALIFORNIA 115 DUBLIN CALIFORNIA Pub ic Art NO FlREAAMS CAMERAS OP LIOVQR ALLOWED I t....;,•; 116 Par<s PROJECT NAME 2022-23 023-24 2024-25 2025-26 2026-27 Five -Year Alamo Ck. Park & Ass. Dist, - Fence Rep. Don Biddle Community Park Downtown Dublin To •vn Square Park Dublin Heritage Park Cemetery Impr. Dublin Sports Grounds Rehabilitation Emerald Glen Recreation & Aquatic Complex Fallon Sports Park - Phase 3 Imagine Playground at Dublin Sports Grounds Iron Horse Nature Park and Open Space Jordan Ranch Neighborhood Square Kolb Park Renovation Parks Playground Replacement Persimmon Drive Asphalt Path Rehabilitation Restrooms Replacement Sunday School Barn Improvements Wallis Ranch Community Park $ 837,068 $ 18,601,115 $ 102,205 $ $ 21,748 $ 218,123 $ 2,669,898 $ 48,820 $ 3,426,889 $ 1,752,244 $ 195,000 $ 999,720 $ 8,719,108 4,680 $ 4,680 $ 150,000 $ 600,000 $ 1,301,100 $ 6,733,100 $ 1,028,775 $ 450,000 $ 2,450,000 $ 1,109,560 125,000 $ 260,000 $ 837,068 $ 18,601,115 $ 111,565 $ 21,748 $ 750,000 $ 218,123 $ 2,669,898 $ 48,820 $ 11,461,089 $ 2,781,019 $ 2,900,000 $ 1,109,560 $ 195,000 $ 999,720 $ 385,000 $ 8,719,108 TOTAL $37,591,938 $3,894,115 $9,462,780 $860,000 $0 $51,808,833 DUBLIN CALIFORNIA Par<s • Projects Not Started 2 PK0124 Parks Playground Replacement PK0224 Kolb Park Renovation • Projects In Design 5 • Projects In Construction 3 • Projects In Closeout/Warranty 4 • Total I 4 Jordan Ranch Neigiboriood Square • � mar fr • RAGKS' CENTRAL PA 'FITNESS STATION+. . 1SERVABLE COVERED fi PICNIC ARE&. BBO • • FOREST WITH NATIVE UNO ER STORY 4- f SLIDE AMPHITHEATER FITNESS STATION PANDORA WAY • a. • POLLIHI GARDEN SHADE CAW GROVE MULTI USE SPORTS COURT • + ICNIC APtA 'FITNESSATATION DUBLIN CALIFORNIA 119 Wal is Ranci Community Park -11 120 Iron Horse Trail Nature Parkand Open Space CITY LIMITS KEY HAP DUDLIII HIGH SCHOOL OUTDOOR EDUCATION IRON HORSE TRAIL STAGECOACH PARK \ • • • • RXISTING CREW DUBLIN HIGH SCHOOL STAGECOACH PARK EXISTING CREEK SHADE STRUCTURES FUTURE TRAIL IRON HORSE TRAIL �i DUBLIN CALIFORNIA Streets Project Name 2022-23 2023-24 2024-25 2025-26 2026-27 Five -Year Arnador Plaza Road Bicycle and Ped. Imp. Annual Street Resurfacing City Entrance Monument Signs Citywide Bicycle and Pedestrian Improvements $ 1,638,223 $ Citywide Signal Communications Upgrade $ 2,799,579 $ Citywide Storm Drain Improvements $ Downtown Dublin Street Grid Network $ 196,893 $ Dublin Boulevard Extension - Fallon Road to North Canyons Parkway $ 16,101,578 Dublin Boulevard Pavement Rehabilitation $ 737,000 Dublin Ranch Street Light Improvements $ 72,607 Golden Gate Drive Intersection Improvements at Dublin Boulevard and St. Patrick Way $ 21,440 $ (Green Stormwater Infrastructure $ 2,153,074 $ Intelligent Transportation System Upgrade - Connected/Autonomous Vehicle and Safety Improvements $ 714,125 $ 860,498 $ 3,797,834 $ $ 485,000 2,299,881 $ 2,299,881 $ 653,228 $ 235,040 $ 30,000 8,990 $ $ 24,652,333 733,228 275,040 $ 8,990 $ 12,000 $ 42,000 113,880 $ 1,135,688 816,320 2,573,961 $ 2,573,961 $ 860,498, 13,545,518 485,000 $ 3,024,679 $ 3,309,659 30,000 $ 157,500 $ 217,500 $ 214,873 $ 40,753,911 $ 737,000 $ 126,607 $ 951,640 $ 3,288,762 $ 714,125 DUBLIN CALIFORNIA 122 Streets (cont.1 Project Name 2022-23 2023-24 Iron Horse Trail Bridge at Dublin Boulevard Local Road Safety Plan San Ramon Road Landscape Renovation San Ramon Road Trail Lighting St. Patrick Way Extension Tassajara Road Improvements - North Dublin Ranch to Quarry Lane School Tassajara Road Realignment and Widening - Fallon Road to North City Limit Traffic Signal Roadway Safety Improvements Traffic Signal Re-Lamping Village Parkway Reconstruction $ 11, 507, 483 $ 94,679 $ 238,660 $ 7,996 $ 3,742,556 $ 12,508,357 $ 12,407,765 $ 60,000 $ 298,540 $ 300,000 $ 500,000 $ 110,000 $ 213,540 $ 250,000 $ $ 1,050,000 $ 135,000 11,150,000 S $ 11,507,483 $ 94,679 $ 238,660 $ 7,996 $ 3,742,556 $ 13,008,357 $ 12, 407,765 $ 5,600,000 $ 170,000 647,080 18,350,000 TOTAL $70,743,887 $30,214,580 $5,225,459 $13,888,961 $8,331,461 $128,404,348 DUBLIN CALIFORNIA Streets • Projects Not Started ST0124 Citywide Storm Drain Improvements ST0218 San Ramon Road Landscape Renovation STO 123 Traffic Signal and Roadway Safety Improvements ST0223 Traffic Signal Re-Lamping • Projects In Design • Projects In Construction • Projects In Closeout/Warranty • Total 4 12 2 5 23 Vil age Par<way Reconstruction VILLAGE PARKWAY LOOKING NORTH 100' 3B6FIY OF me" E}BSTINO f WALLFENCE I � • ` Q' 7 11.5' 115' wE$T BIKE I' TRAVEL TRAVEL SIDEWALK LANE LANE LAME E%6TIHS TwAufFENCE 4. IT WEST BIKE BUFFER TRAVEL NNE TRAWL LANE SIDEWALK LANE MEDIAN Em5T1N6 WALI,>FENCE • iiMiiiMME1 ' 1 11 S' 11.5' T A TAAYEL TRAVEL i' SINE EAST LANE LANE LANE SIDEWALK VILLAGE PARKWAY ALTERNATE A I LOOKING NORTH I00' RICMT OF WAY IMMINE 10• NEdhN 1 11- 11' ; BIKE TFAVEL LANE TRAVEL LANE LANE 17 EAST SIDEWALK 1 DUBLIN CALIFORNIA 125 Iron Horse Trai Bridge Iron Horse Trai Bridge CALIFORNIA 127 Annua Street Resurfacing WM DUBLIN 128 CALIFORNIA Dublin Boulevard Pavement Rehabilitation CALIFORNIA Staff Recommendation • Receive the Report.